- RT IQI sensitivity
- Image quality indicator sensitivity is measured by the smallest wire or hole visible; required sensitivity is typically 2% of material thickness, with T-1, T-2, T-3 hole types by thickness range.
- UT near field length
- The near field length N equals D squared divided by four times wavelength; it defines the distance over which the beam is collimated before diverging.
- PT dwell time
- Penetrant dwell time is typically 10 to 15 minutes; developer dwell time is also 10 to 15 minutes; excess penetrant must be removed carefully to avoid over-washing.
- MT field strength
- Magnetic particle inspection requires a field strength of 30 to 60 gauss for the continuous method, verified with a field indicator, and particle concentration of 0.1 to 0.4 mL per 100 mL.
- NDE method selection
- Surface-breaking flaws are detected by PT or MT; volumetric flaws by RT or UT; austenitic welds need UT with dual-element or phased array; thick sections may need Co-60 or linear accelerator RT.
- ASME UW-51 acceptance
- ASME Section VIII Division 1 UW-51 radiographic acceptance rejects any crack, incomplete fusion, or incomplete penetration; rounded indications are limited by size and density charts.
- NDE personnel qualification
- Personnel are qualified per ASNT SNT-TC-1A or CP-189; Level II must be employer-certified; Level III is required for procedure approval and interpretation of results.
- NDE hold points
- Hold points are root pass, back-gouge, and final weld; inspection must be coordinated with welding and QA before closing; rejected results generate a nonconformance report.
- RT film density
- Radiographic film density for X-rays is typically 1.8 to 4.0, and for gamma rays 2.0 to 4.0; density outside this range may require re-shooting.
- UT beam spread
- Beam spread half-angle is given by sine theta equals 1.22 times wavelength divided by transducer diameter; smaller diameter or higher frequency changes spread.
- PT developer application
- Developer is applied as a thin, uniform coat after penetrant removal and drying; it draws penetrant from surface discontinuities to form visible indications.
- MT particle concentration
- Particle concentration in the bath is checked with a centrifuge tube; acceptable range is 0.1 to 0.4 mL per 100 mL of bath for fluorescent particles.
- RT source selection
- X-ray tubes are used for thin sections; gamma sources such as Ir-192 for medium thickness and Co-60 for thick sections; selection depends on thickness and code requirements.
- UT calibration block
- Calibration blocks such as IIW or ASME basic block are used to set velocity, delay, and sensitivity; calibration is verified at start and end of inspection.
- NDE report content
- NDE reports include method, procedure, personnel, equipment, calibration, acceptance criteria, results, and disposition; they must be signed and traceable.
- Visual inspection (VT)
- Visual inspection is the primary method for weld surface condition; it checks for cracks, undercut, overlap, spatter, and dimensional compliance before other NDE.
- Welding procedure qualification
- A PQR per ASME Section IX records essential variables such as process, base metal P-number, filler F-number, position, preheat, and PWHT; changes require requalification.
- Welder performance qualification
- A WPQ per ASME Section IX QW-300 qualifies a welder; essential variables include process, position, backing, and filler; continuity is maintained by a 6-month log.
- Carbon equivalent formula
- CE equals C plus Mn/6 plus (Cr+Mo+V)/5 plus (Ni+Cu)/15; a CE above 0.4 generally requires preheat to avoid cracking.
- PWHT requirements
- Post-weld heat treatment is required for P-1 carbon steel over 32 mm thick; hold at 595 to 690 degrees Celsius for one hour per 25 mm; cooling rate limited below 425 degrees.
- Weld inspection sequence
- Inspection sequence is fit-up, root pass, fill passes, and final weld; visual inspection is performed at each stage; NDE follows final weld and repair requires re-inspection.
- QA documentation package
- The QA package includes WPS, PQR, WPQ, NDE reports, heat treatment charts, material test reports, and nonconformance reports; all must be traceable to the weld.
- Distortion control methods
- Distortion is controlled by balanced welding sequence, back-step, skip welding, pre-setting, and restraint; dimensional checks monitor compliance.
- Code compliance verification
- ASME Section IX covers qualification; Section VIII covers vessels; AWS D1.1 covers structural; API 1104 covers pipelines; verify WPS and PQR alignment before production.
- Preheat purpose
- Preheat slows cooling rate, reduces hydrogen cracking risk, and improves fusion; minimum preheat is specified by code based on thickness and carbon equivalent.
- Essential variables
- Essential variables are conditions that, if changed, require requalification of the WPS or WPQ; examples include process, position, preheat, and PWHT.
- WPS content
- A WPS specifies process, base metal, filler, position, preheat, current, voltage, travel speed, and PWHT; it must be supported by a qualified PQR.
- PQR test coupon
- The PQR test coupon is welded per the proposed WPS and tested by mechanical methods such as tensile, bend, and impact to qualify the procedure.
- Welder continuity log
- A welder's continuity log records that the welder has used the process within a 6-month period; lapse requires requalification.
- Repair welding procedure
- Repair welding follows a qualified WPS; excavated area is inspected before repair; repair is re-inspected by the same or equivalent NDE method.
- Material test report
- The MTR provides chemical and mechanical properties of the base metal and filler; it is checked against specification and traceability requirements.
- Heat treatment chart
- A heat treatment chart records temperature versus time during preheat or PWHT; it verifies compliance with the code-required cycle and is part of the QA record.