Working load limit (WLL)

The maximum mass a rigging component or assembly is rated to lift in a specific configuration, as assigned by its manufacturer. It is the value marked on the hardware and must never be exceeded during a lift.

Related: Proof load, Design factor, Sling angle factor
Design factor

The ratio between a component's breaking strength and its rated working load limit. It provides a safety margin that absorbs wear, dynamic forces, and minor errors in load estimation or sling configuration.

Related: Working load limit (WLL), Proof load
Proof load

A test load applied to lifting hardware to confirm it performs correctly, usually a set percentage of its breaking strength. Passing a proof load test does not certify the item for service at that load.

Related: Working load limit (WLL), Design factor
Sling angle factor

A multiplier applied to a sling's capacity to account for the angle between the sling leg and the horizontal. Shallower angles increase leg tension sharply, so capacity must be reduced accordingly.

Related: Tension in sling legs, Working load limit (WLL), Centre of gravity
Tension in sling legs

The actual force carried by each sling leg, which rises as the angle between the legs widens. Two legs at 60 degrees from horizontal each carry roughly 0.58 of the load; at 30 degrees, each carries the full load.

Related: Sling angle factor, Bridle hitch
Centre of gravity

The point at which a load's mass is balanced in all directions. The crane hook must sit directly above it, or the load will tilt and shift when lifted, changing load distribution and radius.

Related: Load moment, Rigging geometry
Load moment

The turning effect of a load about the crane's tipping axis, calculated by multiplying load mass by working radius. Load moment, not load mass alone, determines whether a crane remains stable.

Related: Rated capacity, Load radius, Counterweight
Rated capacity

The maximum load a crane may lift at a given radius, boom length, and configuration, as published in the manufacturer's load chart. It already accounts for deductions such as hook block, rigging, and attachments.

Related: Load radius, Gross load, Load chart
Gross load

The total mass suspended from the boom tip, including the payload, slings, shackles, spreader bars, and the hook block. All capacity checks must use gross load, not just the weight of the object being moved.

Related: Rated capacity, Deduction for attachments
Load radius

The horizontal distance from the crane's slewing centre to the vertical line through the hook, measured with the boom under load. Radius increases as the boom is lowered or extended, reducing capacity.

Related: Rated capacity, Load moment
Load chart

The manufacturer-issued table or graph giving permissible loads for each boom length, radius, quadrant, and outrigger configuration. It is the legal authority for every lift and must match the crane's actual setup.

Related: Rated capacity, Deduction for attachments, Quadrant
Deduction for attachments

The amount subtracted from a load chart value for items carried permanently or temporarily on the boom, such as hook blocks, jib, rooster sheave, or auxiliary head. Failing to deduct them overstates capacity.

Related: Gross load, Load chart
Quadrant

One of the defined arcs around the crane's slewing axis, typically over the front, rear, or side, for which separate capacities are published. Capacity differs by quadrant because structural strength varies with boom orientation.

Related: Load chart, Slewing
Outrigger float bearing pressure

The force per unit area transmitted through each outrigger float or pad into the ground. It depends on load moment, float size, and outrigger spread, and must stay below the ground's verified bearing capacity.

Related: Ground bearing capacity, Outrigger mat, Load moment
Ground bearing capacity

The maximum pressure a soil or structure can safely support without excessive settlement or failure. It must be assessed before setup, particularly over fill, utility trenches, vaults, or recently excavated ground.

Related: Outrigger float bearing pressure, Outrigger mat, Underground hazard survey
Outrigger mat

A rigid pad placed under an outrigger float to spread load over a wider area and reduce bearing pressure. Mats must be sized for the calculated pressure and be strong enough not to crush or split.

Related: Outrigger float bearing pressure, Ground bearing capacity
Underground hazard survey

The process of identifying buried services, voids, tanks, or basement structures beneath a crane setup before positioning outriggers. It typically combines drawings, locates, and physical inspection or non-destructive methods.

