Consulting Engineer · Keep the key ideas within reach.

Quick reference

Project and Program Management

  • Earned Value: CV = EV − AC; SV = EV − PV; CPI = EV/AC; SPI = EV/PV. Negative CV or SV means cost overrun or schedule slippage against the baseline.

  • Estimate at Completion: EAC = BAC/CPI when current cost efficiency is expected to persist; EAC = AC + (BAC − EV) when remaining work is expected to proceed at the planned rate.

  • To-Complete Performance Index: TCPI = (BAC − EV)/(BAC − AC) for budget-constrained work; a TCPI above 1.0 means the team must outperform the plan to finish within budget.

  • Critical path is the longest duration path through the network; it has zero total float. Total float = LS − ES = LF − EF. Free float is delay possible without moving any successor's early start.

  • Program management coordinates related projects for consolidated benefit; a project manager optimizes one project's triple constraint, while a program manager arbitrates shared resources and inter-project dependencies.

  • Scope change control: any change to the approved scope baseline passes through integrated change control, producing a change request, impact assessment across scope, schedule, cost, and risk, then approval or rejection.

  • RACI matrix rules: exactly one Accountable per activity; Responsible does the work; Consulted is two-way input; Informed is one-way notification. Multiple Accountable owners create ambiguity.

  • Risk response selection: avoid eliminates the threat, mitigate reduces probability or impact, transfer shifts financial consequence (insurance, fixed-price contract), accept retains exposure with a contingency reserve.

  • Schedule compression: crashing adds resources to critical-path activities at added cost; fast-tracking overlaps sequential activities and adds rework risk. Neither shortens non-critical paths.

Quick reference

Business and Financial Management

  • Net Present Value: NPV = Σ CFt/(1+r)^t − initial investment. Accept independent projects with NPV > 0; among mutually exclusive projects, select the highest NPV.

  • Internal Rate of Return is the discount rate making NPV = 0. IRR can mislead for non-conventional cash flows or when project scale differs; NPV is the primary decision rule.

  • Payback period ignores cash flows after the cutoff and the time value of money; discounted payback corrects for discounting but still ignores post-payback value.

  • Profitability Index = PV of future cash flows / initial investment. PI > 1.0 is acceptable; it ranks projects under capital rationing but can favor small projects.

  • Weighted Average Cost of Capital: WACC = (E/V)·Re + (D/V)·Rd·(1 − tax rate). It is the hurdle rate for projects of average risk; riskier projects warrant a higher discount rate.

  • Break-even quantity = Fixed costs / (Unit price − Unit variable cost). Operating leverage rises with fixed-cost share, amplifying the sensitivity of profit to volume changes.

  • Sunk costs are excluded from incremental analysis; opportunity costs and incremental cash flows, including working capital changes and tax effects, are included.

  • Depreciation is non-cash but shields taxable income. Under straight-line, annual depreciation = (Cost − Salvage)/Useful life; accelerated methods raise early-year tax shields.

Quick reference

Technical and Engineering Analysis

  • Unit consistency is mandatory before any calculation: convert to a coherent system (SI or US customary) and carry units through every step to catch dimensional errors.

  • Significant figures: multiplication and division retain the least number of significant figures in the inputs; addition and subtraction retain the least number of decimal places.

  • Root-sum-square combination applies to independent random uncertainties: u_total = √(u1² + u2² + …). Systematic or correlated errors are added linearly, not in quadrature.

  • Design factor (safety factor) = failure strength / allowable stress. A higher design factor covers greater uncertainty in loads, material properties, and consequences of failure.

  • First law for a steady-flow open system: Q − W = ṁ[(h2 − h1) + (V2² − V1²)/2 + g(z2 − z1)]. Neglect kinetic and potential terms only when justified by magnitude.

  • Beam deflection scales with span to the fourth power for a uniformly loaded simply supported beam (δ = 5wL⁴/384EI); doubling span increases deflection about sixteenfold.

  • Sensitivity analysis identifies which input most affects the output; a tornado diagram ranks variables by swing. Monte Carlo simulation propagates input distributions to an output distribution.

  • Model validation asks whether the model represents the real system for its intended use; verification asks whether the model was implemented correctly. They are distinct checks.

Quick reference

Regulatory, Legal, and Ethical Practice

  • Standard of care for professional services is the degree of care and skill ordinarily exercised by members of the profession under similar circumstances, not a guarantee of perfect results.

  • Negligence requires four elements: a duty of care owed, a breach of that duty, causation (actual and proximate), and damages. Missing any element defeats the claim.

  • A fixed-price contract shifts cost-overrun risk to the seller; a cost-reimbursable contract shifts it to the buyer, usually with a fee and a cost ceiling.

  • Contract formation requires offer, acceptance, consideration, and mutual assent; a counteroffer operates as a rejection of the original offer.

  • Conflict of interest rules require disclosure and, where the conflict is material, written consent or withdrawal. Undisclosed conflicts undermine the independence on which professional advice relies.

  • Public safety paramountcy: when a client instruction would create an unacceptable risk to public health or safety, the engineer must refuse, document the objection, and escalate as required.

  • Records retention and privilege: mark legal-hold documents, avoid destroying records once litigation is reasonably anticipated, and route privileged communications only to counsel.

  • Licensure is jurisdiction-specific; practicing or sealing work outside one's licensed scope is a legal violation even when technically competent.

Quick reference

Client and Stakeholder Relations

  • Stakeholder power/interest grid: high power–high interest are manage closely; high power–low interest are keep satisfied; low power–high interest are keep informed; low–low are monitor.

  • Requirements elicitation separates stated wants from underlying needs; confirm each requirement in writing and trace it to a design element or deliverable.

  • Communication plan defines audience, message, channel, frequency, and owner. Escalation paths and decision rights should be agreed before disputes arise.

  • Expectation management: document assumptions and exclusions in the proposal and contract; unstated assumptions become disputed scope later.

  • Active listening techniques-paraphrasing, summarizing, and open questions-reduce misunderstanding; confirm verbal agreements with written minutes distributed promptly.

  • Change in client priorities is handled through the change control process, not informal side agreements; quantify schedule, cost, and quality impact before acceptance.

  • Confidentiality: client information is used only for the engagement, shared on a need-to-know basis, and protected after the engagement ends.

  • Handling dissatisfaction: acknowledge the concern, gather facts, propose a remedy with a timeline, and record the resolution. Escalation to senior management should be planned, not reactive.

Quick reference

Quality, Safety, and Risk Management

  • Quality assurance is process-focused and preventive; quality control is product-focused and detective (inspection, testing). QA aims to prevent defects that QC would otherwise find.

  • Risk score = Probability × Impact. Prioritize by score; reserve contingency for known risks and management reserve for unknown-unknowns.

  • Hierarchy of controls, most to least effective: elimination, substitution, engineering controls, administrative controls, personal protective equipment.

  • ALARP principle: risks are reduced so far as is reasonably practicable; residual risk must be documented and accepted by the accountable authority.

  • PDCA (Plan-Do-Check-Act) drives continuous improvement; root-cause tools include the 5 Whys and fishbone (Ishikawa) diagrams.

  • Risk register fields: ID, description, cause, trigger, probability, impact, score, owner, response strategy, residual risk, and status.

  • Incident investigation seeks root causes, not blame; corrective actions must be tracked to closure and verified for effectiveness.

  • Quality cost categories: prevention and appraisal costs are conformance costs; internal and external failure costs are nonconformance costs, with external failure typically the most expensive.