BOABC Plumbing Level I study materials
BOABC Plumbing Level I study resources

BOABC Plumbing Level I cheat sheet

BOABC Plumbing Level I · Keep the key ideas within reach.

Quick reference

Plumbing Code and Regulation

  • Uniform Plumbing Code (UPC) and International Plumbing Code (IPC) are the two model codes most U.S. jurisdictions adopt; local amendments supersede the model text.

  • A permit is required for new water, waste, and vent piping, fixture replacement that alters rough-in, and water heater replacement; minor repairs such as washer replacement do not require one.

  • Potable water supply piping must maintain minimum 12-inch horizontal separation from sewer and drain pipe, and 12 inches above a sewer line when crossing.

  • Water-distribution pipe in a trench must be separated from a building sewer by at least 12 inches horizontally and must cross at least 12 inches above the sewer.

  • A backflow prevention device is required at every connection between potable water and a nonpotable system, including irrigation, boiler feed, and fire-sprinkler lines.

  • Each fixture must be individually protected by a trap; a single trap may serve a set of fixtures only where the code expressly permits it (e.g., a three-compartment sink with a continuous waste).

  • Vent stack must terminate at least 6 inches above the roof surface and at least 10 feet from any operable window, door, or air intake.

  • Water heater temperature-and-pressure relief valve discharge must terminate not more than 6 inches above the floor and not less than 6 inches above grade.

Quick reference

Plumbing Plan Review

  • Verify fixture-unit counts against the fixture-unit table for the building occupancy before approving drain sizing.

  • Check that every fixture is shown with its trap, vent, and cleanout, and that vent distances from the trap weir comply with the adopted code.

  • Confirm slope: 1/4 inch per foot for 2-inch and smaller drains, 1/8 inch per foot for 3-inch and larger drains, unless the code specifies otherwise.

  • Review water-supply sizing using the demand-load method: total fixture units converted to gallons per minute, then compared against pipe capacity at the available pressure.

  • Confirm clearances: 15-inch minimum from centerline of a water closet to a side wall, 30-inch minimum clear width in front of fixtures.

  • Check that cleanouts are shown at the base of each stack, at changes in direction greater than 45 degrees, and at intervals not exceeding 100 feet.

  • Verify that the plan shows the building drain, building sewer, and the point of connection to the public sewer or private disposal system.

  • Confirm that plumbing plans match architectural, structural, and mechanical drawings for penetrations, chases, and equipment locations.

Quick reference

Plumbing Field Inspection and Monitoring

  • Rough-in inspection must occur after all piping is in place but before it is covered or concealed; the inspector verifies slope, support, and venting.

  • Water-supply system test: pressurize to at least the working pressure but not less than 100 psi for a minimum of 15 minutes with no drop in pressure.

  • Drain, waste, and vent test: either a water test with a 10-foot head at the lowest point or an air test at 5 psi for 15 minutes.

  • Building sewer test: water test with a minimum 10-foot head at the upstream end, or an air test at 5 psi.

  • Final inspection verifies fixtures, trim, water heater installation, gas piping, and that all prior corrections are complete.

  • Support spacing: horizontal cast-iron pipe at 5-foot intervals for 2-inch pipe, and 10-foot intervals for 4-inch and larger pipe.

  • Trap seal depth must be 2 to 4 inches; a trap more than 4 inches deep is a defect requiring correction.

  • Inspection records must document date, inspector, findings, and corrective action, and the file is retained per the jurisdiction's record-retention schedule.

Quick reference

Professional Practice

  • An inspector's authority is limited to the adopted code and the permit scope; personal preference is not a basis for a correction notice.

  • Written correction notices must cite the code section, describe the condition, and specify the required action and reinspection process.

  • Field notes and photographs are contemporaneous records; they should be dated, identified by location, and retained with the inspection file.

  • Conflicts of interest include inspecting work by a family member, employer, or business associate; disclosure and reassignment are required.

  • Continuing education and code-update training are professional obligations; the adopted edition changes on a cycle set by the jurisdiction.

  • Communicate findings factually and without speculation about intent; describe the observed condition and the code requirement it violates.

  • When a contractor disputes a finding, the correct path is a written request for interpretation or appeal through the jurisdiction's established procedure.

Quick reference

Ethics and Administration

  • Public officials must avoid the appearance of impropriety as well as actual conflicts; gifts, favors, and outside employment are governed by ethics rules.