Related: Ground bearing capacity, Crane setup plan
Crane setup plan

A documented layout showing crane position, outrigger spread, mat locations, load path, and exclusion zones. It is prepared before arrival and verified on site against actual ground and overhead conditions.

Related: Lift plan, Underground hazard survey, Barricade and exclusion zone
Lift plan

A written document that defines the load, rigging, crane configuration, radii, ground conditions, hazards, roles, and contingency for a specific lift. Complexity and risk determine how much engineering detail it requires.

Related: Critical lift, Crane setup plan, Rigging geometry
Critical lift

A lift that exceeds defined risk thresholds, such as near capacity, over occupied areas, tandem lifting, or lifting personnel. It usually requires engineering review, a formal plan, and additional supervision.

Related: Lift plan, Tandem lift, Personnel lifting
Tandem lift

A lift in which two or more cranes share a single load. It demands a coordinated plan, matched capacities, defined load share, communication protocol, and a designated lift director.

Related: Critical lift, Lift director, Rigging geometry
Rigging geometry

The arrangement of slings, hardware, and attachment points relative to the load's centre of gravity. It determines how load is distributed among legs and whether the load stays level and controlled.

Related: Centre of gravity, Bridle hitch, Tension in sling legs
Bridle hitch

A rigging arrangement using two or more slings joined at a common point to connect multiple lifting lugs to a single hook. Load sharing between legs depends on geometry and lug positions.

Related: Tension in sling legs, Rigging geometry
Shackle

A U-shaped connector closed by a pin or bolt, used to join slings to hooks, lugs, or hardware. The pin must be fully seated and the shackle loaded only along its intended axis.

Related: Working load limit (WLL), Rigging hardware inspection
Sling protection

Material such as pads, sleeves, or corner protectors placed between a sling and a load edge to prevent cutting, abrasion, or bending damage. It is required whenever contact surfaces could reduce sling strength.

Related: Sling inspection, Rigging hardware inspection
Sling inspection

A documented check of slings for cuts, broken wires, heat damage, chemical attack, tag loss, or excessive wear before each use. Defective slings must be removed from service immediately.

Related: Sling protection, Pre-operational inspection, Rigging hardware inspection
Rigging hardware inspection

Examination of shackles, hooks, swivels, turnbuckles, and links for cracks, deformation, thread damage, missing safety latches, or illegible markings. Any item failing inspection is tagged out and quarantined.

Related: Shackle, Sling inspection
Pre-operational inspection

The checks a competent operator performs at the start of each shift, covering fluids, tyres, wire rope, hooks, safety devices, brakes, and alarms. Findings are recorded and defects reported before work begins.

Related: Periodic inspection, Wire rope inspection, Load moment indicator (LMI)
Periodic inspection

A more thorough examination carried out at defined intervals by a competent person, covering structural, mechanical, hydraulic, and electrical systems. Records of these inspections must be retained and available.

Related: Pre-operational inspection, Inspection record, Wire rope inspection
Wire rope inspection

Assessment of hoist and boom rope for broken wires, corrosion, kinking, bird-caging, diameter reduction, and end termination condition. Rejection criteria follow the manufacturer and applicable standards.

Related: Pre-operational inspection, Periodic inspection
Load moment indicator (LMI)

An instrument that measures load and radius and warns or stops operation when capacity is approached or exceeded. It is an aid to the operator, not a substitute for reading the load chart.

Related: Rated capacity, Anti-two-block device, Load chart
Anti-two-block device

A sensing system that prevents the hook block from contacting the boom tip by stopping hoist-up or boom-lowering motion. It must be tested and never bypassed or disabled during operation.

Related: Load moment indicator (LMI), Pre-operational inspection
Slewing

Rotation of the crane's upper structure about its vertical axis. Slewing speed must be controlled to limit swing of the load and the resulting side loading on the boom.

