Fachwissen / Technical Subject Knowledge

  • A closed control loop consists of a controller, actuator, plant/process, and sensor with feedback; the manipulated variable u(t) is derived from the error e(t) = setpoint − measured value.

  • PID control law: u(t) = Kp·e(t) + Ki·∫e dt + Kd·de/dt; in parallel form Ki and Kd are independent gains, in standard form the integral time Ti = Kp/Ki and derivative time Td = Kd/Kp.

  • Steady-state error of a proportional controller on a first-order plant is nonzero; an integral term removes offset at the cost of reduced phase margin.

  • A plant pole in the right half-plane makes the open-loop system unstable; stability of the closed loop is judged from the roots of 1 + G(s)H(s) = 0.

  • Nyquist criterion: closed-loop stability requires Z = N + P, where P is open-loop right-half-plane poles and N is the number of clockwise encirclements of −1.

  • Gain margin is the factor by which loop gain can rise before instability; phase margin is the additional phase lag at the gain crossover frequency before the −180° point is reached.

  • First-order step response reaches 63.2 % of final value at one time constant τ; settling to ±2 % takes about 4τ.

  • Sampling theorem: the sample rate must exceed twice the highest signal frequency; the discrete equivalent of an integrator is T·z/(z−1) under backward/forward Euler or Tustin transformation.

Quick reference

Berufspraxis / Professional Practice and Case Handling

  • Case handling sequence: capture the symptom and boundary conditions, reproduce the fault, isolate cause, implement the fix, verify against the specification, and document the outcome.

  • Change control rule: no modification of a running plant without a documented change request, risk assessment, rollback plan, and defined acceptance test.

  • Root-cause analysis distinguishes symptom, immediate cause, and systemic cause; correcting only the symptom leaves the systemic cause active.

  • Fault isolation by bisection: split the signal chain at its midpoint, verify the signal there, and halve the remaining suspect section each iteration.

  • Escalation trigger: escalate when the fault exceeds the technician's authorization, affects safety functions, or when the agreed diagnosis time budget is exhausted.

  • Measurement validity check: verify sensor calibration, lead polarity, and range setting before interpreting an unexpected reading as a process fault.

  • Handover must contain current state, open actions, risks, and the last verified measurement, so the next shift can act without repeating diagnostics.

  • Documentation standard: record date, observer, plant state, measured values with units, instrument used, and conclusion, so the record is reproducible.

Quick reference

Rechtliche Grundlagen / Legal and Regulatory Fundamentals

  • Technical installations require conformity with applicable safety regulations; the operator bears responsibility for safe operation, while the manufacturer bears product-safety responsibility.

  • Personal data processing requires a legal basis: consent, contract, legal obligation, vital interest, public task, or legitimate interest, with purpose limitation and data minimization.

  • Data subjects hold rights to access, rectification, erasure, restriction, portability, and objection; requests must be answered within the statutory deadline.

  • Confidentiality obligations survive termination of the employment or service relationship; disclosure requires authorization or a legal duty.

  • Occupational safety duties: risk assessment, instruction of personnel, provision of protective equipment, and documentation of instruction dates and content.

  • Liability for defective work depends on whether a contract of service (success owed) or contract for services (activity owed) exists; the distinction governs warranty and acceptance.

  • Incident reporting: safety-relevant events must be reported to the responsible authority within the prescribed period and recorded internally regardless of reporting duty.

  • Retention rules: technical records, test reports, and training evidence must be kept for the statutory period and made available to auditors on request.

Quick reference

Methodik und Arbeitsweise / Methodology and Working Approach

  • PDCA cycle: plan the change with a measurable target, do it on a limited scope, check against the target, act by standardizing or reverting.

  • Hypothesis-driven diagnosis: state the hypothesis, predict the observable, test it, and record whether the prediction held; discard hypotheses that fail.

  • Measurement uncertainty: report result ± expanded uncertainty with coverage factor k and state the confidence level; a single reading without uncertainty is not a valid comparison.

  • Design of experiments: vary one factor at a time for screening, use factorial designs when interactions are suspected, and randomize run order to avoid drift bias.

  • FMEA ranks failure modes by risk priority from severity, occurrence, and detection; the highest product is addressed first.

  • Statistical process control: a process is in control when points lie within control limits without runs or trends; control limits are not specification limits.

  • Traceability: every result must be linkable to instrument, calibration status, method version, operator, and timestamp.

  • Peer review rule: independent verification of a critical calculation or safety-relevant setting by a second qualified person before release.

Quick reference

Kommunikation und Beratung / Communication and Client Interaction

  • Active listening technique: paraphrase the client's statement, ask an open question, then confirm the shared understanding before proposing a solution.

  • Feedback rule: describe observable behavior and its effect, not the person; separate observation from interpretation.

  • Advisory structure: situation, options with trade-offs, recommendation with rationale, and the decision the client must make.

  • Informed consent for a technical recommendation requires disclosing the alternatives, the risks of each, and the consequence of doing nothing.

  • Escalating message format: state impact, urgency, what is already done, and what decision is required, in that order.

  • Non-technical audience rule: lead with the consequence for the client, then the mechanism; define each technical term at first use.

  • Conflict handling: separate the factual disagreement from the relationship level, and resolve the factual level with shared data first.

  • Written confirmation: after a verbal agreement, restate scope, deadline, responsibilities, and open points in writing to create a common record.

Quick reference

Qualitäts- und Berufsethik / Quality and Professional Ethics

  • Integrity rule: report data as measured; adjusting, omitting, or selectively presenting results to support a desired conclusion is misconduct.

  • Conflict of interest must be disclosed before advising; a financial or personal interest in the recommended option disqualifies the adviser from deciding alone.

  • Competence boundary: accept only tasks within verified qualification; state the limit and refer to a qualified party when outside it.

  • Safety over schedule: when a safety requirement conflicts with a delivery date, the safety requirement prevails and the conflict is escalated, not resolved silently.

  • Confidentiality and data protection apply to client information even after the engagement ends, unless disclosure is legally required.

  • Independence of testing: the person who performed the work should not be the sole verifier of its acceptance where independence is required.

  • Whistleblowing threshold: a serious risk to safety, health, or law that cannot be resolved internally is reported to the designated body, with documented facts.