Occupational Health and Safety

  • Test-before-touch: verify the tester on a known live source, test the isolated conductor, then re-verify the tester; a single zero reading is not proof of de-energization.

  • CSA Z462 arc flash boundary is the distance at which incident energy equals 1.2 cal/cm²; PPE is then selected from the calculated incident energy at the working distance.

  • Confined space entry requires atmosphere testing before entry: oxygen between 19.5% and 23.0%, combustible gas below 10% LEL, and toxic gases within provincial exposure limits.

  • CEC Rule 76-012 requires Class A ground-fault circuit interrupter protection (5 mA) for 15 A and 20 A receptacles used on construction sites.

  • Fall protection is required at 3 m (10 ft) in most Canadian jurisdictions, and a written rescue plan must exist before any worker relies on it.

  • Flexible cord is permitted only for temporary connection: it may not be used as permanent wiring, concealed in walls, or spliced to extend a run.

  • Every Canadian jurisdiction protects the right to refuse unsafe work; the refusal is reported to the supervisor and investigated with a worker representative present.

  • Temporary site wiring must be supported and protected from mechanical damage, with a lockable disconnecting means provided for each temporary service.

Quick reference

Codes and Standards

  • CEC Rule 8-104: a continuous load is limited to 80% of the rating of the conductor or overcurrent device unless the assembly is approved for 100% loading.

  • CEC Rule 8-102 voltage drop limits: 3% maximum on a branch circuit and 5% total from the service entrance to the load.

  • Rule 4-006 requires conductor ampacity to be taken from Table 2, 4 or 5C using the more restrictive of the conductor insulation rating and the termination temperature rating.

  • Rule 2-024 requires all electrical equipment to be approved and to bear a recognized certification mark such as CSA, cUL, or ULC.

  • Bonding conductor size is selected from Table 16 based on the rating of the overcurrent device protecting the circuit, not on the phase conductor size.

  • Rule 12-3034 box fill: one volume allowance per conductor, one per device or fitting, one for all grounding conductors, and the largest allowance for each cable clamp.

  • The neutral is grounded at only one point - the service or a separately derived source; a second neutral-to-ground bond downstream creates a parallel return path.

  • CEC Section 28 motor branch-circuit conductors are sized at 125% of the motor full-load current taken from Tables 44 or 45, not from the nameplate.

Quick reference

Electrical Theory and Circuit Analysis

  • Ohm's law V = I × R; power P = V × I = I²R = V²/R for resistive DC circuits.

  • Balanced three-phase real power P = √3 × V(line) × I(line) × PF; apparent power S in VA, reactive power Q in VAR, and S² = P² + Q².

  • Impedance Z = √(R² + X²), with X_L = 2πfL and X_C = 1/(2πfC); at resonance X_L = X_C and Z reduces to R.

  • Balanced wye: I(line) = I(phase) and V(line) = √3 × V(phase). Balanced delta: V(line) = V(phase) and I(line) = √3 × I(phase).

  • For a sine wave, RMS = 0.707 × peak, average = 0.637 × peak, and form factor = RMS/average = 1.11.

  • Power-factor correction capacitance: kVAR = P × (tan θ1 − tan θ2), where θ1 and θ2 are the arccosines of the existing and target power factors.

  • Series circuits share one current and sum resistances; parallel circuits share one voltage and sum conductances (1/R_total = sum of reciprocals).

  • Thevenin equivalent: V(th) is the open-circuit terminal voltage and R(th) is the resistance looking back into the network with sources replaced by their internal impedance.

Quick reference

Wiring, Cabling, Raceways and Enclosures

  • Raceway fill limits: 53% of interior cross-sectional area for one conductor, 31% for two conductors, and 40% for three or more.

  • No more than 360° of total bend (four quarter bends) is permitted between pull points in any raceway run.

  • Ampacity from Table 5C must be corrected for ambient temperature and derated for conductor bundling; the lowest resulting value governs the installation.

