Mistake 1

Treating the annular seal as a single 'plug the top' step - specifying only a neat-cement surface seal and no continuous annular seal above the screened interval, then answering questions as if the surface seal alone satisfies the standard.

Field habit and cost pressure push crews toward the minimum visible seal, and the surface seal is the only part of the seal the client ever sees. Candidates then carry that habit into scenario items that ask what must separate the casing from the borehole wall over the full interval above the seal.

What to do instead

Memorize the two-part structure: a surface seal of specified thickness and a continuous annular seal extending from below the surface seal down to the top of the seal or screen, placed by a method that keeps the material in contact with both the casing and the formation (tremie or positive displacement, not free-fall dumping). Practice drawing a well cross-section from memory, labeling each seal zone, its purpose, and the placement method, until the diagram is automatic.

Mistake 2

Answering seal-material questions with 'cement' generically, without distinguishing neat cement, sand-cement, bentonite grout, and concrete, or stating the mixing density and the reason each material is chosen.

On the job the material is whatever the pump truck delivered; the candidate never had to justify the choice in writing, so the distinctions blur. Exam items often hinge on which material is acceptable for a given annulus, hole size, or lost-circulation condition.

What to do instead

Build a one-page comparison table: material, typical mix ratio or density range, setting behavior, shrinkage, tolerance for lost circulation, and where it is prohibited or restricted. For each material, write one sentence explaining the failure it prevents. Rehearse the table until you can reproduce it without notes.

Mistake 3

Describing well development only as 'pumping until the water clears' and omitting the specific development methods (surging, jetting, bailing, air-lift, overpumping), the sequence, and the acceptance criteria that end development.

Development is often rushed and judged by eye on site. Without a written criterion, candidates answer with the visual impression rather than the measurable endpoint the standards and specifications expect.

What to do instead

Learn development as method plus endpoint: for each method, state what it removes (drilling fluid filter cake, fines, introduced solids), the energy it applies, and the risk (formation collapse, sand production, screen damage). Then state the acceptance criteria in measurable terms - turbidity, sand content, specific capacity stabilization - and practice writing a short development plan for a hypothetical screened well.

Mistake 4

Treating disinfection as a formula to memorize (chlorine dose and contact time) while ignoring the prerequisites: removing the chlorine demand of the system first, achieving the required residual after contact, and verifying with a bacteriological sample rather than smell.

Disinfection is the last task on a long day and is verified by odor, which is unreliable. Candidates memorize a number without the conditions that make the number meaningful.

What to do instead

Study disinfection as a sequence: clean the well and remove debris, calculate the volume of water in the well and the dose to reach the target concentration, introduce the solution so it contacts the entire column and the pump and piping, hold for the required contact time, pump to waste until the residual falls to the permitted level, then sample. Memorize that a residual measured before contact is meaningless and that verification is a laboratory result.

Mistake 5

Giving the same destruction procedure for every well - filling the entire borehole with one material - without adjusting for well type, casing diameter, screen, annular seal, and whether the well penetrates multiple aquifers or an aquitard.

Abandonment is low-visibility work and the candidate has seen one method used repeatedly. Exam items test whether the candidate can select a seal material and placement for a gravel-packed screened well versus a small-diameter piezometer versus an open borehole.

What to do instead

Create a matrix of well type against destruction method: what is removed (casing pulled or perforated), what sealing material is placed in each interval, how the seal is placed to avoid bridging, and what is placed at the surface. For each row, write the reason the method differs. Then practice converting a described well into the correct row.

Mistake 6

Reporting the well as constructed rather than as actually built - copying design depths, casing lengths, and seal intervals from the permit instead of recording measured values, and omitting changes made in the field.

Paperwork is completed at the end of the job from memory or from the plan, and field changes are treated as minor. Candidates underestimate how heavily the exam tests the accuracy and completeness obligations of the report.

What to do instead

Learn the report as a factual record: measured total depth, casing size, weight, and setting depth, screen or perforation intervals, seal material and the actual interval sealed, static and pumping water levels, yield, and any variance from the permit with its reason. Practice filling a blank report from a narrative field description, then check every field against the narrative.

Mistake 7

Confusing the roles of the state standards and local ordinances - assuming a local agency cannot be stricter, or that complying with the county permit satisfies everything, or conversely that local rules override the state minimums.

Candidates learn one jurisdiction's process and generalize. The relationship between statewide standards and local adoption, and where local requirements may exceed the state minimum, is a frequent source of scenario questions.

What to do instead

State the relationship in one sentence and test yourself on it: statewide standards set a floor, local agencies may adopt more stringent requirements, and the driller must meet both. Then work through three short scenarios - a county requiring a deeper seal, a county silent on a topic, and a conflict - and write the correct compliance answer for each.

Mistake 8

Answering casing design questions by picking a diameter and wall thickness from habit, without connecting the choice to collapse pressure, tensile load, corrosion allowance, driving or installation stresses, and the screen or pump that must fit inside.

Sizing is often inherited from the previous job. Candidates never had to justify the selection against loads, so they cannot evaluate an item that changes the depth, the artesian head, or the installation method.

What to do instead

Work casing selection as a load problem: identify the loads (external collapse from the formation or artesian pressure, internal pressure, tensile load from hanging weight, installation driving), then check the selected casing against each, then verify the inside diameter clears the pump and the screen. Do three hand calculations at different depths and heads and compare the answers.

Mistake 9

Skipping the pre-drilling and site evaluation reasoning - treating the siting question as a matter of convenience and not addressing setbacks from contamination sources, septic systems, property lines, flood-prone areas, and known groundwater conditions.

Siting is decided by the client and the access road, and the driller's role in evaluating it is underappreciated. Exam items test whether the candidate can identify a site condition that should stop or relocate a well.

What to do instead

Learn siting as a checklist of hazards: distance and gradient from septic systems, animal enclosures, fuel storage, chemical handling, and surface water; flooding exposure; and the completion interval relative to known contamination. For each hazard, state the concern and the action (relocate, deepen the seal, refuse). Then practice identifying the disqualifying condition in short site descriptions.

Mistake 10

Approaching pumping-test and yield questions as a single drawdown number, without distinguishing static level, pumping level, drawdown, specific capacity, and the duration and stabilization conditions that make a test result meaningful.

Yield is quoted as a single figure on the report, so the candidate memorizes the figure and not the measurement. Items that change pumping rate or test duration then defeat the memorized answer.

What to do instead

Define each term precisely and relate them: static water level, pumping water level at a stated rate and time, drawdown as the difference, and specific capacity as yield per unit drawdown. Learn that a valid test requires stabilization and a recorded duration and rate. Practice computing specific capacity from paired numbers and explaining why a short test at a high rate overstates the reliable yield.