CTC (NAR): A Ten-Week Commitment on a Twelve-Week Critical Path

CTC · Put your knowledge to work in context.

All case studies

A Ten-Week Commitment on a Twelve-Week Critical Path

You inherit a system migration project with a 10-week deadline from the sponsor. The approved plan has two critical paths because a shared approval, A, and a shared cutover test, G, sit on both. Path 1 is A at 2 weeks, B at 5 weeks, D at 3 weeks, and G at 2 weeks. Path 2 is A at 2 weeks, C at 4 weeks, E at 4 weeks, and G at 2 weeks. Both total 12 weeks. Crashing options: A can be shortened by 1 week for $5,000; B by up to 2 weeks at $4,000 per week; C by up to 2 weeks at $3,000 per week; D by 1 week at $6,000; E by 1 week at $8,000; G by 1 week at $7,000. The vendor says B may slip one week because of a dependency. The sponsor wants a firm 10-week commitment and has already promised the date to a customer. Your team has no float and one shared test environment.

1. Calculate the least-cost way to reach 10 weeks, showing why crashing the cheapest activity alone is insufficient.

Read the worked answer

Both paths start at 12 weeks, so the project needs two weeks removed from each path. Because A and G are shared, shortening either one reduces both paths. Shortening B or D affects only Path 1; shortening C or E affects only Path 2.

The least-cost options at $12,000 are:

Option Cost Path 1 Path 2
A 1 week + G 1 week $5k + $7k = $12k 10 10
A 1 week + B 1 week + C 1 week $5k + $4k + $3k = $12k 10 10
B 2 weeks + C 2 weeks $8k + $6k = $14k 10 10

Crashing only B, the cheapest per-week activity, fails because Path 2 stays at 12 weeks, so the project does not finish earlier. Crashing only shared A by one week also fails because both paths remain at 11 weeks.

Between the two $12k options, I would choose A + B + C if G's weekend cutover test is technically risky or the client cannot support it, because it avoids compressing the shared acceptance gate. I would choose A + G if the B vendor dependency is unstable, because A + B + C relies on B's crash being real. Either way, the minimum crash cost is $12k, not the $14k naive path-by-path solution. With B's possible one-week slip, the required crash budget rises to about $16k, so the commitment needs a contingency.

2. What should you tell the sponsor about the 10-week commitment, and what risk response and tracking would you put in place?

Read the worked answer

I would not give an unconditional yes. I would say: 'I can commit to 10 weeks only with $12k of crash funding and two conditions: the G cutover slot is confirmed, and the vendor stabilizes B. Without those, the defensible commitment is 11 weeks or a phased cutover.' That is more credible than a date the team cannot protect, especially when the sponsor has already promised it to a customer.

Risk responses: avoid by freezing scope and deferring non-critical features; mitigate the vendor dependency with a written milestone and weekly checkpoint; mitigate the test-environment constraint by booking a dedicated window and defining a fallback environment; transfer schedule risk through vendor penalties if the contract allows; and accept residual risk with a management reserve of about $4k because B may slip. I would set a trigger at the week-3 vendor checkpoint: if B has not recovered, either release the reserve or re-baseline to 11 weeks.

Tracking: a two-path burn-down chart updated twice weekly, daily stand-ups on A, B, C, and G, a visible critical-path owner, and a change-control rule that any new scope requires a sponsor decision. I would report P50 and P80 dates rather than a single date. If the sponsor insists on an unconditional 10 weeks, I would document the assumptions and the residual risk in the decision record so the commitment is not silently transferred to the delivery team.