CO Land Surveyor study materials
CO Land Surveyor study resources

CO Land Surveyor cheat sheet

CO Land Surveyor · Keep the key ideas within reach.

Quick reference

Boundary Surveying and Retracement

  • Retracement follows the footsteps of the original surveyor; it does not re-establish lines by proportionate measure unless the original monuments are lost and the record evidence supports it.

  • Priority of evidence: natural monuments, then artificial monuments, then courses and distances, then area (federal rule). Intent of the original parties controls over mathematical precision.

  • A boundary line is fixed where the original monument stood; subsequent movement or destruction does not move the legal line.

  • Adverse possession in Colorado requires 18 years of actual, adverse, open, notorious, exclusive, and continuous possession; payment of taxes is not a statutory element but is evidence of claim.

  • Unwritten rights such as prescriptive easements require 18 years of adverse use; easements by necessity arise from unity of title and strict necessity, not convenience.

  • Ambiguity in a deed is construed against the grantor; a call for a monument generally prevails over a call for a distance or area.

  • Corner search: check the record, plat, and field notes, then search for original evidence within a reasonable radius; accept the best available evidence and document all found and set monuments.

  • Occupational lines and possession lines may define practical boundaries but do not, standing alone, override the written deed description.

  • A boundary survey should show the record description, the measured position, found monuments, and any discrepancy; the client must understand that a survey is an opinion, not a guarantee of title.

Quick reference

Cadastral Surveying and Public Land Survey System

  • The PLSS is based on principal meridians and base lines; Colorado has several, including the Sixth Principal Meridian and the New Mexico Principal Meridian, plus other principal meridians in the state.

  • Townships are 6 miles square, containing 36 sections of 1 square mile (640 acres); sections are numbered boustrophedon from the northeast corner, 1 through 36.

  • Standard parallels (correction lines) and guide meridians limit the accumulation of error; standard parallels are generally every 24 miles north of the base line.

  • Section corners include standard corners, closing corners, quarter-section corners, and meander corners; meander corners are set at the intersection of survey lines with navigable water bodies.

  • A regular quarter-section corner is at the midpoint of a section line; a closing corner is set where a surveyed line closes on a previously established line and may not be at midpoint.

  • The 1873 and later rules: when original corners are lost, re-establish by proportionate measurement between the nearest existing original corners, preserving the record of the original survey.

  • Fractional lots along navigable waters or reservation boundaries are numbered and their areas computed from the actual meander lines, not from 40-acre nominal divisions.

  • Subdivision of a section: quarter sections by quarter-quarter corners; the center quarter-section corner is common to four quarter sections and is set at the intersection of lines connecting opposite quarter-section corners.

  • A cadastral survey by the BLM is an official survey; private surveys retracing federal corners must follow the 2009 Manual of Surveying Instructions and report discrepancies to the BLM.

Quick reference

Geodetic and Control Surveying

  • NAD83 (2011) and NATRF2022 are horizontal datums; NAVD88 is the vertical datum, realized through tidal benchmarks and replaced by NAPGD2022. Datum tags must accompany every coordinate.

  • SPCS83 in Colorado uses Lambert Conformal Conic projections with zones North, Central, and South; scale factor combines grid scale and elevation (sea-level) factor.

  • Grid distance = ground distance × combined factor, where combined factor = grid scale factor × elevation factor; elevation factor ≈ R/(R + h) using mean Earth radius.

  • State plane coordinates are grid coordinates, not ground coordinates; a surveyor must state whether distances shown are grid or ground and apply the combined factor to convert.

  • GNSS static observations yield geodetic coordinates; OPUS solutions provide NAD83 (2011) coordinates and orthometric heights with reported accuracies.

  • Geoid models (GEOID18, and newer) convert ellipsoid heights to orthometric heights: H = h − N, where N is the geoid undulation.

  • A control network should have redundant observations and a least-squares adjustment; report reference variance, standard deviations, and error ellipses.

  • Traverse closure: linear misclosure divided by total traverse length gives relative precision; angular misclosure is compared with allowable error based on the number of angles.

