OACETT IEPPE study materials
OACETT IEPPE study resources

OACETT IEPPE cheat sheet

OACETT IEPPE · Keep the key ideas within reach.

Quick reference

Engineering and Applied Science Technology Practice in Ontario

  • Professional practice is regulated in Ontario under the Professional Engineers Act; a licensed professional engineer holds a P.Eng., while OACETT certifies engineering technologists (C.E.T.) and technicians (C.Tech.).

  • Scope-of-practice rule: work requiring professional engineering (design of works affecting public safety, signing/sealing engineering documents) is reserved to P.Eng. holders; certified technologists practise within their certified scope and under appropriate supervision where the Act requires.

  • The 'practice of professional engineering' includes design, evaluation, inspection, and reporting on engineering works where the work affects public safety, health, or welfare.

  • OACETT certification grades: C.Tech. (technician, typically 2-year diploma plus experience), C.E.T. (technologist, typically 3-year diploma plus experience), and associate/student categories.

  • Technologist deliverables must be traceable: calculations, assumptions, references, and approval signatures recorded so another competent practitioner can verify the work.

  • When scope of a task exceeds certified competence, the correct action is to escalate to a P.Eng. or qualified specialist rather than proceed independently.

  • Continuing competence is a condition of certification; OACETT requires ongoing professional development and periodic reporting.

Quick reference

Professional Ethics, Integrity and Accountability

  • Core ethical hierarchy: public safety, health, and welfare first; then client/employer interests; then professional reputation and personal interest.

  • Conflict-of-interest rule: disclose any financial or personal interest that could bias judgment; recuse when a reasonable observer would question objectivity.

  • Confidentiality applies to client information obtained in the course of work; exceptions are legal compulsion (court order, regulator), imminent danger to life, or client-authorized release.

  • Signing or sealing a document attests personal review and technical responsibility; endorsing work not reviewed is a falsification of professional record.

  • Gifts or inducements that could influence technical decisions must be declined or disclosed per employer policy.

  • Whistleblower duty: where an employer's action endangers public safety, the technologist must report internally first, then to the regulator or authority if unresolved.

  • Accountability means documenting decisions contemporaneously - a defensible record shows what was known, decided, and why at the time.

Quick reference

Occupational Health and Safety and Workplace Legislation

  • Ontario Occupational Health and Safety Act (OHSA) establishes the internal responsibility system: employers, supervisors, and workers each have defined duties.

  • Employer duties under OHSA s.25 include providing a safe workplace, information, instruction, supervision, and prescribed protective equipment at no cost to the worker.

  • Worker rights under OHSA: right to know hazards, right to participate (JHSC), right to refuse unsafe work (s.43), and right to stop work in certain circumstances.

  • Work refusal procedure: report to supervisor, supervisor investigates with worker and a JHSC member/health and safety representative present; unresolved refusals go to an MLITSD inspector.

  • Joint Health and Safety Committee (JHSC) is required at workplaces with 20+ workers; certification of at least one worker and one management member is required at 20+ (and other prescribed) workplaces.

  • Critical injury and fatality notification: report immediately to the MLITSD, JHSC, and union; preserve the scene except to prevent further harm.

  • Workplace Hazardous Materials Information System (WHMIS) requires labels, safety data sheets, and worker training for controlled products.

Quick reference

Codes, Standards, Regulations and Permitting

  • Hierarchy of authority: statute (Act) > regulation made under the Act > adopted standard/code > project specification > manufacturer instruction.

  • Ontario Building Code (OBC) is a regulation under the Building Code Act; compliance is verified through building permits and inspections by the principal authority.

  • Canadian Standards Association (CSA), ASTM, and National Building Code of Canada standards are often incorporated by reference; the edition referenced governs, not the newest edition.

  • A building permit is required before construction or alteration of most structures; work without a permit can trigger stop-work orders and demolition orders.

  • Environmental permits: Ontario Regulation 1/17 (Environmental Activity and Sector Registry) and Environmental Compliance Approvals (ECAs) under the Environmental Protection Act govern discharges to air, land, and water.

  • Technical Standards and Safety Authority (TSSA) regulates fuels, boilers, pressure vessels, and elevating devices; installation requires TSSA-registered contractors and inspection.

  • Electrical work in Ontario is governed by the Electrical Safety Code and inspected by ESA (Electrical Safety Authority).

Quick reference

Technical Documentation, Drawings and Specifications

  • Drawing types: plan (top view), elevation (vertical face), section (cut view), detail (enlarged portion), and isometric/pictorial views.

  • Scale is the ratio of drawing dimension to real dimension; a 1:50 scale drawing means 1 unit on paper equals 50 units in reality.

  • Line conventions: object lines (thick continuous), hidden lines (dashed), centre lines (long-short dash), dimension/extension lines (thin continuous), and break lines.

  • Dimensioning rule: place dimensions on the view that best shows the feature; avoid duplicate dimensions; do not scale a drawing when a dimension is given.

  • Title block content: project name, drawing number, scale, date, revision, designer/checker initials, and professional seal where required.

  • Specification divisions follow MasterFormat (e.g., Division 03 Concrete, Division 05 Metals, Division 26 Electrical); the specification governs quality, the drawing governs quantity and location.

  • Revision control: superseded drawings must be marked void and removed from active use; a revision cloud and delta mark identify changed areas.

Quick reference

Project Management, Scheduling and Cost Control

  • Critical path method (CPM): the critical path is the longest-duration path through the network; its total float equals zero, so any delay there delays project completion.

