- Professional Engineer (P.Eng.) Licence
- Related: Certificate of Authorization, Limited Licence (L.E.L.)
A provincial licence granted by Professional Engineers Ontario that authorises an individual to practise professional engineering, use the title, and take legal responsibility for engineering work affecting public safety.
- Certificate of Authorization (C of A)
- Related: Professional Engineer (P.Eng.) Licence, Seal and Signature
A licence issued to a firm that provides engineering services to the public, requiring the firm to have a professional engineer who assumes responsibility for the firm's engineering work.
- Limited Licence (L.E.L.)
- Related: Professional Engineer (P.Eng.) Licence, Scope of Practice
A licence issued to an individual who is not a professional engineer but whose scope of practice is limited to a specific area of engineering, allowing independent practice within that defined scope.
- Scope of Practice
- Related: Limited Licence (L.E.L.), Competence
The defined range of engineering activities a licensee is competent and authorised to perform, determined by education, experience, and the terms of the licence or certificate.
- Seal and Signature
- Related: Certificate of Authorization (C of A), Technical Documentation
The professional engineer's stamp and handwritten or electronic signature applied to documents to certify that the work was performed by or under the supervision of a licensed engineer.
- Code of Ethics
- Related: Conflict of Interest, Public Interest
The set of principles and rules adopted by OACETT and PEO that govern the conduct of members, requiring honesty, fairness, competence, and protection of the public interest.
- Conflict of Interest
- Related: Code of Ethics, Integrity
A situation in which a member's personal, financial, or other interest could improperly influence professional judgment, requiring disclosure and avoidance or management of the conflict.
- Public Interest
- Related: Code of Ethics, Professional Accountability
The welfare and safety of the general public, which takes precedence over the interests of clients, employers, or the professional, and is the foundation of professional regulation.
- Integrity
- Related: Conflict of Interest, Professional Accountability
The quality of being honest, consistent, and principled in professional conduct, including refusing to misrepresent qualifications, test results, or the status of work.
- Professional Accountability
- Related: Public Interest, Due Diligence
The obligation of a practitioner to accept responsibility for their actions, decisions, and work products, including errors and omissions, and to report and correct problems promptly.
- Due Diligence
- Related: Professional Accountability, Risk Assessment
The level of care, investigation, and precaution a reasonable professional would exercise to identify and manage risks before making decisions or issuing work.
- Occupational Health and Safety Act (OHSA)
- Related: Workplace Hazardous Materials Information System (WHMIS), Internal Responsibility System
Ontario legislation that sets out the duties of employers, supervisors, and workers to protect health and safety in the workplace, including the right to refuse unsafe work.
- Internal Responsibility System (IRS)
- Related: Occupational Health and Safety Act (OHSA), Joint Health and Safety Committee (JHSC)
The principle underlying Ontario's OHSA that everyone in the workplace shares responsibility for health and safety, with defined duties for employers, supervisors, and workers.
- Joint Health and Safety Committee (JHSC)
- Related: Internal Responsibility System (IRS), Workplace Hazardous Materials Information System (WHMIS)
A workplace committee composed of worker and employer representatives that identifies hazards, makes recommendations, and helps resolve health and safety concerns, as required by Ontario law.
- Workplace Hazardous Materials Information System (WHMIS)
- Related: Occupational Health and Safety Act (OHSA), Safety Data Sheet (SDS)
A Canada-wide system that requires suppliers and employers to provide labels and safety data sheets and to train workers about hazardous materials in the workplace.
- Safety Data Sheet (SDS)
- Related: Workplace Hazardous Materials Information System (WHMIS), Personal Protective Equipment (PPE)
A standardized document that provides information about the hazards, safe handling, storage, and emergency measures for a hazardous product, required under WHMIS.
- Personal Protective Equipment (PPE)
- Related: Safety Data Sheet (SDS), Hierarchy of Controls
Equipment worn by a worker to minimize exposure to hazards, such as helmets, gloves, and eye protection, used as a last line of defence after engineering and administrative controls.
- Hierarchy of Controls
- Related: Personal Protective Equipment (PPE), Risk Assessment
A risk-management framework that ranks hazard controls from most to least effective: elimination, substitution, engineering controls, administrative controls, and personal protective equipment.
