- Fall protection height
- In most Canadian jurisdictions, fall protection is required when working at heights of 3 metres (10 feet) or more. This includes guardrails, safety nets, or personal fall arrest systems.
- WHMIS 2015
- Workplace Hazardous Materials Information System requires supplier labels and safety data sheets (SDS) for controlled products, and worker training on their safe use and handling.
- Scaffold platform width
- Scaffold platforms must be at least 460 mm (18 inches) wide and equipped with guardrails including top rail, mid rail, and toe board to prevent falls and falling objects.
- Ladder setup angle
- A ladder should be set at a 1:4 ratio (75-degree angle), meaning for every 4 units of height, the base is 1 unit from the wall. It must extend 1 metre above the landing.
- NBC fire-resistance rating
- Fire-resistance ratings are expressed in hours (e.g., 1 hour, 2 hours) and are achieved by specific assemblies listed in the National Building Code or manufacturer listings.
- STC 50 requirement
- The National Building Code requires a Sound Transmission Class (STC) rating of at least 50 for party walls between dwelling units to reduce airborne sound transmission.
- Vapour barrier permeance
- In cold climates, a vapour barrier with a permeance of 0.15 perm (8.5 ng/(Pa·s·m²)) or less is typically required on the warm side of the insulation, as per code.
- Drawing line conventions
- On architectural drawings, dashed lines often indicate objects above the cut plane (e.g., a soffit), while solid lines show visible objects. Always refer to the legend for symbols.
- Steel stud spacing
- Interior steel studs are typically spaced at 400 mm (16 inches) or 600 mm (24 inches) on centre, depending on gypsum board thickness and required fire-resistance rating.
- Suspended ceiling hanger spacing
- Hanger wires for suspended ceilings must be 12-gauge galvanized steel, spaced at maximum 1200 mm (4 feet) on centre along main runners, and within 150 mm (6 inches) of ends.
- Resilient channel orientation
- Resilient channels are installed perpendicular to studs and spaced at 400 mm (16 inches) or 600 mm (24 inches) on centre to decouple gypsum board and improve acoustics.
- Control joint spacing
- Control joints in gypsum board ceilings are required at maximum 9.3 square metres (100 square feet) per joint and at intervals not exceeding 9.1 metres (30 feet).
- Gypsum board finish levels
- Joint compound finish levels range from Level 1 (for plenum areas) to Level 5 (for glossy paint under critical lighting). Level 4 is standard for most residential walls.
- Stucco coat thicknesses
- Three-coat stucco consists of a scratch coat 10 mm (3/8 in), a brown coat 6 mm (1/4 in), and a finish coat 3 mm (1/8 in), for a total thickness of at least 19 mm (3/4 in).
- Acoustic panel acclimatization
- Lay-in acoustic ceiling panels must be acclimatized to room temperature and humidity for at least 24 hours before installation to prevent warping and ensure proper fit.
- Corner bead fastener spacing
- Corner bead is installed on external corners of gypsum board and fastened at maximum 150 mm (6 inches) on centre to provide a straight, reinforced corner.
- Gypsum board thicknesses
- Common gypsum board thicknesses are 6.4 mm (1/4 in), 9.5 mm (3/8 in), 12.7 mm (1/2 in), 15.9 mm (5/8 in), and 19 mm (3/4 in). 12.7 mm is standard for walls.
- Screw spacing on ceilings
- When installing gypsum board on ceilings, screws are spaced at maximum 300 mm (12 inches) on centre; on walls, maximum 400 mm (16 inches) on centre.
- Fire-rated assembly matching
- For fire-rated assemblies, the type and spacing of fasteners, the type of gypsum board (e.g., Type X), and joint treatment must exactly match the listed ULC design.
- Sheathing expansion gap
- Plywood or OSB sheathing must be installed with a 3 mm (1/8 inch) gap between panels to allow for expansion and prevent buckling.
- Vapour barrier placement
- In cold climates, the vapour barrier is installed on the warm side of the insulation (interior side). In Canada, 0.15 mm (6 mil) polyethylene is commonly used.
- Air barrier continuity
- The air barrier must be continuous across the building envelope, including at penetrations, joints, and intersections, and must be sealed with compatible sealants or tapes.
- Batt insulation compression
- Compressing batt insulation reduces its R-value. For example, compressing a nominal R-12 batt by 50% can reduce its R-value by nearly half.
- Vapour barrier sealing
- All seams and penetrations in the vapour barrier must be sealed with approved tape or acoustical sealant, including at the perimeter and at electrical boxes.
- Metal lath weight
- Diamond mesh metal lath is available in weights of 1.75 lb/yd² and 2.5 lb/yd². It must be fastened to framing at maximum 150 mm (6 inches) on centre.
- Plaster basecoat thickness
- For gypsum plaster, a basecoat of 10 mm (3/8 inch) is applied over lath, followed by a finish coat of 3 mm (1/8 inch).
- Stucco curing time
- Stucco must be moist-cured for at least 48 hours after the scratch coat and 48 hours after the brown coat to allow proper hydration and prevent cracking.
- Scratch coat scoring
- The scratch coat of stucco must be scored with horizontal lines to provide a mechanical key for the brown coat to bond to.
- Powder-actuated tool safety
- Only trained and certified operators may use powder-actuated tools. Wear eye and hearing protection, and never use them in an explosive atmosphere.
- Screw gun depth setting
- Adjust the depth setting on a drywall screw gun so the screw head dimples the paper without breaking it. Replace worn bits regularly for consistent results.
- Mixing plaster speed
- When mixing plaster or joint compound, use a heavy-duty drill with a mixing paddle at low speed to avoid air entrainment. Allow the mix to slake before final mixing.
- Gypsum board waste factor
- When estimating gypsum board, calculate total square footage and divide by sheet area (e.g., 32 sq ft for 4x8 sheet). Add 10% for waste and cuts.
- Joint compound estimation
- Approximately 1 kg (2.2 lb) of joint compound is needed per 1 square metre (10.8 square feet) of gypsum board for a Level 4 finish.