Question 1Project Management and Administration
On a construction project, the contractor's baseline schedule shows a planned earned value of $400,000 at the end of month four, but actual earned value is $360,000 and actual cost is $390,000. What is the cost performance index, and what does it indicate?
- CPI = 0.92, indicating the project is over budget for work performed Correct answer.
- CPI = 1.11, indicating the project is ahead of schedule
- CPI = 0.90, indicating the project is behind schedule
- CPI = 1.08, indicating the project is under budget
Explanation
CPI equals earned value divided by actual cost, so $360,000 divided by $390,000 yields approximately 0.92. A CPI below 1.0 means each dollar spent is buying less than a dollar of earned value, so the work accomplished is costing more than planned. Schedule status is measured separately by the schedule performance index.
Question 2Project Management and Administration
A constructor is preparing a project execution plan and must document how changes to the scope of work will be authorized and priced. Which project management document primarily governs this?
- The communications matrix
- The change management plan Correct answer.
- The risk register
- The project charter
Explanation
The change management plan defines the process for submitting, evaluating, approving, and pricing changes to scope, schedule, or contract value. It identifies who has authority to approve changes and how impacts are documented. The charter authorizes the project but does not detail change procedures.
Question 3Project Management and Administration
During construction, the owner directs the contractor to add a fourth floor to a building already under construction. Under a standard fixed-price contract, how should the contractor typically proceed?
- Refuse the work because the contract scope is fixed
- Perform the work and absorb the cost as a field condition
- Proceed with the work and submit a claim at final completion
- Obtain a written change order defining scope, price, and time impact before proceeding Correct answer.
Explanation
A directed scope change should be documented through the contract's change order process, which establishes the revised price and time before or as the work proceeds. Proceeding without written authorization risks nonpayment and disputes over entitlement. Refusing outright ignores the owner's right to direct changes within the contract terms.
Question 4Project Management and Administration
A project manager is building a network diagram and needs to identify the longest path through the activities to determine the minimum project duration. Which technique is being applied?
- Monte Carlo simulation
- Critical path method Correct answer.
- Resource leveling
- Fast tracking
Explanation
The critical path method calculates the longest sequence of dependent activities through the network, which sets the shortest possible project duration. Activities on that path carry zero total float and drive the completion date. Resource leveling and fast tracking are schedule adjustment techniques applied after the network is analyzed.
Question 5Project Management and Administration
An activity has an early start of day 10, an early finish of day 16, a late start of day 14, and a late finish of day 20. What is the total float of this activity?
- 10 days
- 4 days Correct answer.
- 6 days
- 2 days
Explanation
Total float equals late start minus early start, or late finish minus early finish. Here 14 minus 10 equals 4 days, and 20 minus 16 also equals 4 days. This is the amount the activity can slip without delaying the project finish.
Question 6Project Management and Administration
A general contractor is evaluating a subcontractor bid and wants to transfer the risk of a subcontractor's defective workmanship. Which contract provision most directly accomplishes this?
- An indemnification and warranty clause Correct answer.
- A force majeure clause
- A liquidated damages clause
- A time-is-of-the-essence clause
Explanation
Indemnification and warranty provisions shift responsibility for defective work and related losses to the subcontractor. They obligate the subcontractor to correct deficiencies and hold the contractor harmless for resulting claims. Liquidated damages address delay, not workmanship defects.
Question 7Project Management and Administration
In a construction contract, a clause states that the contractor will be paid the actual cost of labor, materials, and equipment plus a fixed percentage for overhead and profit. Which contract type is this?
- Guaranteed maximum price contract
- Lump-sum contract
- Unit-price contract
- Cost-plus-percentage contract Correct answer.
Explanation
A cost-plus-percentage contract reimburses allowable costs and adds a percentage fee, so the contractor's compensation rises as costs rise. This gives the owner less cost certainty. A guaranteed maximum price caps the owner's exposure, and a lump sum fixes the price.
Question 8Project Management and Administration
A project manager notices that a key structural steel supplier has repeatedly missed delivery dates, threatening the schedule. Which document should be updated to record this issue, its potential impact, and the planned response?
- The work breakdown structure
- The risk register Correct answer.
