Armour Damage at an Exposed Rubble-Mound Breakwater
A rubble-mound breakwater protects a small-craft harbour on an exposed coast. The seaward slope is 1:2, the crest is at +7.5 m CD and the toe sits on the seabed at -6.0 m CD. The design significant wave height at the structure is 5.5 m with a peak period of 12 s, and waves break over an outer shoal before reaching the trunk. The armour layer is two layers of quarried rock with a median mass of 4.0 t and a density of 2,650 kg/m³. After a storm estimated at a 20-year return period, 60 stones have been displaced along a 120 m length, mostly at and just above still-water level; the underlayer is exposed and there is a 1.2 m deep scour hole at the toe. The nearest quarry can supply up to 6 t; larger rock must be hauled 400 km at 2.6 times the unit cost. Precast concrete cubes can be produced locally. The client asks whether to repair with the same 4 t rock, order larger rock, or switch to concrete units, and whether the toe is the real problem.
1. Check the existing armour size against the design wave using the Hudson relation and explain why the structure has nevertheless survived for years.
Read the worked answer
Hudson check. W = ρr·H³ / (KD·Δ³·cotθ), with ρr = 2,650 kg/m³, ρw = 1,025 kg/m³, Δ = 1.585, Δ³ = 3.98, cotθ = 2.
- For H = 5.5 m and KD = 2 (rock, no damage): W = 2,650 × 166.4 / (2 × 3.98 × 2) = 440,900 / 15.9 ≈ 27.7 t.
- Depth-limited check: at a toe depth of 6.0 m the maximum wave at the structure is roughly 0.78 × 6.0 ≈ 4.7 m, giving W ≈ 2,650 × 103.8 / 15.9 ≈ 17.3 t.
- Reverse the equation for the 4.0 t stone: H = (4,000 × 15.9 / 2,650)^(1/3) ≈ 2.9 m.
On any reading the 4 t armour is between 3 and 6 times too light for a no-damage design at this wave height, and corresponds to a stable sea state of about 2.9 m.
Why has it survived? Several possibilities, and the honest answer is that we cannot yet distinguish them:
- The design H may be an offshore or deep-water value rather than the height at the toe; if the real toe height is 3.5–4.0 m, 4 t rock is marginal but not absurd.
- KD = 2 is conservative. Non-breaking, non-overtopping rock can carry KD = 4; with H = 4.7 m that would still call for about 8.6 t.
- The 20-year storm may not have been the design event; the structure may be living on borrowed time and the recent damage is the first sign.
Critical clarification before any repair design: confirm whether 5.5 m is Hsig or H1/10, and at what location. Using Hsig where the KD table assumes H1/10 under-predicts by about 2× in weight. The damage pattern - waterline concentrated - also points at breaking-wave attack and toe scour rather than uniform overloading, which is a separate design issue.
2. Compare repair with 4 t rock, larger rock from the distant quarry, and concrete cubes, and recommend an armour solution.
Read the worked answer
Capacity of each candidate (H for no damage, cotθ = 2 unless noted, from H = (W·KD·Δ³·cotθ/ρr)^(1/3)):
| Option | KD | Stable H |
|---|---|---|
| Existing 4 t rock | 2 | 2.9 m |
| 6 t rock (local maximum) | 2 | 3.3 m |
| 6 t rock, slope flattened to 1:3 | 2 | 3.8 m |
| 12 t rock (400 km haul) | 2 | 4.2 m |
| 20 t rock (400 km haul) | 2 | 4.9 m |
| 4 t concrete cube | 8 | 4.6 m |
| 6 t concrete cube | 7 at 1:2 | 5.2 m |
| 6 t concrete cube, slope 1:2.5 | 8 | 5.6 m |
Assessment.
- Same 4 t rock: not a repair, a repeat. The exposed underlayer will strip in the next storm and the damage will propagate.
- 6 t local rock: still only stable to about 3.3 m; even with a flatter slope it does not cover the design event. It is a temporary measure at best.
- Large rock: to reach 5.5 m needs roughly 28 t, which is beyond normal quarry production, requires 400 km haulage at 2.6× unit cost, and needs plant that may not be available. Rejected.
- Concrete cubes: 6–7 t units on a 1:2.5 slope cover the design condition at KD 8, are locally produced, and can be placed by the same plant. The weight is manageable and the units can be designed with a specific gravity and interlock suited to the site.
Recommendation.
- Rebuild the damaged 120 m with 6–7 t concrete cubes on a 1:2.5 seaward slope, with a correctly sized two-layer underlayer (W/10 and W/15) and a properly founded toe berm.
- Keep rock on the less exposed sections, but armour the exposed length consistently - mixed armour along a trunk creates weak points.
- Verify with a physical model test covering overtopping, toe stability and wave breaking on the foreshore, because Hudson says nothing about any of those.
- Before the next storm season, place temporary 1–3 t rock over the exposed underlayer and fill the scour hole - an emergency measure, not a design.
3. Is the toe the real problem? Design the toe protection and set out a repair sequence.
Read the worked answer
Yes, probably the proximate cause. The evidence supports it:
- 1.2 m of scour at the toe means the armour has lost its support and can rotate and settle seaward; displaced stones at the waterline are often the visible end of a toe failure, not its beginning.
- A 1:2 slope with the toe only 6 m below still-water level sits in the breaking zone; plunging waves and reflection scour the seabed directly in front of the structure.
- Once scour lowers the bed, the effective water depth at the toe increases and the waves reaching the armour get larger, so damage accelerates.
Toe design principles.
- Toe berm of 1–3 t rock, at least two layers thick and with a crest width of at least three armour diameters, founded on a geotextile or granular filter.
- Extend the berm to below the credible scour depth - at least 1.5 × the observed 1.2 m, so a base at about −8 m CD unless the toe is raised instead.
- Check toe stability with the depth-limited wave at the scoured depth, not the design depth, and check that the berm does not simply sink into the mobile bed.
- Consider raising the toe and flattening the lower slope; a 1:3 lower slope is cheaper than adding armour weight.
Repair sequence.
- Immediate (before next storm season): place 1–3 t rock to fill the scour hole and cover the exposed underlayer along the 120 m; survey and record as-built.
- Design: physical model of the toe and armour; finalise cube size, underlayer, berm geometry and crest level, including overtopping discharge against the acceptable limit for the harbour behind.
- Construction: work in the calm season, from the seaward side with a crane and split barges, building the toe berm first so the armour always has support; do not place armour from the crest downward onto an unsupported toe.
- Post-repair: annual bathymetric survey of the toe, plus a survey after every significant storm, with a documented trigger for topping up the berm.