Gold Seal Foreperson flashcards
Gold Seal Foreperson · Build recall with a focused review session.
44 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Critical path definition
- The longest duration sequence of dependent activities through a project network. Its total float is zero, so any delay on it shifts project completion by the same number of days.
- Total float formula
- Late start minus early start, or late finish minus early finish. It is the time an activity can slip without delaying the project completion date.
- Cost performance index
- Earned value divided by actual cost. A value below 1.0 means the work performed cost more than budgeted; above 1.0 means under budget at that point.
- Schedule performance index
- Earned value divided by planned value. A value below 1.0 indicates the project is behind the planned schedule progress at the measurement date.
- Estimate at completion by CPI
- Budget at completion divided by the cost performance index. This forecast assumes remaining work continues at the same cost efficiency observed to date.
- Percent plan complete
- Completed commitments divided by total commitments made in the weekly work plan. It measures short-interval planning reliability rather than physical progress alone.
- Labor burden rate
- The percentage added to base wages for payroll taxes, insurance, and benefits, commonly 25 to 40 percent. Burdened rates must be used in all cost comparisons.
- Margin versus markup
- Markup is added to cost as a percentage of cost. Margin is a percentage of selling price, so price equals cost divided by one minus the margin.
- Learning curve effect
- Repetitive operations improve roughly 10 to 20 percent per doubling of units until reaching a plateau. First-unit rates should not be applied to total quantity.
- Fall protection trigger height
- In general construction, fall protection is required at 6 feet or more above a lower level. General industry work uses a 4-foot trigger height.
- Excavation protective system threshold
- Excavations 5 feet or deeper require a protective system such as sloping, shoring, or shielding. A competent person must classify soil and inspect daily.
- Excavation egress distance
- In trenches 4 feet or deeper, a means of egress such as a ladder must be within 25 feet of lateral travel for every worker in the excavation.
- Spoil pile setback
- Excavated material, equipment, and supplies must be kept at least 2 feet back from the edge of an excavation to reduce surcharge and collapse risk.
- Extension ladder slope
- Extension ladders are set at a 4-to-1 ratio, meaning 1 foot of base setback for every 4 feet of working height, with 3 feet extending above the landing.
- Hazard control hierarchy
- Controls ranked from most to least effective: elimination, substitution, engineering controls, administrative controls, and personal protective equipment as the last line of defense.
- Hearing protection threshold
- Hearing protection is required when noise exposure reaches an 8-hour time-weighted average of 85 decibels, with a monitoring and training program in place.
- Lockout tagout verification
- Each worker applies a personal lock, then verifies zero energy by attempting start-up or testing. Only the worker who applied a lock may remove it.
- Guardrail height standard
- Top rail is 42 inches plus or minus 3 inches above the walking surface, with a midrail at approximately 21 inches and a toe board where required.
- Concrete cylinder specification
- Standard test cylinder is 6 inches diameter by 12 inches tall, cured and tested at 28 days. Cylinder strength is roughly 0.8 times cube strength.
- Water-cement ratio effect
- Lower water-cement ratio increases strength and reduces permeability. Each 0.01 reduction typically adds roughly 250 to 400 psi of 28-day strength.
- Footing area calculation
- Footing area equals total load divided by allowable soil bearing pressure. Typical allowable values are 1,500 psf for firm clay and 3,000 psf for compacted granular soil.
- Minimum drainage slope
- Site grading and flat roofs drain at a minimum of 1/4 inch per foot, which is 2 percent, directing water away from structures and ponding areas.
- Rebar tension lap splice
- For Grade 60 reinforcement in normal-weight concrete, a tension lap splice is typically 40 bar diameters, with a standard hook extending 12 bar diameters.
- W-shape designation meaning
- A W12x26 is a wide-flange beam with nominal depth 12 inches and weight 26 pounds per linear foot. Weight, not depth, uniquely identifies the section.
- Nominal versus dressed lumber
- Dressed lumber is smaller than nominal size: a 2x4 measures 1-1/2 by 3-1/2 inches, and a 2x10 measures 1-1/2 by 9-1/4 inches.
- Typical span of control
- A working foreperson effectively supervises about 5 to 12 workers. Beyond that range, add a lead or split the crew by task area.
- Progressive discipline sequence
- Steps run from verbal coaching to written warning, suspension, and termination. Each step requires a dated record of behavior, expectation, and consequence.
- Toolbox talk standard
- A 10- to 15-minute hazard briefing at the start of shift, focused on that day's tasks, with each attending worker signing the attendance record.
- Delegation confirmation rule
- Assign by result and deadline, then ask the worker to restate the task to confirm understanding. Check at agreed milestones rather than continuously.
- First-inspection quality control
- The first unit of repetitive work is inspected and approved against the specification before production continues, preventing repeated defects across the run.
- Hold point definition
- A stage in the inspection and test plan where work cannot proceed until the required check is performed and signed off by the designated party.
- Change order required content
- A change order states the scope change, price adjustment, time impact, and resulting schedule adjustment, and requires written authorization before work proceeds.
- Nonconformance report content
- It records location, requirement, actual condition, disposition such as rework, repair, concession, or reject, and verification that the corrective action closed the item.
- Submittal review statuses
- Return statuses are approved, approved as noted, revise and resubmit, and rejected. Installation may not begin until an approved or approved-as-noted status is issued.
- Substantial completion effect
- Substantial completion starts warranty periods, allows owner occupancy, and typically releases part of retainage, while a deficiency list remains to be corrected.
- Document order of precedence
- The agreement usually governs first, then addenda, specifications, and drawings, with standard conditions last. The more stringent requirement generally controls conflicts.
- Shop drawing definition
- Contractor-prepared details showing fabrication and installation. Designer review confirms general conformance only and does not relieve the contractor of contract compliance.
- Daily site report content
- It records date, weather, temperatures, crew counts by trade, equipment, work performed, deliveries, visitors, delays, and instructions received that day.
- Written notice of claim
- Most contracts require notice of a claim within a set number of days after the triggering event. Late notice can bar an otherwise valid claim.
- Punch list item standard
- Each entry must state location, specific description, responsible trade, and target date. Vague entries cause disputes at final acceptance and delay closeout.
- Performance documentation standard
- Record observable behavior and outcome rather than personality, including date, time, location, witnesses, and the specific standard that was not met.
- Shift handover log
- A written record of open work, hazards, equipment status, and pending inspections, signed by both outgoing and incoming forepersons at shift change.
- Cross-training matrix purpose
- It maps workers to tasks with proficiency levels, revealing single-point skill dependencies that could stall production if one worker is absent.
- Crew meeting minute timing
- Minutes circulated within 24 hours create a contemporaneous record of assignments and commitments that later supports schedule and claim positions.