OBC Designer Legal/Process study materials
OBC Designer Legal/Process study resources

OBC Designer Legal/Process key terms

OBC Designer Legal/Process · Get comfortable with the vocabulary.

Building Code Act, 1992

Ontario statute that establishes the framework for building regulation, including permit issuance, inspection, enforcement, and the making of the Building Code regulation itself.

Related: Ontario Building Code (Regulation 332/12), Building Code Commission
Ontario Building Code (Regulation 332/12)

The regulation made under the Act that sets out technical requirements for construction, demolition, change of use, and the standards referenced by designers and inspectors.

Related: Building Code Act, 1992, Substantial Compliance
Regulation 350/06

Regulation governing sewage systems under the Act, covering design, permit requirements, siting, maintenance, and inspection of on-site sewage disposal systems in Ontario.

Related: Sewage System Permit, Certificate of Approval for Sewage System
Chief Building Official (CBO)

The person appointed by a municipality to administer and enforce the Act locally, including issuing permits, conducting inspections, and making orders.

Related: Inspector, Order to Comply
Inspector

A person appointed under the Act by a municipality or the province to examine plans, conduct inspections, and enforce compliance with permits and the Building Code.

Related: Chief Building Official (CBO), Inspection Notice
Building Permit

Written authorization issued by the CBO allowing specified construction, demolition, or change of use to proceed in accordance with submitted plans and the Building Code.

Related: Permit Application, Conditional Permit
Permit Application

The submission, with required forms, fees, drawings, and information, by which an owner or authorized agent requests that a building permit be issued.

Related: Building Permit, Plans Review
Conditional Permit

A permit the CBO may issue before all requirements are satisfied, subject to stated conditions the applicant must meet, such as further plans or approvals.

Related: Building Permit, Occupancy Permit
Plans Review

The examination of submitted drawings and documents by the CBO or inspector to determine whether proposed work complies with the Act and Building Code before a permit is issued.

Related: Permit Application, Substantial Compliance
Substantial Compliance

The standard applied when reviewing plans and construction, requiring the work to meet the substantive requirements of the Code rather than exact literal conformity in every respect.

Related: Plans Review, Equivalent Performance
Equivalent Performance

A design approach permitting alternatives that achieve at least the level of health, safety, and fire protection intended by the Code's acceptable solutions, supported by justification.

Related: Substantial Compliance, Alternative Solution
Alternative Solution

A proposed design that differs from the Code's acceptable solutions but is shown, through analysis, to satisfy the applicable objectives and functional statements.

Related: Equivalent Performance, Substantial Compliance
Inspection Notice

The required notification by the permit holder or constructor to the CBO at prescribed stages of work so that inspections can be carried out before work is covered.

Related: Inspector, Order to Comply
Occupancy Permit

Authorization issued when a building or part is fit for occupancy, confirming that required inspections, tests, and conditions have been satisfied for the intended use.

Related: Change of Use, Conditional Permit
Change of Use

A change in the purpose or occupancy classification of a building or part that may trigger Code compliance requirements and permit obligations even without construction.

Related: Occupancy Permit, Building Permit
Sewage System Permit

Authorization required under the Act and Regulation 350/06 before constructing, altering, extending, or repairing an on-site sewage system, subject to prescribed standards.

Related: Regulation 350/06, Certificate of Approval for Sewage System
Certificate of Approval for Sewage System

A document issued for certain sewage system work or existing systems confirming compliance with Regulation 350/06 requirements and any conditions attached to the approval.

Related: Sewage System Permit, Regulation 350/06
Designer

A person who prepares or supervises the preparation of plans, specifications, or reports submitted for a permit, and who is responsible for their Code compliance.

Related: Constructor, Registered Code User
Constructor

The person responsible for the construction or demolition of a building, including ensuring the work complies with the permit, the Act, and the Building Code.

Related: Designer, Inspection Notice
Registered Code User

A qualification category under the Act allowing certain persons to carry out specified Code-related functions, such as plan examination or inspection, within defined limits.

Related: Designer, Building Code Commission
Qualification and Registration

The process by which designers, inspectors, and other regulated participants demonstrate required education, experience, and good standing to perform Code-related work.

Related: Registered Code User, Designer
Professional Responsibility

The duty of designers and constructors to act competently, honestly, and in the public interest, ensuring work complies with the Act and does not endanger safety.

Related: Conflict of Interest, Designer
Conflict of Interest

A situation where a designer's or official's personal, financial, or professional interests could improperly influence decisions, requiring disclosure or avoidance to preserve impartiality.

Related: Professional Responsibility, Chief Building Official (CBO)
Order to Comply

An order issued by the CBO or inspector requiring a person to remedy a contravention of the Act, the Code, or a permit, within a stated time.

Related: Stop Work Order, Inspection Notice
Stop Work Order

An order directing that construction or demolition cease where work is being done without a required permit or in serious contravention of the Act or Code.

Related: Order to Comply, Building Permit
Building Code Commission

A provincial body that hears applications for review of certain CBO decisions and provides interpretations or rulings on Code application and sufficiency of compliance.

Related: Appeal, Building Code Act, 1992
Appeal

A formal challenge to a decision such as a refusal to issue a permit, an order, or a condition, brought before the appropriate review body within prescribed time limits.

Related: Building Code Commission, Order to Comply
Records Retention

The obligation to keep permit applications, plans, inspection records, orders, and related documents for the periods and in the manner required by the Act and regulation.

Related: Inspection Notice, Order to Comply
Notice of Violation

A written notice documenting non-compliance with the Act, Code, or permit conditions, often preceding or accompanying enforcement action and requiring corrective steps.

Related: Order to Comply, Stop Work Order
Offence and Penalty

A contravention of the Act or Code that may be prosecuted, exposing the offender to fines and other penalties set out in the statute and its regulation.

Related: Order to Comply, Stop Work Order
Municipal Authority

The local government role of administering and enforcing the Act, including appointing the CBO and inspectors, issuing permits, and adopting local enforcement policies.

Related: Chief Building Official (CBO), Building Permit
Site Plan / Plot Plan

A scaled drawing showing the building's location relative to property lines, setbacks, and adjacent structures, used to assess zoning and Code siting compliance.

Related: Permit Application, Plans Review
Demolition Permit

Authorization required before demolishing a building or part, subject to conditions protecting adjacent structures, services, and public safety.

Related: Building Permit, Order to Comply
Certificate of Occupancy

A municipal document confirming that a completed building or portion may be lawfully occupied for its intended use after required inspections and approvals.

Related: Occupancy Permit, Change of Use
Enforcement Procedure

The structured steps an inspector or CBO follows to investigate complaints, document non-compliance, issue orders, and pursue remedies under the Act.

Related: Notice of Violation, Order to Comply
Public Safety Objective

The overarching goal of the Act and Code to protect public health and safety, including fire protection, structural sufficiency, and safe occupancy of buildings.

Related: Professional Responsibility, Substantial Compliance