  • Ex parte communications about a pending permit or appeal should be documented and disclosed to all parties.

  • Permit fees, inspection scheduling, and enforcement actions must be applied uniformly; selective enforcement is an ethics violation.

  • Records of inspections and permits are public records subject to disclosure law, with limited exceptions for security-sensitive information.

  • An appeal of an inspector's decision typically goes to the board of appeals within a set number of days, often 20 to 30, after the decision.

  • Administrative due process requires notice of the alleged violation, an opportunity to respond, and a written decision.

  • Inspectors must not perform design or contracting work within their jurisdiction; that separation prevents self-review and conflicts.

  • Revocation or suspension of a license or certification follows a defined disciplinary process with notice, hearing, and written findings.

Quick reference

Plumbing Code and Regulation

  • Fixture unit values are assigned by fixture type in the code tables; a water closet is typically 3 or 4 fixture units depending on flush type.

  • A building drain carries waste from the building to the building sewer, which extends from the building to the public sewer or private disposal.

  • Horizontal wet venting requires the vent to be sized and sloped so that the vent remains above the water level in the drain it serves.

  • A cleanout is required at the base of every stack, at the junction of the building drain and building sewer, and at the end of every horizontal drain.

  • Air admittance valves may substitute for vent terminals only where the adopted code permits and the valve is accessible and listed for the use.

  • Gas piping must be tested at not less than 1.5 times the working pressure, with a minimum of 3 psi for a 10-minute test unless the code states otherwise.

  • A water heater must be installed with a temperature-and-pressure relief valve, a discharge pipe, and a pan where leakage would cause damage.

Quick reference

Plumbing Plan Review

  • Check that the plan set includes a plumbing isometric or riser diagram showing stacks, vents, and fixture connections.

  • Verify that the fixture-unit total for each branch, stack, and building drain is shown and matches the sizing table.

  • Confirm that water-supply pipe sizes are shown for each branch and that the developed length and pressure loss are accounted for.

  • Review that the plan shows the location of the water service, meter, backflow preventer, and shutoff valves.

  • Check that the plan identifies the drainage fixture units and the corresponding drain sizes for each horizontal branch.

  • Confirm that the plan shows the vent terminal location relative to windows and air intakes on the roof plan.

  • Verify that the plan includes a schedule of fixtures with the manufacturer, model, and water-consumption rate for each fixture.

Quick reference

Plumbing Field Inspection and Monitoring

  • Rough-in inspection confirms that all piping is installed, supported, and sloped before concealment.

  • Final inspection confirms that fixtures, trim, and appliances are installed and operational.

  • Test records must show the test method, pressure or head, duration, and the result for each system tested.

  • Correction notices must identify the code section and the specific corrective action required.

  • Reinspection is scheduled after the correction is complete and documented by the contractor.

  • Inspection findings should be recorded in the field and entered into the permit record the same day.

  • Photographs taken during inspection should show the condition, the location, and a scale or reference where possible.

  • Stop-work orders are issued when work proceeds without a permit or when a condition presents an immediate hazard.

Quick reference

Professional Practice

  • The inspector's role is to verify code compliance, not to direct the contractor's means or methods of construction.

  • Correction notices must be specific, code-referenced, and written in neutral language.

  • Field records should be contemporaneous and retained according to the jurisdiction's schedule.

  • Conflicts of interest must be disclosed and the inspector reassigned when a personal or financial relationship exists.

  • Continuing education keeps the inspector current with the adopted code edition and local amendments.

  • Disputes are resolved through the jurisdiction's written interpretation and appeal process, not through informal pressure.

  • Communication with contractors and owners should be factual, documented, and consistent across similar situations.

Quick reference

Ethics and Administration

  • Ethics rules prohibit gifts, favors, and outside employment that could influence official decisions.

  • Ex parte communications about a pending permit or appeal must be disclosed to all parties.

  • Enforcement actions must be applied uniformly; selective enforcement is an ethics violation.

  • Inspection and permit records are public records subject to disclosure law with limited exceptions.

  • Appeals of an inspector's decision go to the board of appeals within a set period, often 20 to 30 days.

  • Due process requires notice, an opportunity to respond, and a written decision.

  • Inspectors must not perform design or contracting work within their jurisdiction.

  • License suspension or revocation follows a defined disciplinary process with notice, hearing, and written findings.