BCxA Certified Commissioning Professional (CCP) flashcards
BCxA Certified Commissioning Professional (CCP) · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Commissioning Authority (CxA)
- The individual or firm responsible for planning, organizing, and leading the commissioning process, documenting results, and reporting to the Owner. Independence from design and construction contracts preserves objectivity.
- Commissioning Plan
- A living document defining Cx scope, systems, roles, schedule, budget, documentation, and acceptance criteria. It is updated at each project phase to reflect current conditions.
- Total Building Commissioning
- An integrated commissioning approach covering envelope, structural, mechanical, electrical, plumbing, fire protection, and interior systems in one coordinated process rather than isolated system checks.
- Pre-Design Phase Cx
- The earliest Cx phase where the CxA is engaged, scope and budget are established, and OPR development begins before design work proceeds.
- Owner's Project Requirements (OPR)
- A written document detailing the functional requirements and expectations of how the project will be used and operated, including measurable performance criteria, budget, schedule, and environmental goals.
- Basis of Design (BOD)
- The designer's written explanation of assumptions, calculations, and decisions supporting the design, demonstrating traceability to the OPR. It is owned by the design team.
- OPR-BOD Gap Analysis
- A design review comparison identifying OPR requirements not addressed in the BOD, flagged for resolution before construction documents are finalized.
- Measurable Performance Criteria
- Quantitative OPR requirements such as temperature setpoints, ventilation rates, lighting levels, and energy use intensity that become acceptance benchmarks for functional performance testing.
- Design Review Stages
- Commissioning design reviews typically occur at schematic design, design development, and construction documents stages, with a final review before bid and award.
- Pre-Bid Cx Meeting
- A meeting communicating Cx scope, roles, schedule, and documentation requirements to bidders and contractors, reducing later disputes and change orders related to commissioning.
- Commissioned Systems List
- A pre-construction document defining which systems are in Cx scope versus excluded, establishing clear boundaries for testing, documentation, and acceptance responsibilities.
- Design Review Comment Log
- A tracked record of design review comments with responsible party, due date, and resolution status; unresolved items escalate to the Owner for decision.
- Cx Specification
- A contract document, typically in Division 01, defining Cx scope, team roles, contractor responsibilities, submittal requirements, testing procedures, and acceptance criteria.
- CxA Procurement Path
- The CxA is typically procured directly by the Owner rather than through design or construction contracts, preserving independence and objectivity in reporting findings.
- Contractor Cx Responsibilities
- Contract-specified duties including pre-functional checklists, participation in functional tests, TAB, controls verification, deficiency correction, and delivery of O&M and training documentation.
- Retesting Cost Allocation
- Contract provisions assigning responsibility for retesting costs and schedule impacts after deficiency correction, preventing disputes during acceptance.
- Pre-Functional Checklist (PFC)
- A contractor-completed and CxA-verified document confirming equipment is installed per manufacturer requirements and design before functional performance testing begins.
- Installation Verification
- Construction-phase checks of clearances, access, labeling, insulation, seismic restraint, electrical connections, and controls wiring against design and manufacturer requirements.
- TAB Report Review
- CxA review of Testing, Adjusting, and Balancing results to confirm measured air and water flows match design values within specified tolerances before functional testing.
- Point-to-Point Verification
- Confirmation that each sensor, actuator, and output is correctly wired and mapped to the building automation system before control sequence testing proceeds.
- Functional Performance Test (FPT)
- A documented test verifying that systems and components perform interactively according to the OPR, BOD, and contract documents under simulated and actual operating conditions.
- FPT Procedure Contents
- A test document specifying system tested, prerequisites, instrumentation, test steps, expected results, acceptance criteria, and documentation requirements for each functional test.
- Failure Mode Testing
- Simulating equipment failure, power loss, or alarm conditions to verify safety responses, alarms, and sequence-of-operation behavior match the controls narrative.
- Deferred Seasonal Testing
- Testing scheduled when weather-dependent conditions cannot be achieved during initial testing, with results appended to the commissioning record at a later date.
- Issues Log
- A tracked record of each deficiency with ID, description, location, responsible party, severity, due date, status, and resolution evidence, maintained through acceptance.
- Deficiency Severity Categories
- Classification of issues as critical, major, or minor to prioritize correction; critical items affecting life safety or major function must be resolved before substantial completion.
- Certificate of Acceptance
- A document confirming Cx requirements are met or that remaining items are tracked, supporting the Owner's final acceptance and substantial completion decisions.
- Punch List vs. Cx Log
- The punch list addresses cosmetic or minor construction items, while the Cx issues log focuses on performance, functional, and documentation compliance.
- Systems Manual
- A compiled reference including OPR, BOD, as-built drawings, equipment schedules, control sequences, TAB reports, FPT results, warranties, and O&M data for operations.
- Training Verification
- CxA confirmation that contract-specified training occurred, covering topics, audience, duration, format, and documentation such as agendas, attendance, and recordings.
- Cx Final Report
- A handover document summarizing the commissioning process, test results, outstanding items, and recommendations for ongoing commissioning and future retro-commissioning.
- Retro-Commissioning (RCx)
- Applying the commissioning process to existing buildings not previously commissioned, focusing on low-cost operational improvements with typical energy savings of five to fifteen percent.
- Monitoring-Based Commissioning
- A continuous commissioning approach using BAS trend data and analytics to detect faults, prioritize corrective actions, and verify persistence of energy savings over time.