- The responsibility assignment matrix
- The quality management plan
Explanation
The risk register captures identified risks, their probability and impact, and the planned response and owner. A supplier with a demonstrated pattern of late delivery is a schedule risk that belongs there. The WBS decomposes scope and does not track risk responses.
Question 9Project Management and Administration
A contractor has completed 60 percent of a project but has only received payment for 45 percent of work in place because the owner retains a percentage of each payment. What is the primary purpose of this retention?
- To provide the owner security for completion and correction of defects Correct answer.
- To reduce the contractor's tax liability
- To fund the owner's contingency for design changes
- To accelerate the contractor's cash flow
Explanation
Retainage withholds a portion of each payment to protect the owner if the contractor fails to complete the work or correct defects. It is released according to the contract, often at substantial completion or after the warranty period. It does not fund design changes or improve the contractor's cash position.
Question 10Project Management and Administration
Which project delivery method places a single entity under contract with the owner for both design and construction, giving the owner a single point of responsibility?
- Multiple prime contracting
- Design-bid-build
- Design-build Correct answer.
- Construction management at risk
Explanation
In design-build, one entity contracts with the owner to provide both design and construction, creating a single point of responsibility. This can reduce coordination disputes and compress schedule through overlap. Design-bid-build separates design and construction into sequential contracts.
Question 11Project Management and Administration
A constructor is negotiating a contract and wants to limit liability for indirect losses such as lost profits or lost use resulting from delay. Which provision addresses this?
- A no-damage-for-delay clause
- A pay-when-paid clause
- A differing site conditions clause
- A mutual waiver of consequential damages Correct answer.
Explanation
A mutual waiver of consequential damages bars both parties from recovering indirect losses such as lost profits or lost use. It caps exposure to direct damages and is common in negotiated construction contracts. A no-damage-for-delay clause instead bars schedule-related damages against the owner.
Question 12Project Management and Administration
A project manager needs to assign clear accountability for each work package so that every deliverable has one responsible individual. Which tool is most appropriate?
- A responsibility assignment matrix Correct answer.
- A precedence diagram
- A Pareto chart
- A resource histogram
Explanation
A responsibility assignment matrix, such as a RACI chart, maps work packages to roles and clarifies who is responsible, accountable, consulted, and informed. Assigning one accountable party per deliverable prevents gaps and duplication. A resource histogram shows staffing levels over time, not accountability.
Question 13Project Management and Administration
An owner and contractor disagree about whether a delay was caused by unusually severe weather. The contract states that weather exceeding a defined historical threshold entitles the contractor to a time extension but not to additional cost. What is the contractor entitled to if the threshold is exceeded?
- Delay costs only
- Both a time extension and delay costs
- Neither a time extension nor costs
- A time extension only Correct answer.
Explanation
The contract expressly grants a time extension without cost for weather beyond the stated threshold, so the contractor receives schedule relief only. Excusable but noncompensable delays shift the completion date without shifting money. The contract language governs over general assumptions about weather delays.
Question 14Project Management and Administration
Which document establishes the contractor's contractual commitment to perform the work for a stated sum and forms the basis for the contract once accepted by the owner?
- The punch list
- The request for information
- The daily field report
- The contractor's bid or proposal Correct answer.
Explanation
An accepted bid or proposal becomes the contractor's offer to perform for a stated price and, once accepted, forms the basis of the contract. It defines scope and price commitments. A request for information clarifies documents but does not create a contractual commitment.
Question 15Project Management and Administration
A project is behind schedule on a critical activity, and the manager decides to add a second crew to work in parallel with the first on the same activity. What schedule compression technique is being used?
- Crashing Correct answer.
- Fast tracking
- Scope reduction
- Resource leveling
Explanation
Crashing adds resources, such as additional crews or overtime, to shorten an activity's duration, usually at increased cost. Fast tracking instead overlaps activities that were originally sequential. Crashing is applied when the added cost is justified by schedule recovery.
Question 16Project Management and Administration
A contractor submits a pay application that includes stored materials not yet incorporated into the work. What should the owner's representative typically verify before approving payment for those materials?
- That the materials were purchased at the lowest available price
- That the materials are listed in the contractor's safety plan
- That the materials have been installed and accepted
- That the materials are properly stored, labeled, insured, and traceable to the project Correct answer.
