Koeltechnicus Cat I study materials
Koeltechnicus Cat I study resources

Koeltechnicus Cat I study plan

Koeltechnicus Cat I · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

F-gas certification of refrigeration technicians (category I)

  • Map the F-gas regulation scope and explain which equipment categories and refrigerant charges fall under category I responsibilities.

  • Define global warming potential and CO2-equivalent, then convert at least five example charges into tonnes CO2e by hand.

  • List the legal obligations of a certified technician: leak checks, record keeping, labelling, and handling of recovered refrigerant.

  • Identify the penalties and enforcement consequences of non-compliance for both technician and operator.

Your checkpoint

A one-page reference sheet of key legal thresholds (charge sizes, CO2e limits, check intervals) plus five worked CO2e conversion examples with correct units.

Week 2

F-gas certification of refrigeration technicians (category I)

  • Explain the environmental impact chain from refrigerant emission to ozone depletion and climate change.

  • Compare ODP and GWP values for the main refrigerant families and justify why a low-GWP choice is not automatically the safest choice.

  • Describe the containment hierarchy: prevention first, then detection, then recovery.

  • Summarise the F-gas phase-down schedule and what it means for service practice on existing equipment.

Your checkpoint

A comparison table of at least eight refrigerants with ODP, GWP, safety group, and typical application, plus a 150-word written justification of one refrigerant substitution decision.

Week 3

F-gas certification of refrigeration technicians (category I)

  • Sequence the full recovery procedure for small self-contained units and for larger split systems.

  • Select recovery equipment and cylinders appropriate to the refrigerant, charge size, and system type.

  • Explain cylinder filling limits, non-return safeguards, and why cylinders must never be overfilled.

  • Describe safe handling, transport, and storage rules for recovered refrigerant containers.

Your checkpoint

A step-by-step recovery checklist covering pre-checks, equipment setup, recovery, cylinder weighing, and documentation, validated against at least three different system scenarios.

Week 4

F-gas certification of refrigeration technicians (category I)

  • Perform leak detection using at least three methods and state the sensitivity and limits of each.

  • Apply the correct leak-check frequency for a given charge size and system type.

  • Describe leak repair obligations, deadlines, and what to record after a repair.

  • Explain the rules for reclaiming, recycling, and destroying recovered refrigerant.

Your checkpoint

A timed practice test on F-gas rules scored at 80 percent or higher, with every wrong answer rewritten as a corrected statement.

Week 5

Refrigeration installation and maintenance practice

  • Trace the vapour-compression cycle and label pressure, temperature, and phase at each of the four main points.

  • Read a pressure-enthalpy diagram to locate superheat, subcooling, and the compression ratio for a given operating condition.

  • Identify the main system components and explain the function of each in the circuit.

  • Interpret common fault symptoms such as high superheat, low subcooling, and abnormal discharge temperature.

Your checkpoint

An annotated hand-drawn refrigeration circuit diagram with measured or given values at each point and a written diagnosis of two fault scenarios.

Week 6

Refrigeration installation and maintenance practice

  • Perform commissioning steps: pressure testing, evacuation to target vacuum, and charging by weight.

  • Explain why evacuation must reach a defined vacuum level and how moisture and non-condensables damage a system.

  • Describe brazing and connection practices that keep the circuit clean and leak-tight.

  • Carry out a leak test on a newly assembled circuit and document the result.

Your checkpoint

A commissioning procedure document for one specific system type, including target vacuum, holding time, charge weight calculation, and a completed test record form.

Week 7

Refrigeration installation and maintenance practice

  • Diagnose electrical and control faults using a systematic measurement sequence.

  • Explain the role of safety devices such as high-pressure switches, low-pressure switches, and thermal protection.

  • Describe maintenance tasks for compressors, condensers, evaporators, and expansion devices and their inspection intervals.

  • Plan a preventive maintenance visit with a prioritised task list and required tools.

Your checkpoint

A preventive maintenance checklist for one plant type with at least 15 verifiable tasks, each with an acceptance criterion and a tool required.

Week 8

F-gas certification of refrigeration technicians (category I) & Refrigeration installation and maintenance practice

  • Integrate legal requirements with practical service steps so that every job ends with correct records and labelling.

  • Solve mixed scenario questions combining leak-check intervals, CO2e conversion, and fault diagnosis.

  • Review all previously missed questions and restate the underlying rule or principle for each.

  • Rehearse the full workflow from job receipt to refrigerant recovery and documentation.

Your checkpoint

A full-length mock exam completed under time pressure, scored, with a personal error log listing each weak area and the corrective action.

Milestones

Week 2: Can explain GWP, CO2e conversion, and the phase-down without notes, and correctly convert five random charge sizes.

Week 4: Scores 80 percent or higher on an F-gas-only practice test and can state every leak-check interval from memory.

Week 6: Produces a complete commissioning procedure from memory and correctly diagnoses two seeded system faults.

Week 8: Passes a timed mixed mock exam at 75 percent or higher with no repeated error from the personal error log.