Registered Civil Engineer (Port & Waterway): Construction Methods, Marine Equipment and Project Management

Registered Civil Engineer (Port & Waterway) · Work through your exam, one topic at a time.

All guide sections

Construction Methods, Marine Equipment and Project Management

Marine construction questions test plant selection, method sequencing, measurement rules, and the contractual management of weather and ground risk.

Marine plant and methods

  • Piling runs from jack-up platforms or floating barges with templates; vibratory hammers for sheet piles, hydraulic impact hammers for bearing piles, with set criteria from dynamic testing or restrike.
  • Concrete underwater is placed by tremie from the bottom up with the pipe kept embedded; never free-fall concrete through water.
  • Caissons and cofferdams need sinking and ballasting control, sealing checks, and a dewatering check against uplift.
  • Rock and armour placement uses fallpipe vessels for accuracy and side-dump for bulk; positioning by DGPS with tolerance stated per layer.

Measurement and payment

  • Dredging may be measured in situ by before-and-after survey, in the hopper, or in barges; each yields a different number because of bulking and overflow losses, so read the specification before pricing.
  • Reclamation fill is often paid on placed compacted volume; subsoil settlement risk usually sits with the employer, construction tolerances with the contractor.

Programme and cost control

  • Critical path and float: weather downtime belongs in the programme as a probabilistic allowance, not as a fixed line item added at the end.
  • Earned value: CPI = EV/AC and SPI = EV/PV; a CPI below 1 means each unit of work costs more than planned.
  • Risk allocation: ground conditions, wave climate and permitting delays are the classic dispute areas on marine contracts.

Worked example

A piling package: planned value PV = 1,000 units, earned value EV = 800, actual cost AC = 900. CPI = 800/900 = 0.89, so work costs 12% more per unit than planned. SPI = 800/1,000 = 0.80, so 20% of planned work is not yet done. Forecast cost at completion = BAC/CPI = 1,000/0.89 ≈ 1,124 units - valid only if the variance is systemic rather than a one-off, which is the judgement the question expects you to state.

Traps

  • Comparing dredging volumes measured on different bases without conversion factors.
  • Programming zero weather downtime and claiming it later as a variation.
  • Quoting CPI and SPI without stating the baseline or whether the variance is typical.