The Belarus Construction Specialist Attestation (Аттестация специалистов в области строительства) is a professional knowledge assessment for people who take responsibility for construction work in the Republic of Belarus - site managers, engineers, technical supervision staff, estimators, and specialists in structural design, engineering systems, and fire or environmental safety. The certificate demonstrates that a specialist can work within the country's technical regulatory system: legislation and mandatory technical documents, construction organization and management, building structures, materials and technologies, water, heat, gas and ventilation systems, occupational safety, quality control and supervision, cost estimation and pricing, geodesy and engineering surveys, and fire safety and environmental protection. The Belarus Construction Specialist Attestation case studies are 5 cases and about 2,656 words.

1

Attestation of a site engineer and scope of the construction licence

A private Belarusian company has a licence for general contracting of residential buildings up to 5 storeys. It wins a tender for a 4-storey residential block with an attached 1-storey commercial annex and an underground car park for 40 cars.

581 words, about 3 min
2

Choosing a structural scheme for a 9-storey panel building on weak soils

A 9-storey large-panel residential building is planned on a site where the top 4 m is soft loam with a design resistance of about 90 kPa, underlain by dense sand at 6 m. The client wants the cheapest foundation and a construction period of 10 months.

693 words, about 3 min
3

Water supply pressure failure in a 5-storey building

A 5-storey residential building is connected to the city water main at a guaranteed pressure of 0.18 MPa at the connection point. The top floor fixtures are 14 m above the connection.

482 words, about 2 min
4

Acceptance of concealed works before backfilling a foundation

A contractor is ready to backfill the foundation of a warehouse after installing the waterproofing, the drainage, and the foundation reinforcement. The technical supervision engineer is on leave and the contractor wants to proceed to keep the schedule.

439 words, about 2 min
5

Fire safety and environmental control at a site with a temporary fuel store

A construction site for a 12-storey building has a temporary diesel fuel store of 3 m3 in a metal container, a refuelling point for two excavators, and a temporary electrical installation with a distribution board. The site is 25 m from a neighbouring residential building and 8 m from a public footpath.

461 words, about 2 min