  • Float (slack) = late start − early start = late finish − early finish; total float is shared along a path, free float is available without delaying the successor.

  • Earned Value formulas: CV = EV − AC; SV = EV − PV; CPI = EV / AC; SPI = EV / PV; EAC ≈ BAC / CPI.

  • Cost variance interpretation: CPI < 1 means over budget per unit of work performed; SPI < 1 means behind schedule.

  • Contract types: lump sum (fixed price), unit price (measured quantities), cost-plus (time and material), and design-build; risk allocation shifts with contract type.

  • Change order control: any scope change requires documented authorization before execution; track against contingency and update the schedule baseline.

  • Three-point estimate: expected duration = (optimistic + 4×most likely + pessimistic) / 6 (PERT).

Quick reference

Quality Assurance, Testing and Inspection

  • Quality assurance (process-focused, preventive) differs from quality control (product-focused, inspection and testing of outputs).

  • Inspection and Test Plan (ITP) defines hold points (work cannot proceed without sign-off) and witness points (notification required, work may proceed).

  • Sampling and acceptance: concrete compressive strength is assessed on cylinders tested at 7 and 28 days; slump and air content are tested at placement.

  • Non-conformance report (NCR) documents the deviation, disposition (rework, repair, use-as-is, reject), and corrective action to prevent recurrence.

  • Calibration of test equipment must be traceable to a national standard; out-of-calibration instruments invalidate results obtained with them.

  • Statistical process control uses control charts; a process is out of control when points exceed control limits or show non-random patterns (trends, runs).

  • Root cause analysis tools include the 5-Whys, fishbone (Ishikawa) diagram, and Pareto analysis of defect frequency.

Quick reference

Communication, Client Relations and Teamwork

  • Communication model: sender → encoding → medium → decoding → receiver, with feedback and noise as the distortion factors.

  • Active listening behaviours: paraphrasing, clarifying questions, summarizing, and withholding judgment until the speaker completes the point.

  • Written technical communication structure: purpose/scope, findings, recommendation, and supporting data; lead with the conclusion for decision-makers.

  • Conflict resolution sequence: address privately, focus on interests not positions, agree on facts first, then negotiate options.

  • Client expectation management: document scope, exclusions, and assumptions in writing; verbal agreements must be confirmed by email or memo.

  • Team roles (Belbin-style): coordinator, implementer, shaper, plant, resource investigator, monitor-evaluator, teamworker, completer-finisher, specialist - balance improves performance.

  • Escalation protocol: notify the appropriate level within the agreed timeframe and in writing when a risk to schedule, cost, or safety emerges.

Quick reference

Environmental Responsibility and Sustainability

  • Environmental Protection Act (Ontario) prohibits discharge of contaminants into the natural environment that causes or may cause an adverse effect.

  • Spill reporting: report spills immediately to the Ministry of the Environment, Conservation and Parks (MECP) Spills Action Centre (1-800-268-6060) and to the municipality where required.

  • Waste hierarchy, in order of preference: reduce, reuse, recycle, recover (energy), treat, dispose.

  • Environmental assessment (EA) process under the Environmental Assessment Act applies to public-sector and prescribed undertakings; Class EAs streamline routine projects.

  • Design for sustainability: life-cycle assessment, energy modelling, water conservation, low-impact development for stormwater, and material selection with recycled content.

  • Designated substances (e.g., asbestos, lead, silica) and excess soil management are regulated; soil must be characterized before off-site movement under Ontario Regulation 406/19.

  • Greenhouse gas accounting: Scope 1 (direct), Scope 2 (purchased energy), Scope 3 (value chain) emissions.

Quick reference

Professional Development, Competency Maintenance and OACETT Governance

  • OACETT is governed by a Council and administered by a Registrar and staff; chapters provide local professional development and networking.

  • Continuing Professional Development (CPD) requirement: members maintain and report professional development activities on a defined cycle to retain certification.

  • Certification maintenance requires good standing: payment of annual fees, adherence to the Code of Ethics, and compliance with CPD reporting.

  • The OACETT Code of Ethics obliges members to hold public safety paramount, practise competently, maintain confidentiality, and avoid conflicts of interest.

  • Competency categories typically tracked: technical competence, communication, project/management skills, and ethical/legal knowledge.

  • Mentoring and volunteer chapter involvement count toward professional development and are recognized through OACETT awards and recognition programs.

  • Discipline process: complaints are reviewed by a Complaints Committee and may proceed to a Discipline Committee; sanctions range from caution to revocation of certification.

Quick reference

Additional Practice Integration

  • Document retention: keep design calculations, test records, and inspection reports for the period required by contract and statute; engineering records commonly retained for the life of the asset plus limitation period.

  • Limitation period in Ontario for civil claims is 2 years from discovery, with an ultimate 15-year limit from the act or omission.

  • Occupational Health and Safety re certification: the C.E.T./C.Tech. credential is a protected title; misrepresentation of certification is an offence.

  • Safety in design: apply the hierarchy of controls - eliminate, substitute, engineer, administrate, then PPE as the last line.

  • Risk assessment formula: risk = likelihood × severity; prioritize controls by reducing either factor.

  • Record keeping for permits: maintain inspection records, permits, and approvals on site and available to the inspector on request.

  • Ethical use of AI and software tools: the certified member remains responsible for the output; verify calculations and never seal unreviewed automated output.