  • EMT is supported within 1 m of each box and at intervals not exceeding 1.5 m; rigid metal conduit is supported at intervals not exceeding 3 m.

  • NMD90 is non-metallic sheathed cable for dry locations; AC90 is armoured cable; TECK90 is armoured with a moisture-resistant jacket for dry, damp, wet, and listed direct-burial use.

  • Minimum bending radius of a cable is expressed as a multiple of its overall diameter; tighter bends crack insulation and reduce dielectric withstand.

  • Expansion and deflection fittings are required where a raceway crosses a building expansion joint or is subject to thermal movement.

  • All metal raceways and cable sheaths must be bonded into an effective ground-fault current path, using listed bonding bushings at concentric or eccentric knockouts.

  • Boxes must remain accessible; junction boxes may not be buried in walls, ceilings, or underground without an approved means of access.

Quick reference

Transformers and Power Distribution Systems

  • Ideal transformer relations: V1/V2 = N1/N2 = I2/I1, so voltage steps up while current steps down in the same ratio.

  • Percent impedance sets fault current: I(sc) ≈ FLA ÷ (%Z/100); a 5%Z transformer delivers roughly 20 times full-load current into a bolted fault.

  • A delta–wye transformation introduces a 30° electrical phase shift that must be accounted for before paralleling with another source.

  • Transformers may be paralleled only when polarity, turns ratio, percent impedance, and phase-angle group all match.

  • Magnetizing inrush reaches 8 to 12 times rated current for a few cycles, so time-delay fuses or a raised magnetic setting is used to ride through it.

  • A wye secondary that is a separately derived system requires a grounded neutral and a system bonding jumper sized from Table 16 or 16B.

  • Three-phase transformer kVA = (√3 × V × I) ÷ 1000; single-phase kVA = (V × I) ÷ 1000.

  • An open-delta bank of two single-phase units delivers about 58% of the capacity of a full three-unit bank and is used only for light three-phase loads.

  • Cooling class designations (AA, AN, ONAN) state the cooling medium and method, which determine the allowable temperature rise and continuous loading.

Quick reference

Motors, Generators and Rotating Equipment

  • Synchronous speed N(s) = 120f ÷ P; a 4-pole motor on a 60 Hz supply runs at 1800 r/min.

  • Slip % = (N(s) − N(r)) ÷ N(s) × 100, and rotor frequency = slip × line frequency.

  • Motor full-load current is taken from CEC Tables 44 and 45 by horsepower and voltage; branch-circuit conductors are sized at 125% of that value.

  • Overload protection is normally set at 115% to 125% of nameplate full-load current, selected by service factor and temperature rise.

  • A three-phase motor is reversed by interchanging any two supply leads; a single-phase motor is reversed by changing the start-winding connections.

  • Insulation resistance rule of thumb: minimum acceptable is 1 MΩ plus 1 MΩ per kV of rating; test at 500 V DC for 600 V machines.

  • Single-phasing raises current in the remaining phases and causes rapid overheating; phase-loss and current-unbalance protection is used to detect it.

  • NEMA Design B is the general-purpose motor with normal starting torque and low starting current; Designs C and D provide higher starting torque for high-inertia loads.

Quick reference

Motor Controls, Starters and Variable Speed Drives

  • Three-wire control uses momentary start/stop pushbuttons with a holding contact; two-wire control uses maintained contacts and restarts automatically when power returns.

  • Overload relay class (10, 20, 30) is the maximum trip time in seconds at six times rated current; Class 20 or 30 suits high-inertia loads.

  • Forward/reverse starters need both electrical and mechanical interlocking so both contactors cannot close together and create a line-to-line short.

  • Wye-delta starting applies 58% of line voltage during the start period and produces one-third of direct-on-line starting torque.

  • Control transformer sizing uses the sealed VA of all continuously energized devices plus the inrush VA of the largest coil at 85% of rated primary voltage.

