Project fundamentals

  • A project is a temporary endeavor that creates a unique product, service, or result; ongoing repetitive work is an operation.

  • The triple constraint links scope, schedule, and cost; a change to any one normally requires adjustment to at least one other and affects quality.

  • Process groups are Initiating, Planning, Executing, Monitoring and Controlling, and Closing; they are not the same as project phases.

  • A program coordinates related projects for shared benefits; a portfolio is a set of projects, programs, and operations selected to meet strategic objectives.

  • A project charter authorizes the project and names the project manager; it contains purpose, measurable objectives, high-level scope, key deliverables, milestones, budget, sponsor, and PM authority.

  • A business case justifies the investment through benefits, costs, risks, and strategic fit; it is approved before or with the charter.

  • A phase gate is a formal go/kill/hold/recycle decision at a phase boundary; entry and exit criteria are defined before the gate.

  • PMO types: supportive provides templates and advice; controlling requires compliance with methods; directive assigns project managers and owns project delivery.

  • Benefits are realized after the output is transitioned to operations; the project manager may deliver the output but not own benefit realization.

Quick reference

Governance and professional ethics

  • Project governance defines decision rights, accountability, oversight, and escalation paths; the sponsor or board sets it, not the project manager alone.

  • A stage gate is a governance control: go, kill, hold, or recycle; decision criteria and decision authority are agreed before the gate.

  • Core ethical duties include honesty, responsibility, fairness, and respect; ethical requirements can exceed legal minimums.

  • A conflict of interest exists when a personal, financial, or other interest could improperly influence professional judgment; disclose it and recuse from the decision.

  • Confidential project information may not be used for personal gain or disclosed without authorization, except where law or professional duty requires reporting.

  • Procurement integrity prohibits bid rigging, collusion, undisclosed conflicts, and gifts or hospitality that could influence award decisions.

  • Whistleblowing is reporting illegal or unethical conduct; use internal channels first unless immediate external reporting is required by law or safety risk.

  • Accountability cannot be delegated without matching authority; a RACI matrix assigns one accountable owner per deliverable or decision.

  • Records must be accurate, complete, and retained per contract and legal requirements; falsifying progress, costs, or test results is misconduct.

Quick reference

Scope, schedule and cost planning and control

  • The WBS is a hierarchical decomposition of total scope; the 100% rule requires child elements to sum to the parent without overlap.

  • Scope creep is uncontrolled addition of work without change control; gold plating is adding unrequested features.

  • Change control: log request, assess impact on scope, schedule, cost, quality, and risk, obtain decision from the authorized body, then update baselines and communicate.

  • Critical path is the longest path through the network; it has the least total float, often zero, and sets the shortest project duration.

  • Total float = LS − ES or LF − EF; free float is the time an activity can slip without delaying the early start of its successor.

  • PERT expected duration = (optimistic + 4 × most likely + pessimistic) / 6; PERT variance = ((pessimistic − optimistic) / 6)².

  • EVM: CV = EV − AC; SV = EV − PV; CPI = EV / AC; SPI = EV / PV; CPI or SPI below 1.0 indicates unfavorable performance.

  • Forecast EAC = BAC / CPI when current cost efficiency continues; ETC = EAC − AC; VAC = BAC − EAC.

  • Contingency reserve covers known unknowns and is included in the cost baseline; management reserve covers unknown unknowns and sits above the baseline.

Quick reference

Risk, quality and procurement management

  • Risk is an uncertain event or condition that, if it occurs, affects one or more project objectives; an issue is a risk that has occurred.

  • Risk management sequence: plan, identify, analyze, plan responses, implement responses, and monitor; risks are owned by named risk owners.

  • EMV = probability × monetary impact; decision trees sum EMVs across branches; Monte Carlo simulates combined uncertainty.

  • Negative risk responses: avoid, mitigate, transfer, accept; positive risk responses: exploit, enhance, share, accept.

  • Quality assurance is process-focused and preventive; quality control is product-focused and detects defects through inspection and testing.

  • Cost of quality = prevention + appraisal + internal failure + external failure; external failure is usually the most expensive category.

  • Pareto analysis separates the vital few causes from the trivial many, typically using the 80/20 principle; fishbone diagrams organize root causes.

  • Fixed-price contracts place cost risk on the seller; cost-reimbursable contracts place cost risk on the buyer; time-and-materials shares risk.

  • Procurement sequence: make-or-buy analysis, solicitation, bid evaluation, award, contract administration, and closeout.

Quick reference

Stakeholder engagement, communication and team leadership

  • A stakeholder is any person or group that can affect or be affected by the project; stakeholder engagement is continuous, not a one-time register update.

  • Power/interest grid: high power/high interest manage closely; high power/low interest keep satisfied; low power/high interest keep informed; low power/low interest monitor.

  • Communication channels = n(n − 1) / 2 for n stakeholders, counting each two-way channel once.

  • The communication model includes sender, encoding, message, medium, decoding, receiver, feedback, and noise; noise is any interference that distorts the message.

  • Tuckman team stages: forming, storming, norming, performing, adjourning; storming is normal and should be addressed, not avoided.

  • RACI: Responsible performs the work; Accountable owns the outcome and should be one person per task; Consulted gives two-way input; Informed receives one-way updates.

  • Conflict modes: collaborate, compromise, accommodate, compete, avoid; collaboration seeks a win-win solution and is preferred for important long-term issues.

  • Herzberg: hygiene factors such as pay, working conditions, and policy prevent dissatisfaction; motivators such as achievement, recognition, and growth create satisfaction.

  • Servant leadership prioritizes removing impediments and developing team members; transactional leadership exchanges rewards for performance.

Quick reference

Health, safety, sustainability and regulatory compliance

  • Hierarchy of controls: elimination, substitution, engineering controls, administrative controls, personal protective equipment; PPE is the last line of defense.

  • Risk assessment rates severity and likelihood; ALARP means reducing risk as low as reasonably practicable, balancing risk reduction against cost and effort.

  • A near miss is an incident without injury or damage; reporting near misses is a leading indicator and should be investigated for root causes.

  • Lagging indicators include injury frequency and lost-time rates; leading indicators include training completion, near-miss reports, and safety observations.

  • Triple bottom line evaluates performance across people, planet, and profit; life-cycle assessment considers impacts from raw material to disposal.

  • Waste hierarchy: prevent, reuse, recycle, recover energy, and dispose; prevention is preferred over disposal.

  • A permit-to-work system authorizes high-risk activities with defined precautions, isolations, and sign-offs before work starts.

  • Regulatory compliance includes identifying legal requirements, obtaining permits, monitoring, auditing, and reporting; non-compliance can cause stop-work orders, fines, or prosecution.

  • Emergency response plans define roles, alarms, evacuation routes, assembly points, communication, and drills; drills test the plan and identify gaps.