Project Planning and Scheduling

  • Critical path is the longest-duration path through the schedule network; its activities have zero total float in deterministic CPM and set the minimum project duration.

  • Total float = late start − early start = late finish − early finish; free float = early start of successor − early finish of the activity.

  • PERT expected duration = (optimistic + 4 × most likely + pessimistic) ÷ 6; variance = ((pessimistic − optimistic) ÷ 6)².

  • A finish-to-start lag adds waiting time between activities; a lead allows the successor to start before the predecessor finishes.

  • Resource leveling can extend project duration when it consumes float; resource smoothing uses available float without changing the critical path.

  • A milestone has zero duration and marks a significant event or contractual date; it is not a work activity.

  • The approved schedule baseline is the comparison point for progress and delay analysis; changes to it require formal approval.

  • A rolling look-ahead schedule commonly covers the next one to six weeks and is updated as work progresses.

Quick reference

Cost Management and Estimating

  • Total estimate = direct costs + indirect costs + contingency + overhead and profit; direct costs include labor, material, equipment, and subcontracts.

  • Contingency covers known-unknown risks within scope; management reserve covers unknown-unknown risks outside the approved baseline.

  • Unit cost = total cost ÷ quantity; labor productivity = installed quantity ÷ labor hours.

  • Cost variance CV = earned value EV − actual cost AC; positive CV means under budget.

  • Schedule variance SV = EV − planned value PV; positive SV means ahead of schedule in cost terms.

  • CPI = EV ÷ AC; SPI = EV ÷ PV; EAC = BAC ÷ CPI when current cost efficiency is expected to continue.

  • Labor burden includes payroll taxes, insurance, benefits, and statutory costs; it is applied as a percentage of base wages.

  • A quantity takeoff measures net quantities from drawings; waste, overlap, and conversion factors are added separately.

  • Cash flow forecast aligns billing, retainage, payment lag, and schedule progress; profit is not cash until collected.

Quick reference

Contract Administration and Construction Law

  • A change order is a written, signed amendment to contract scope, price, or time; a field instruction alone may not change the contract until confirmed.

  • Substantial completion occurs when the work is usable for its intended purpose, even if minor punch-list items remain; it often triggers warranty and lien periods.

  • Compensable delay is owner-caused or owner-risk and supports time and cost; excusable noncompensable delay supports time only; inexcusable delay supports neither.

  • Contract notice provisions can operate as conditions precedent; late notice may bar an otherwise valid time or cost claim.

  • Statutory construction lien holdback is set by provincial legislation; amount, release timing, and permissible substitutions vary by jurisdiction.

  • Payment certification confirms amount due under the contract; it does not necessarily waive defects or accept nonconforming work.

  • When contract documents conflict, apply the contract's stated order of precedence before reliance on general common-law rules.

  • Ambiguity in a contract is generally construed against the party that drafted it under contra proferentem, unless another rule applies.

  • Typical dispute resolution sequence is negotiation, mediation, then arbitration or litigation as specified in the contract.

Quick reference

Construction Safety and Risk Management

  • Hierarchy of controls, from most to least effective: elimination, substitution, engineering controls, administrative controls, then personal protective equipment.

  • Risk score = likelihood × severity; controls are prioritized for hazards with the highest score and for those with severe irreversible outcomes.

  • A job hazard analysis breaks a task into steps, identifies hazards for each step, and assigns controls before work starts.

  • A near miss is an unplanned event that did not cause injury or damage but had the potential to do so; it is recorded and investigated.

  • Confined-space entry requires hazard assessment, atmospheric testing, isolation, ventilation, a permit, an attendant, and a rescue plan.

  • Root-cause analysis seeks underlying management-system causes; immediate causes describe the unsafe act or condition at the event.

  • Incident investigation should identify what happened, why barriers failed, and what corrective actions prevent recurrence.

  • Emergency response plans define roles, evacuation routes, communication, rescue, and medical arrangements for site-specific hazards.

  • Experience rating modifies workers' compensation premiums based on claims history relative to industry peers.

Quick reference

Quality Management

  • Quality assurance covers planned processes that prevent defects; quality control covers inspection, testing, and measurement of completed work.

  • An inspection and test plan lists activities, acceptance criteria, inspection methods, frequencies, and hold or witness points.

  • Cost of quality = prevention + appraisal + internal failure + external failure; external failure usually carries the highest cost.

  • PDCA cycle: plan the change, do it on a small scale, check results against criteria, and act by standardizing or correcting.

  • A nonconformance report records the requirement not met, disposition, root cause, corrective action, and verification.

  • Dispositions for nonconforming work include rework, repair, concession or deviation acceptance, and rejection.

  • Calibration confirms that measuring and test equipment has known accuracy against a traceable standard.

  • A mock-up or benchmark establishes a visible quality standard before repetitive work begins.

Quick reference

Leadership, Communication and Human Resources

  • Tuckman team stages are forming, storming, norming, performing, and adjourning; performance usually stabilizes after storming is resolved.

  • Communication channels = n(n − 1) ÷ 2, where n is the number of participants; channels grow rapidly as team size increases.

  • SMART goals are specific, measurable, achievable, relevant, and time-bound.

  • Situational leadership matches directive or supportive behavior to follower competence and commitment.

  • Conflict modes are competing, collaborating, compromising, avoiding, and accommodating; collaborating seeks a win-win solution.

  • Herzberg separates hygiene factors, such as pay and working conditions, from motivators, such as achievement and recognition.

  • Active listening includes attending, paraphrasing, questioning, and confirming understanding before responding.

  • Progressive discipline typically moves from verbal warning to written warning to suspension and termination, with documentation at each step.

  • A stakeholder power-interest grid prioritizes engagement by influence and interest.