  • VFD V/Hz control holds voltage proportional to frequency below base speed to maintain flux and torque; above base speed the motor enters the constant-power field-weakening region.

  • Carrier frequency trades audible motor noise against drive switching losses and insulation stress; long motor leads require dv/dt filters or load reactors.

  • Shielded VFD cable is bonded at both the drive and motor ends, and the shield is never used as the equipment grounding conductor.

Quick reference

Programmable Logic Controllers and Industrial Automation

  • The PLC scan repeats: read input status, solve the ladder program rung by rung, then update outputs; total time is the scan time.

  • A sourcing (PNP) DC device feeds positive voltage into the input terminal; a sinking (NPN) device pulls the input terminal to common.

  • TON is on-delay, TOF is off-delay, and RTO is retentive and holds its accumulated value after the rung goes false until reset.

  • The watchdog timer faults the processor when scan time exceeds the set limit and drives outputs to their configured safe state.

  • Analog scaling: engineering value = (raw − raw_min)/(raw_max − raw_min) × (EU_max − EU_min) + EU_min.

  • A 12-bit analog input divides its range into 4096 counts; applied to a 4–20 mA loop this gives roughly 3.9 µA per count.

  • Ladder instructions: XIC examines for true, XIO examines for false, OTE is a non-retentive output, and OTL/OTU are latch and unlatch.

  • Remote I/O over Ethernet/IP, Profibus, or Modbus must be configured so that loss of communications forces outputs to a defined safe state.

Quick reference

Instrumentation and Process Control

  • Live-zero 4–20 mA convention: 4 mA = 0% of span, 20 mA = 100% of span, and a 0 mA reading indicates an open loop or lost supply.

  • A 250 Ω resistor across a 4–20 mA loop converts the signal to 1–5 V DC for legacy controllers and recorders.

  • A Pt100 RTD measures 100 Ω at 0 °C and rises about 0.385 Ω/°C, making it more linear and stable than a thermocouple.

  • Thermocouples output a small millivolt signal proportional to the hot-to-cold junction difference, so cold-junction compensation is mandatory.

  • PID: proportional acts on present error, integral removes steady-state offset, and derivative responds to rate of change while amplifying measurement noise.

  • ISA-5.1 tag letters: the first letter is the measured variable (F flow, P pressure, T temperature, L level) and the second is the function (T transmitter, C controller, I indicator).

  • HART superimposes a digital FSK signal on the 4–20 mA current without disturbing the analog process value.

  • Intrinsic safety barriers limit energy into a hazardous location and must be installed in the safe area with a dedicated IS grounding conductor.

  • Calibration is checked at 0, 25, 50, 75, and 100% of span, both increasing and decreasing, to verify zero, span, and linearity.

Quick reference

Electronics, Power Supplies and Communication Systems

  • A full-wave bridge rectifier fed from 60 Hz produces 120 Hz ripple; the filter capacitor value determines the resulting ripple amplitude.

  • Linear supplies dissipate the difference between input and output voltage as heat; switching supplies reach 80–95% efficiency at smaller size and weight.

  • An online double-conversion UPS powers the load continuously from its inverter; a line-interactive UPS switches to battery only on input failure.

  • RS-485 is a differential bus supporting up to 32 unit loads over about 1200 m, with a 120 Ω termination resistor at each physical end.

  • Copper Ethernet (Cat 5e/6) is limited to 100 m per channel; fibre extends distance and provides galvanic isolation between nodes.

  • Inverting op-amp gain = −R(f)/R(in); non-inverting gain = 1 + R(f)/R(in).

  • A switching transistor operates either cut off (no base current, no collector current) or saturated (minimum collector-emitter voltage) to minimize dissipation.

  • Analog signal commons are grounded at a single point to prevent ground loops, and low-frequency cable shields are grounded at one end only.

  • A silicon diode drops about 0.7 V when forward biased; a Zener diode regulates by operating in controlled reverse breakdown.