A regional hospital's finance director, Priya, must decide whether to renew a $420,000 annual contract for an external patient-scheduling platform. The vendor reports 94% uptime and a 12-minute average call-handling time, but the hospital's own ticketing data shows 38% of scheduling requests still require a human callback. Priya's CEO has already told the board the platform 'cut wait times by a third,' citing a vendor case study from a different hospital. Priya has three weeks before renewal, no budget for a formal evaluation, and a competing bid that is 15% cheaper but unproven. Her chief nursing officer wants to keep the current vendor; her IT lead wants to switch. Priya notices the original business case for the platform was written by the vendor's own solutions team and never updated.

1. Identify the decision-making traps operating in this situation and explain how each could distort Priya's choice.

Read the worked answer

At least four traps are active. Anchoring on the CEO's 'one-third' figure: it comes from a different hospital and was never validated locally, yet it now frames the renewal as a success story. Confirmation bias: the vendor's 94% uptime and 12-minute handling time are being used as evidence of success while the 38% callback rate - the metric that actually reflects the patient experience - is treated as an operational detail. Sunk-cost thinking: the $420,000 already spent is irrelevant to the forward-looking renewal decision, but it will feel like a reason to continue. Groupthink/social pressure: the CNO and IT lead have staked out opposing positions, which pushes Priya toward a compromise (renew for one year) rather than an evidence-based choice. A fifth trap is authority bias toward the vendor-authored business case, which was never independently updated. Naming the traps matters because each suggests a different corrective: re-baseline the metrics locally, separate sunk costs from future costs, and solicit dissenting views deliberately rather than splitting the difference.

2. Priya has three weeks and no evaluation budget. Propose a decision process she can actually run in that window, and justify the sequence.

Read the worked answer

A defensible three-week process: Week 1 - define the decision and the criteria. Write down the actual question ('renew, switch, or extend-and-pilot?'), the objectives (patient wait time, staff workload, cost per scheduled appointment, switching risk), and the must-have constraints. Pull the hospital's own ticketing data and compute the callback rate by department and by hour of day; this replaces the vendor case study with local evidence. Week 2 - get comparison evidence cheaply. Ask both vendors for the same five metrics under the same definitions, and run a short structured interview with 8–10 schedulers and a sample of patients. A one-week pilot of the cheaper bid on a single department is feasible and far cheaper than a formal evaluation. Week 3 - decide and document. Convene the CNO and IT lead with a shared scoring sheet, record the reasoning, and set a review date. The sequence matters because criteria must be fixed before evidence is gathered, or the evidence will be selected to fit pre-existing positions. The one-year extension is a legitimate option only if it is paired with the pilot and a hard review gate - otherwise it is just deferral.