Cross-Connection Control and Backflow Prevention

  • Cross-connection: any actual or potential physical connection between a potable water system and any source of nonpotable fluid or substance.

  • Backsiphonage is caused by negative or sub-atmospheric pressure in the supply; backpressure is caused by downstream pressure exceeding supply pressure.

  • Pollution hazard degrades quality (aesthetic, no health risk); contamination hazard creates a health hazard and requires a higher protection level.

  • Air gap is the only non-mechanical protection; minimum separation is two times the effective opening diameter, never less than 1 inch, and the gap must be above the flood-level rim.

  • An atmospheric vacuum breaker may not be installed under continuous pressure (no downstream shutoff) for more than 12 hours; it has no test cocks and cannot be field-tested.

  • A pressure vacuum breaker must be installed at least 12 inches above the highest downstream outlet; a spill-resistant PVB is required where the device could be flooded.

  • A reduced pressure principle assembly provides protection against both backsiphonage and backpressure and may be installed where backpressure exists; it discharges water from the relief port when a differential of about 2 psi is lost.

  • A double check valve assembly protects against backpressure and backsiphonage only for non-health-hazard (pollution) conditions and is not permitted for contamination hazards.

  • A hose-bibb vacuum breaker must not be under continuous pressure and must not have a shutoff downstream; a dual check is used only as a low-hazard, non-testable device at the meter or appliance.

Quick reference

Backflow Prevention Assembly Testing

  • Differential pressure check: close test cock 2, open high side to upstream and low side to downstream; a passing check holds a differential that does not drop below 1.0 psi (RP relief check) or the manufacturer's specified minimum.

  • RP assembly test sequence: check 1 differential, then check 2 differential, then relief valve opening point; the relief valve must open when the inlet pressure is reduced to a differential of 2.0 psi or more.

  • RP relief valve opening point is confirmed by bleeding the low side until the relief discharges, then noting the pressure differential at which discharge begins (typically 2.0 psi minimum).

  • DC assembly test: record static line pressure, then measure check 1 and check 2 differentials; each check must hold at least 1.0 psi and the device must not leak past either check.

  • PVB test: record line pressure, then measure the air-inlet opening point; the air inlet must open when the differential drops to 1.0 psi or greater.

  • Test gauges must be calibrated at least annually, have a range appropriate to the line pressure, and be connected with the high side to upstream and the low side to downstream of the check being tested.

  • Record on the test report: assembly make, model, size, serial number, location, static pressure, each differential or opening point, pass/fail, tester name, certification number, and date.

  • A failed assembly must be tagged, reported to the water purveyor and property owner, and either repaired by a licensed technician and retested or replaced; a failed device is not left in service.