Registered Civil Engineer (Port & Waterway) flashcards
Registered Civil Engineer (Port & Waterway) · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Design vessel
- The largest or governing ship a port facility must accommodate; its length overall, beam, draft, and displacement set berth dimensions, channel depth, and structural loads.
- Under-keel clearance
- Vertical gap between a vessel's keel and the seabed, covering squat, wave response, tide prediction error, and siltation; typically 10-15% of draft with a minimum absolute value.
- Squat
- Ship sinkage caused by flow acceleration beneath the hull in shallow or confined water; increases with speed squared and is largest when depth-to-draft ratio is small.
- Shields parameter
- Dimensionless bed shear stress θ = τ/((ρs-ρ)gD); sediment motion begins near a critical value of about 0.05 for uniform sand.
- Wave shoaling
- Reduction in wavelength and increase in wave height as waves enter shallow water; energy flux is conserved until breaking, when H/d reaches roughly 0.78.
- Littoral drift
- Longshore sediment transport driven by oblique wave breaking; the CERC formula scales transport with wave height to the 5/2 power times the sine of twice the breaker angle.
- Undrained shear strength
- Shear strength of saturated fine-grained soil under no drainage, denoted su; measured by UU triaxial, vane shear, or estimated from CPT as qc divided by Nk.
- p-y curve
- A relationship between soil resistance per unit pile length and lateral pile deflection, used to analyze laterally loaded piles; curves differ by soil type and depth.
- Liquefaction screening
- Assessment comparing cyclic stress ratio from design earthquake to cyclic resistance ratio from penetration tests; loose saturated sands with low (N1)60 are most vulnerable.
- Berthing energy
- Kinetic energy absorbed by fenders, E = 0.5·Cs·Md·Vb², where Cs is an eccentricity factor, Md the virtual mass, and Vb the berthing velocity.
- Apron width
- The strip between the quay edge and the first shed or stack area; must accommodate crane rails, truck lanes, and container handling equipment.
- Bollard spacing
- Longitudinal distance between mooring bollards along a quay, commonly 15-30 m; set by vessel size, mooring line angles, and line load limits.
- Cutter suction dredger
- Dredger that cuts stiff or compacted soils with a rotating cutter head and pumps the loosened material as a slurry, often directly to a reclamation area.
- Trailing suction hopper dredger
- Self-propelled vessel that drags suction pipes along the seabed to load loose sediments into hoppers, then transports and discharges them at a disposal or reclamation site.
- Swell factor
- Ratio of loosened dredged or excavated volume to in-situ volume; roughly 1.05-1.15 for sand and 1.2-1.4 for clay, used for transport and fill quantity estimates.
- Hudson formula
- Empirical equation for rubblemound armor weight W = ρr·H³/(KD·Δ³·cotθ), where KD depends on armor unit type and acceptable damage level.
- Breakwater overtopping
- Wave runup and splash passing over a breakwater crest; controlled by crest height, armor slope, and wave conditions, and affects harbor tranquility and safety.
- Lock chamber dimensions
- Usable length, width, and depth of a lock chamber, set by design vessel size plus clearance for fenders, mooring, and water-level variation during filling.
- Ship lift
- A mechanical structure that raises or lowers vessels in a caisson or counterweighted chamber between water levels; efficient for large lifts but limited by chamber size.
- CEMT navigation class
- European classification of inland waterways by vessel dimensions, defining minimum channel depth, width, and bridge clearance for each class.
- River training works
- Structures such as groynes, training walls, and revetments that guide flow, maintain a navigable low-flow channel, and protect banks from erosion.
- Flow-duration curve
- Cumulative frequency plot of discharge versus percentage of time exceeded; used to assess low-flow availability and navigable discharge for inland waterways.
- Jack-up platform
- Mobile offshore unit with legs lowered to the seabed to lift the hull above water, providing a stable work platform for piling, drilling, or construction in shallow water.
- Driveability analysis
- Wave-equation modeling of pile driving that predicts blow counts, stresses, and refusal risk for a given hammer and soil profile before construction.
- Earned value management
- Project control method comparing planned value, earned value, and actual cost; cost performance index CPI = EV/AC and schedule performance index SPI = EV/PV.
- Weather window
- Period when sea state and wind are within workable limits for a marine operation; workability limits depend on the vessel and activity, such as crane or diving work.
- Environmental impact assessment
- Formal process of scoping, baseline study, impact prediction, mitigation design, and monitoring for major port, dredging, or waterway projects before approval.
- London Convention
- International treaty regulating disposal of wastes at sea; dredged material disposal requires sediment testing and permits under the convention and its protocol.
- MARPOL
- International convention preventing pollution from ships, covering oil, noxious liquids, sewage, garbage, and air emissions including sulfur limits.
- Benefit-cost ratio
- Ratio of discounted project benefits to discounted costs; a value above one indicates economic viability, and incremental ratios rank mutually exclusive alternatives.
- Life-cycle cost
- Total discounted cost of construction, operation, maintenance, repair, and residual value over a project's life; used to compare long-lived marine infrastructure alternatives.
- Professional seal
- Engineer's stamp on drawings and reports certifying competence and responsibility; applied only within the engineer's qualified area of practice and jurisdiction.