Explanation
Payment for stored materials normally requires verification that the materials are properly stored, identified for the project, insured, and documented so the owner has security in them. Some contracts require a bill of sale or title transfer. Installed and accepted materials are handled separately from stored materials.
Question 17Project Management and Administration
A project manager is preparing a cost baseline and must include an amount to cover known risks with identified responses but uncertain timing. Which reserve is this?
- Contingency reserve Correct answer.
- Escalation allowance
- Retainage
- Management reserve
Explanation
The contingency reserve covers known risks, sometimes called known-unknowns, that have been identified with planned responses. It is typically included in the cost baseline and controlled by the project manager. Management reserve covers unidentified risks and usually sits outside the baseline.
Question 18Project Management and Administration
During a project, a subcontractor discovers that a required permit will take eight weeks longer than assumed. The project manager documents the issue, assesses its effect on the critical path, and escalates it to the owner. This activity is best described as which process?
- Quality assurance
- Configuration management
- Issue management and escalation Correct answer.
- Procurement planning
Explanation
Issue management captures, assesses, and escalates problems that are already occurring and affecting objectives. Unlike risks, issues have materialized and require resolution and communication to the responsible authority. Escalation ensures decisions are made at the appropriate level.
Question 19Project Management and Administration
A contractor's foreman instructs workers to skip a required compaction test to save time. The quality manager stops the work and requires the test. Which quality principle does this best illustrate?
- Prevention and conformance to requirements take priority over speed Correct answer.
- Quality responsibility rests solely with the owner
- Quality is achieved through inspection at project completion
- Quality costs are limited to rework expenses
Explanation
Quality management emphasizes preventing defects and conforming to specified requirements rather than catching problems later. Stopping work to enforce a required test reflects prevention over expedience. Inspection at completion is a costly and ineffective substitute for conformance during construction.
Question 20Project Management and Administration
A constructor is reviewing a subcontract that makes payment to the subcontractor contingent on the owner first paying the general contractor. Which clause is this, and what risk does it create for the subcontractor?
- A pay-when-paid clause, which guarantees payment within a fixed period
- A liquidated damages clause, which penalizes late completion
- A pay-if-paid clause, which shifts owner nonpayment risk to the subcontractor Correct answer.
- A retainage clause, which withholds a percentage of each payment
Explanation
A pay-if-paid clause makes owner payment a condition precedent to the contractor's obligation to pay the subcontractor, shifting the risk of owner nonpayment downstream. A pay-when-paid clause, by contrast, typically sets a timing mechanism rather than eliminating the obligation. Subcontractors often negotiate to limit pay-if-paid language.
Question 21Project Management and Administration
A project manager is developing a stakeholder engagement strategy and must prioritize stakeholders. Which factor most directly determines a stakeholder's influence on project outcomes?
- The stakeholder's tenure in the industry
- The stakeholder's power and interest relative to the project Correct answer.
- The stakeholder's physical distance from the site
- The stakeholder's preferred communication channel
Explanation
Stakeholder prioritization commonly uses power and interest, or influence and impact, to determine how closely each party must be managed. High-power, high-interest stakeholders require active engagement. Communication preferences affect how engagement occurs, not how much influence a stakeholder holds.
Question 22Project Management and Administration
A contractor is required to provide a performance bond and a payment bond. What is the primary function of the payment bond?
- To guarantee the contractor completes the work
- To guarantee the contractor's bid price
- To protect subcontractors and suppliers who are not paid for labor and materials Correct answer.
- To insure the owner against fire loss during construction
Explanation
A payment bond protects subcontractors and suppliers by providing a surety-backed source of payment if the contractor fails to pay them. It reduces the risk of mechanics liens against the owner's property. A performance bond, by contrast, guarantees completion of the work.
Question 23Project Management and Administration
A project manager observes that a recurring defect is causing most of the rework. She wants to focus improvement efforts on the few causes responsible for the majority of problems. Which tool should she use?
- A Pareto chart Correct answer.
- A control chart
- A scatter diagram
- A fishbone diagram
Explanation
A Pareto chart ranks causes or defect types by frequency, illustrating the principle that a few causes account for most problems. It helps direct limited improvement resources to the highest-impact issues. A fishbone diagram identifies possible causes but does not rank them by frequency.
