Arizona Low Voltage Practice study plan
Arizona Low Voltage Practice · Give each week a clear focus.
8 weeks · About 7 hours per week
General Electrical Knowledge and Ohm's Law & Low Voltage Cabling and Wiring Methods
Solve 30 Ohm's law and power-formula problems (E=IR, P=IE) without notes, including series and parallel resistor combinations
Compute voltage drop for 12 AWG and 18 AWG copper runs at 1 A and 2 A over 100 ft, 250 ft, and 500 ft, and compare results to a 5 percent threshold
Convert between circular mils, AWG sizes, and cross-sectional area, and state the ampacity basis for typical low-voltage conductors
Identify the wiring methods and cable types named in Article 725 Class 2 and Class 3 circuits and match each to one permitted and one prohibited use
Label every conductor in a hand-drawn 24 VDC power distribution sketch (source, OCPD, cable, load) and annotate current, voltage drop, and ampacity
Your checkpoint
A one-page formula and voltage-drop reference sheet plus a scored problem set of 30 worked calculations (target 80 percent correct)
Low Voltage Cabling and Wiring Methods & Grounding, Bonding, and Electrical Protection
Classify ten given cable types by fire-resistance and plenum, riser, or general-purpose rating and state where each may be installed
Explain separation, support, and securing requirements for low-voltage cable in ceilings, walls, and riser shafts in your own words
Describe how to bond and ground a low-voltage system, including grounding electrode conductor sizing and equipment grounding conductor continuity
Distinguish bonding from grounding and give two failure symptoms of each when done incorrectly
Draw a riser diagram showing cable routing, supports, penetrations, and bonding points for a two-floor installation
Your checkpoint
A labeled riser diagram with an accompanying 300-word written justification of cable selection, separation, and bonding choices
Fire Alarm and Life Safety Systems & Grounding, Bonding, and Electrical Protection
Identify the major components of a fire alarm system (initiating devices, notification appliances, FACP, wiring classes) and state the function of each
Differentiate Class A and Class B signaling line circuits and explain how each responds to a single open or ground fault
Explain supervision, end-of-line devices, and why unprotected conductors and ground faults matter in life safety circuits
Sequence the events from alarm initiation through notification, annunciation, and off-premises transmission
List the acceptance-test and documentation steps a technician should expect to witness before system turnover
Your checkpoint
A two-page fire alarm system narrative covering components, circuit classes, supervision, and the alarm sequence, with a labeled block diagram
Security, Access Control, and CCTV Systems & Communications, Data, and Audio/Video Distribution
Compare cabling and connector choices for access control readers, door hardware, and CCTV cameras using distance, bandwidth, and power-delivery criteria
Design a PoE budget for six cameras and two access control panels, summing device draw and comparing to switch capacity
Explain structured cabling hierarchy (work area, horizontal, backbone) and the role of patch panels, cross-connects, and labeling
Describe best practices for separation of communications cable from power conductors and for grounding of shielded and outdoor cable
Produce a device schedule with cable type, run length, power source, and termination for a small mixed system
Your checkpoint
A device and cable schedule for a 6-camera, 2-door system including a completed PoE load calculation
Arizona Licensing Laws, Rules, and Safety & General Electrical Knowledge and Ohm's Law
Summarize the Arizona low-voltage contractor licensing framework, including who must hold a license, qualifying-party responsibilities, and renewal obligations
Outline the rules for advertising, contracts, permits, and supervision of unlicensed workers in Arizona
List the personal protective equipment, lockout/tagout, ladder, and confined-space practices expected on a low-voltage job site
Re-solve ten missed calculation problems from week 1 and write the correct method for each
Draft a pre-job safety and compliance checklist covering hazard assessment, PPE, and license and permit verification
Your checkpoint
A one-page Arizona compliance and jobsite safety checklist plus a corrected set of ten previously missed calculations
Fire Alarm and Life Safety Systems & Security, Access Control, and CCTV Systems
Trace a fault from a non-reporting smoke detector through the loop to the panel and list the diagnostic steps in order
Explain how to verify notification appliance circuit voltage drop and audibility coverage limits
Troubleshoot a non-responding access control reader and a camera that drops off the network, listing likely causes by layer
Describe the documentation and recordkeeping expected for testing, inspection, and service of life safety and security systems
Write a standardized troubleshooting flow for each of three fault scenarios
Your checkpoint
Three written troubleshooting flowcharts, each with at least five ordered diagnostic steps and the expected measurement at each step
Low Voltage Cabling and Wiring Methods & Communications, Data, and Audio/Video Distribution & General Electrical Knowledge and Ohm's Law
Re-derive the voltage-drop and PoE calculations from weeks 1 and 4 without reference material
Match fifteen cable and wiring-method scenarios to the correct permitted installation
Explain the interaction between cable fill, bundling, and heat when many low-voltage cables share a pathway
Practice explaining three code and design decisions aloud as you would to an inspector or client
Complete a 40-question mixed practice set under timed conditions and log every miss by domain
Your checkpoint
A timed 40-question practice score with a domain-by-domain error log identifying the top three weak areas
Arizona Licensing Laws, Rules, and Safety & Fire Alarm and Life Safety Systems & Grounding, Bonding, and Electrical Protection
Review the Arizona licensing rules, safety practices, and life safety content flagged as weak in week 7
Recite the grounding, bonding, and supervision principles from memory and apply them to two new scenarios
Complete a full-length timed practice exam and review every incorrect or guessed answer
Build a final one-page summary sheet of formulas, cable ratings, and compliance points for exam-day reference
Confirm exam logistics, identification requirements, and allowed reference materials for test day
Your checkpoint
A full-length timed practice exam score of at least 80 percent plus a completed one-page final summary sheet
Milestones
Week 2: Can solve Ohm's law and voltage-drop problems cold and correctly classify ten cable types by rating and permitted location
Week 4: Can explain fire alarm circuit classes, supervision, and the alarm sequence, and produce a defensible PoE and cable schedule
Week 6: Can troubleshoot fire alarm, access control, and CCTV faults using written ordered flows and cite Arizona licensing obligations
Week 8: Scores 80 percent or higher on a full-length timed practice exam with no domain below 70 percent