- Title 24 publication cycle
- California's building standards are adopted and published on a three-year cycle, with each edition taking effect on January 1 of the following odd-numbered year.
- Certificate of occupancy
- A document issued by the building official confirming a completed structure complies with the approved plans and code, required before the building may be occupied or used.
- Permit expiration rule
- Under CBC Section 105.5, a permit becomes invalid if work does not begin within 12 months and expires if work is suspended for 180 days.
- Type IV mass timber
- The 2021 codes add Types IV-A, IV-B, and IV-C for mass timber, with 3-hour, 2-hour, and 1-hour fire-resistance ratings plus corresponding height and area limits.
- Chapter 11A
- The portion of the California Building Code governing accessibility for covered multifamily dwellings, including dwelling unit features, common areas, and site elements.
- Chapter 11B
- The portion of the California Building Code governing accessibility for public accommodations, commercial facilities, and publicly funded buildings, generally exceeding federal minimums.
- Van-accessible parking ratio
- At least one of every six accessible parking spaces, and never fewer than one, must be van-accessible with an appropriate access aisle.
- CASp inspection
- A review by a Certified Access Specialist that identifies accessibility compliance issues; commercial leases must disclose CASp status under Civil Code Section 1938.
- Alquist-Priolo Act
- A California statute zoning active earthquake faults and prohibiting structures for human occupancy within 50 feet of a mapped fault trace without geologic investigation.
- Seismic Design Category
- A classification from A through F derived from mapped spectral accelerations and Risk Category, governing permitted structural systems and detailing requirements.
- Field Act
- California law requiring DSA plan review and construction observation for K-12 and community college buildings to improve seismic performance and protect occupants.
- Seismic Hazards Mapping Act
- Requires state mapping of liquefaction and landslide zones; projects within a Zone of Required Investigation must include a site-specific geotechnical evaluation.
- Business occupant load factor
- Under CBC Table 1004.5, business occupancy uses 150 gross square feet per occupant for computing egress capacity, plumbing fixtures, and related requirements.
- Dead-end corridor limits
- Corridor dead ends may not exceed 20 feet in nonsprinklered buildings or 50 feet where the building is protected by an automatic sprinkler system.
- Chapter 7A wildfire construction
- California requirements for ignition-resistant construction in Wildland-Urban Interface fire hazard severity zones, covering roofs, vents, walls, decks, and windows.
- NFPA 13R sprinklers
- A residential sprinkler design standard permitted for residential occupancies up to four stories in height, with reduced water supply and coverage demands.
- CALGreen Part 11
- California's green building standards code, containing mandatory statewide measures plus voluntary Tier 1 and Tier 2 reach standards a jurisdiction may adopt.
- Construction waste diversion
- CALGreen requires covered projects to divert at least 65 percent of construction and demolition waste from landfill through recycling and salvage.
- HERS verification
- Third-party field verification and diagnostic testing by a certified rater of specified energy measures such as duct leakage and refrigerant charge.
- Residential PV requirement
- Title 24 Part 6 requires on-site photovoltaic generation on new low-rise residential buildings, with recent editions adding battery storage readiness.
- CEQA lead agency
- The public agency with principal responsibility for approving a project and therefore for preparing or overseeing its environmental review documents.
- Mitigated negative declaration
- An environmental document used when a project's significant effects are reduced to less than significant through revisions or mitigation incorporated before approval.
- SB 743 VMT metric
- California's change replacing level of service with vehicle miles traveled as the basis for analyzing transportation impacts under CEQA.
- Housing element cycle
- The housing element of a general plan must be updated every eight years and demonstrate capacity to meet the jurisdiction's Regional Housing Needs Allocation.
- Preliminary 20-day notice
- A statutory notice generally required before a claimant may record a mechanic's lien or serve a stop payment notice on a private work of improvement.
- Civil Code 2782.8
- Limits indemnity obligations in design professional contracts with public agencies, barring indemnity for a public agency's sole negligence, gross negligence, or willful misconduct.
- Statute of repose
- Code of Civil Procedure Section 337.15 bars latent construction defect claims filed more than ten years after substantial completion of the improvement.
- Construction manager at risk
- A delivery method in which the contractor provides preconstruction services and holds trade contracts, typically committing to a guaranteed maximum price.
- Responsible control
- The standard requiring a licensed architect to directly supervise and be responsible for documents that the architect signs and seals.
- Continuing education hours
- California architects must complete 5 hours of continuing education each year, including at least 2 hours related to accessibility, to renew licensure.
- Architect Registration Examination
- The national licensure exam administered by NCARB, currently organized into six divisions covering practice management through building design and systems.
- Instruments of service ownership
- Absent contract language to the contrary, the architect retains ownership and copyright of drawings and specifications and grants the client a license to use them.