- Ontario Building Code (OBC)
- Related: Permit to Construct, Canadian Standards Association (CSA) Standards
A regulation under Ontario's Building Code Act that sets minimum standards for the design, construction, renovation, and demolition of buildings, including fire safety and structural requirements.
- Permit to Construct
- Related: Ontario Building Code (OBC), Authority Having Jurisdiction (AHJ)
An official authorization issued by a municipality or authority having jurisdiction that allows construction or alteration work to proceed after plans have been reviewed for code compliance.
- Authority Having Jurisdiction (AHJ)
- Related: Permit to Construct, Canadian Standards Association (CSA) Standards
The organization or official responsible for enforcing code requirements and approving equipment, materials, installations, or procedures within a defined geographic or technical area.
- Canadian Standards Association (CSA) Standards
- Related: Ontario Building Code (OBC), Authority Having Jurisdiction (AHJ)
Consensus-based technical standards developed by the CSA Group that are widely referenced in Ontario regulations for electrical, mechanical, structural, and safety-related design and installation.
- Technical Documentation
- Related: Seal and Signature, As-Built Drawings
The complete set of records, drawings, specifications, calculations, and reports that define a design, support approvals, and guide construction, operation, and maintenance.
- As-Built Drawings
- Related: Technical Documentation, Shop Drawings
Drawings revised after construction to show the actual installed conditions, dimensions, and locations of components, used for future maintenance, renovation, and record-keeping.
- Shop Drawings
- Related: As-Built Drawings, Submittal Review
Detailed drawings prepared by a contractor or fabricator that show how specific components will be manufactured and installed, submitted to the designer for review and approval.
- Submittal Review
- Related: Shop Drawings, Request for Information (RFI)
The process by which the design professional examines contractor submissions such as shop drawings, product data, and samples to verify conformance with the contract documents.
- Request for Information (RFI)
- Related: Submittal Review, Change Order
A formal written request from a contractor to the design professional seeking clarification or additional information about the contract documents during a project.
- Change Order
- Related: Request for Information (RFI), Critical Path Method (CPM)
A written amendment to the contract, authorised by the owner, that modifies the scope, schedule, or price of the work after the contract has been executed.
- Critical Path Method (CPM)
- Related: Gantt Chart, Earned Value Management (EVM)
A scheduling technique that identifies the longest sequence of dependent activities determining the project's minimum duration, and highlights activities where delay affects completion.
- Gantt Chart
- Related: Critical Path Method (CPM), Milestone
A bar chart that displays project activities against a calendar timeline, showing start and finish dates, durations, and sometimes dependencies and progress.
- Earned Value Management (EVM)
- Related: Critical Path Method (CPM), Cost Variance
A project control method that integrates scope, schedule, and cost by comparing planned value, earned value, and actual cost to measure performance and forecast outcomes.
- Cost Variance
- Related: Earned Value Management (EVM), Schedule Variance
The difference between the budgeted cost of work performed (earned value) and the actual cost of that work, indicating whether a project is under or over budget.
- Schedule Variance
- Related: Earned Value Management (EVM), Cost Variance
The difference between the budgeted cost of work performed (earned value) and the budgeted cost of work scheduled, indicating whether a project is ahead of or behind schedule.
- Quality Assurance (QA)
- Related: Quality Control (QC), Inspection and Test Plan (ITP)
The planned and systematic activities implemented to ensure that products or services meet specified quality requirements, focusing on process improvement and defect prevention.
- Quality Control (QC)
- Related: Quality Assurance (QA), Non-Conformance Report (NCR)
The operational techniques and activities used to verify that work products conform to quality requirements, including inspection, testing, and measurement of completed work.
- Inspection and Test Plan (ITP)
- Related: Quality Assurance (QA), Hold Point
A project document that lists the inspections and tests required for specific work, the acceptance criteria, and the hold points where work cannot proceed without approval.
- Hold Point
- Related: Inspection and Test Plan (ITP), Witness Point
A designated stage in a process where work must stop and specified inspection or approval must be obtained before proceeding, as defined in the inspection and test plan.
- Witness Point
- Related: Hold Point, Inspection and Test Plan (ITP)
A point in a process where an inspector or client may observe the activity but work may proceed without their attendance if they do not attend.
- Non-Conformance Report (NCR)
- Related: Quality Control (QC), Corrective Action
A document that records a failure of a product, process, or service to meet specified requirements, and describes the disposition and corrective action required.