Engagement Planning

  • Objectives state what the engagement will accomplish; they must be consistent with the audit plan and address risks, controls, and governance of the activity under review.

  • Scope must be sufficient to satisfy the objectives and covers systems, records, personnel, physical property, and the time period; scope limitations are disclosed in the final communication.

  • A complete engagement plan documents objectives, scope, timing, budgeted hours, staffing, an understanding of the activity, the risk assessment, and the work program.

  • The work program lists the procedures to be performed; it is approved by the CAE or designee before work begins, and any change is documented with its reason and approval.

  • Engagement-level risk assessment weighs likelihood and impact and considers fraud exposure, IT dependency, third parties, recent changes, complexity, and prior findings.

  • Engagement criteria - the standards or expectations used to evaluate condition - are identified during planning so that findings are judged against an agreed benchmark.

  • Materiality sets the depth of testing and the threshold for reporting; lowering materiality increases the nature, timing, and extent of procedures.

  • Due professional care means the competence and care of a reasonably prudent auditor, not infallibility; procedures are weighed against their cost and benefit.

Quick reference

Engagement Execution

  • Evidence must be sufficient, reliable, relevant, and useful; failing any one attribute weakens the support for the engagement's conclusions.

  • Reliability hierarchy: independent external sources over internal; original documents over copies; direct auditor observation over indirect report; strong source controls over weak.

  • Workpapers record procedures performed, information obtained, analysis, and conclusions; they are the organization's property and are retained per policy and legal requirements.

  • Workpaper quality criteria: complete, accurate, clear, legible, properly indexed, cross-referenced, and prepared on a timely basis.

  • Supervisory review is documented before the final communication is issued, with evidence of the reviewer's identity, date, and the extent of the review.

  • In attribute sampling, sample size increases when confidence level rises or the tolerable deviation rate falls; precision is the allowance for sampling risk.

  • Analytical procedures compare current data with prior periods, budgets, or industry norms, use a defined investigation threshold, and require documented explanations for significant variances.

  • Fraud indicators - missing documents, unusual journal entries, control overrides, unexplained lifestyle changes - call for expanded procedures and escalation, not confrontation by the auditor.

Quick reference

Engagement Communication

  • The final communication includes objectives, scope, results, conclusions, and recommendations or action plans; if objectives or scope are omitted, the reason is disclosed.

  • Seven quality attributes apply to every communication: accurate, objective, clear, concise, constructive, complete, and timely.

  • The CAE approves distribution of the final report; recipients are those able to ensure results receive due consideration, subject to confidentiality requirements.

  • Auditee disagreement is not suppressed: dissenting views may be included in the report alongside the auditor's position and supporting evidence.

  • Interim reports are issued when a significant matter requires prompt attention and never replace the final engagement communication.

  • An overall conclusion or opinion is expressed only when supported by sufficient, reliable, relevant, and useful evidence, and it uses a defined rating scale.

  • Recommendations should address root causes and be paired with a management action plan naming a responsible owner and a target completion date.

  • If a final report contains a material error or omission, a corrected report is issued to every recipient of the original version.

Quick reference

Engagement Monitoring

  • Follow-up verifies that management actions were implemented effectively or that senior management has accepted the risk; the CAE establishes and monitors this process.

  • Follow-up is risk-based: findings with higher risk exposure and larger potential impact are tracked more frequently and escalated sooner.

  • Significant findings that remain unresolved after the agreed timeline are escalated to senior management, and ultimately to the board.

  • Unresolved prior findings are re-evaluated during planning and can change the scope, objectives, and risk assessment of the next engagement.

  • Supervision is ongoing monitoring inside an engagement: approving the work program, reviewing evidence, resolving problems, and confirming staff competence.

  • Engagement performance measures include budget versus actual hours, cycle time, recommendation implementation rate, and stakeholder feedback.

  • The quality assurance and improvement program combines ongoing and periodic internal assessments with an external assessment at least once every five years.