Related: Quadrant, Load swing control
Load swing control

Technique of leading, stopping, and steadying a suspended load so it does not pendulum or strike objects. It relies on smooth acceleration, tag lines, and anticipating the load's momentum.

Related: Slewing, Tag line
Tag line

A rope attached to a load and controlled by a person on the ground to restrain rotation and swinging. Handlers must stay clear of the load path and never wrap the line around a body part.

Related: Load swing control, Barricade and exclusion zone
Barricade and exclusion zone

A marked or physically blocked area beneath and around the lift where unauthorized people are not permitted. Its size accounts for load drop, swing, and potential failure of rigging or ground.

Related: Tag line, Lift plan
Personnel lifting

Carrying a worker in a crane-supported platform or basket. It is high risk, generally requires specific approval, a certified platform, secondary attachment, and a dedicated lift plan.

Related: Critical lift, Lift plan
Lift director

The person with overall responsibility for planning and executing a lift, including verifying setup, rigging, roles, and communications. Authority to stop the lift rests with this role.

Related: Lift plan, Tandem lift, Signal person
Signal person

A designated, competent worker who directs crane motion using standard hand signals, voice, or radio. The operator follows only one signal source at a time, except for an emergency stop from anyone.

Related: Standard hand signals, Emergency stop signal, Lift director
Standard hand signals

An agreed set of arm and hand movements used to command hoist, lower, slew, boom, and stop actions. Signals must be unambiguous, visible to the operator, and understood by all parties before the lift.

Related: Signal person, Emergency stop signal
Emergency stop signal

A signal any person may give to halt crane motion immediately when danger is seen. The operator must obey it regardless of who gives it, then await direction from the designated signal person.

Related: Standard hand signals, Signal person
Competent person

A person who, by training, experience, and qualification, is able to identify hazards and take appropriate corrective action in the work being performed. Legislation assigns specific duties to this role.

Related: Qualified operator, Pre-operational inspection, Lift plan
Qualified operator

A crane operator holding the certification, licence, or permit required by the jurisdiction for the crane class being used. The operator remains responsible for refusing unsafe lifts.

Related: Competent person, Operator logbook
Right to refuse unsafe work

The legal protection allowing a worker to decline a task they reasonably believe is dangerous, without reprisal, until the concern is resolved. It is a core element of occupational health and safety law.

Related: Competent person, Barricade and exclusion zone
Inspection record

A written or electronic entry documenting the date, scope, findings, and sign-off of an inspection. Records demonstrate due diligence and must be kept for the period required by regulation.

Related: Periodic inspection, Operator logbook
Operator logbook

A record maintained for the crane showing operating hours, inspections, defects, repairs, and operating conditions. It supports maintenance scheduling and provides evidence during incident investigation.

Related: Inspection record, Pre-operational inspection
Assembly and disassembly plan

A documented sequence for erecting or dismantling the crane, including component order, rigging, personnel, wind limits, and verification steps. It must follow the manufacturer's instructions and be supervised.

Related: Counterweight, Boom assembly, Load test after assembly
Counterweight

Mass added to the rear of the crane's upper structure to balance the load moment and improve stability. It must be installed exactly as specified and never altered or removed without approval.

Related: Load moment, Assembly and disassembly plan
Boom assembly

The process of connecting boom sections, pins, and rigging to achieve the specified length and configuration. Correct pinning, alignment, and torque are essential to structural integrity.

Related: Assembly and disassembly plan, Load test after assembly
Load test after assembly

A verification lift or test performed after erection to confirm the crane and safety devices function correctly. Results are recorded before the crane is released for service.

Related: Assembly and disassembly plan, Load moment indicator (LMI)
Transport configuration

The specified condition of the crane for road travel, including boom removal or retraction, axle loads, width, and securing of components. It must meet both manufacturer limits and highway regulations.

Related: Assembly and disassembly plan, Counterweight