  • Monument stability and centering errors dominate short-baseline GNSS work; use longer occupations and check ties to published control before accepting a network.

Quick reference

Survey Measurement and Computation

  • Coordinate geometry: northing = distance × cos(azimuth), easting = distance × sin(azimuth); inverse computes azimuth and distance from coordinate differences.

  • Azimuths are measured clockwise from north; bearings are measured from north or south toward east or west and must state the quadrant.

  • Traverse area by coordinates (shoelace): 2A = Σ(Xi × Yi+1 − Xi+1 × Yi), taken in order around the traverse; the sign indicates direction.

  • Curve formulas: tangent T = R tan(Δ/2); length L = RΔ (Δ in radians); chord C = 2R sin(Δ/2); external E = R(sec(Δ/2) − 1); middle ordinate M = R(1 − cos(Δ/2)).

  • Degree of curve: arc definition D = 5729.578/R; chord definition D = 2 arcsin(50/R). Colorado highway work typically uses arc definition.

  • Vertical curves: parabola with rate of change r = (g2 − g1)/L; elevation at distance x: y = g1x + rx²/2; high or low point where slope equals zero.

  • Leveling: elevation difference = backsight − foresight; loop misclosure is distributed in proportion to distance or number of setups; curvature and refraction correction ≈ 0.0206 D² (D in hundreds of feet).

  • Least-squares adjustment distributes residuals by observation weights; weights are inversely proportional to variance, and a blunder check should precede adjustment.

  • Measurement uncertainty: report standard deviations and confidence intervals; 95% confidence uses a coverage factor of about 1.96 for normal distributions.

Quick reference

Land Development and Construction Surveying

  • Construction staking converts design coordinates to field positions; check design coordinates against control and report any discrepancy before staking.

  • Horizontal and vertical control must be established and held; benchmarks and traverse points should be set outside the construction limit of disturbance.

  • Subdivision plats in Colorado are governed by municipal or county subdivision regulations and must be prepared by or under the supervision of a licensed land surveyor.

  • Floodplain and drainage design rely on FEMA FIRM data; elevations are referenced to NAVD88 and must match the datum used in the design.

  • ADA accessibility and drainage grades require precise control: typical minimum slope for paved surfaces is 1% to 2%, and ponding must be avoided.

  • Machine control and GPS-guided grading require a site calibration tying design coordinates to local control; verify calibration residuals before production work.

  • As-built surveys compare constructed improvements with design; report deviations and verify that monumentation and easements are in place.

  • Easement and right-of-way lines must be staked and shown on improvement plans; utility conflicts are identified through record research and potholing.

  • Colorado requires a surveyor's seal and signature on plats and reports; unlicensed practice is prohibited under Title 12, Article 120, C.R.S.

Quick reference

Professional Practice, Ethics, and Colorado Law

  • Colorado licenses land surveyors through the State Board of Licensure for Architects, Professional Engineers, and Professional Land Surveyors under Title 12, Article 120, C.R.S.

  • Licensure requires education, experience, and examination; a licensed surveyor must obtain continuing professional development hours each renewal cycle as set by the Board.

  • Sealing and signing work: a licensee may seal only work they performed or directly supervised; sealing work beyond competence is a violation.

  • The surveyor's duty runs to the public health, safety, and welfare; conflicts of interest must be disclosed, and contingent fees that compromise professional judgment are prohibited.

  • Colorado boundary surveys must be filed with the county in specified circumstances, and plats and monument records are public records.

  • A land surveyor may not practice law; title opinions and legal interpretations of deeds should be referred to counsel, though boundary evidence analysis is surveying.

  • Confidentiality: client information is not disclosed without consent except as required by law or to prevent serious harm.

  • Competence and supervision: field and office work must be performed under responsible charge; unlicensed staff may perform tasks but not sign or seal.

  • Statutory and professional standards require accurate records, monument perpetuation, and reporting of errors; falsifying field data is grounds for discipline.