Administration of Moves, Adds, and Changes

BICSI RCDD · Put your knowledge to work in context.

All case studies

Administration of Moves, Adds, and Changes

A regional insurer has 4,000 outlets across three buildings. The IT team maintains a spreadsheet of outlet locations, but it is three years out of date and does not reflect 600 MACs performed since. The facilities team uses a separate CAD drawing set. A recent audit found that 12% of outlets could not be located within 30 minutes during an incident. The owner wants a single source of truth and has asked for a plan. Budget is limited, and the IT staff has no dedicated documentation role.

1. Propose an approach to establish and maintain accurate records.

Read the worked answer

Start with a physical audit to reconcile outlets, identifiers, and locations against the CAD set, then build a single database keyed by a unique outlet identifier with links to drawings. Assign ownership and define a MAC workflow that requires record updates before work is closed. Use labeling standards so field identification matches records. The goal is a maintained record, not a one-time cleanup; without a workflow, the data will drift again.

2. The owner asks whether to hire a dedicated documentation role or add it to existing staff duties. How do you advise?

Read the worked answer

Present both options with trade-offs. A dedicated role improves consistency but adds cost; embedding the duty in existing staff works only if it is explicitly assigned, time is allocated, and completion is enforced at project closeout. Given the audit finding and the 600-MAC backlog, a temporary audit resource plus a permanent assigned owner with defined responsibilities is a pragmatic middle path. The decision should be documented with the chosen owner and metrics.

3. Define how you would measure whether the new process is working.

Read the worked answer

Track time to locate an outlet during drills or incidents, percentage of MACs with records updated at closeout, audit discrepancy rate, and completeness of the as-built drawing set. Set targets (e.g., locate within 5 minutes, 95% MAC records updated) and review them quarterly. Metrics make the process accountable and reveal drift early.