Question 24Project Management and Administration
A constructor must decide whether to self-perform a specialty trade or subcontract it. The trade requires skills the firm lacks, and the schedule is tight. Which consideration most strongly favors subcontracting?
- The firm wants to capture the subcontractor's markup
- The firm lacks the specialized capability and needs immediate qualified labor Correct answer.
- The firm wants to retain direct control over daily field operations
- The firm wants to reduce the number of contracts it administers
Explanation
Subcontracting is favored when the firm lacks specialized skills and needs qualified labor quickly, since a subcontractor can supply both capability and capacity. Self-performance is favored when control, margin capture, or available capacity justify it. Reducing contract administration and retaining direct control both point toward self-performance.
Question 25Project Management and Administration
A project manager is preparing a cash flow forecast and must account for the time between when the contractor incurs costs and when the owner pays. What is the primary purpose of this forecast?
- To anticipate the contractor's financing needs and avoid cash shortfalls Correct answer.
- To determine the project's tax depreciation schedule
- To set the contract's liquidated damages rate
- To establish the project's quality acceptance criteria
Explanation
A cash flow forecast aligns expected expenditures with expected receipts so the contractor can arrange financing and avoid shortfalls during the lag between cost incurrence and owner payment. It supports working capital planning across the project. It does not set tax, damages, or quality provisions.
Question 26Project Management and Administration
A constructor is preparing the project execution plan and must define how formal acceptance of completed work will be obtained from the owner at each milestone. Which project management process group primarily contains the activity of formalizing acceptance of the completed project deliverables?
- Executing
- Monitoring and Controlling Correct answer.
- Closing
- Initiating
Explanation
Formal acceptance of deliverables, including milestone sign-offs and verification of completed work, is performed in the Monitoring and Controlling process group through the Validate Scope process. Executing produces the work, while Closing finalizes the project or phase after acceptance has already been obtained.
Question 27Project Management and Administration
A general contractor's project manager is building the responsibility assignment matrix for a design-bid-build project. The owner wants assurance that exactly one party is accountable for each work package, while several parties may need to be consulted. Which responsibility assignment approach best satisfies this requirement?
- A resource histogram that allocates staff hours to each work package by trade
- A RACI chart, where each work package has one Accountable party and any number of Responsible, Consulted, and Informed parties Correct answer.
- An organizational breakdown structure that assigns work packages only to functional departments
- A linear responsibility chart in which every task is assigned to two co-accountable managers for redundancy
Explanation
A RACI chart explicitly separates accountability from responsibility, ensuring that each work package has a single accountable party while allowing multiple contributors and stakeholders. This avoids the ambiguity and diffusion of ownership that occurs when accountability is shared.
Question 28Project Management and Administration
A project manager is developing the project charter for a new wastewater treatment plant. Which element is essential to include because it authorizes the project manager to apply organizational resources to project activities?
- The complete bill of quantities and unit prices
- The documented authorization of the project manager to apply resources to the project Correct answer.
- The subcontractor bid tabulation and award recommendations
- The detailed construction schedule with all critical path activities
Explanation
The project charter formally authorizes the project and identifies the project manager with the authority to apply organizational resources to project activities. Detailed schedules, pricing, and procurement records are developed later and are not charter-level content.
Question 29Project Management and Administration
A constructor is establishing the project's communication approach for a large hospital expansion with many stakeholders. Which document defines who will receive what information, when, and in what format, and serves as the primary output of communication planning?
- The work performance report
- The stakeholder register
- The communications management plan Correct answer.
- The issue log
Explanation
The communications management plan specifies stakeholder information needs, the format, timing, and sender of communications, and is the key output of the Plan Communications Management process. The stakeholder register identifies stakeholders but does not define the communication approach.
Question 30Project Management and Administration
A project manager on a bridge replacement is reviewing the schedule and sees that a critical activity's float has become negative. What does negative total float indicate about the project?
- The activity can be delayed without affecting the project finish date
- The project is projected to finish later than the imposed completion date unless the schedule is compressed Correct answer.
- The activity has more resources assigned than its duration requires
- The activity is no longer on the critical path
Explanation
Negative total float means the path cannot meet the imposed finish date under current logic and durations, so the project will finish late unless activities are compressed or the constraint is changed. Zero float means the path is exactly on the imposed date, while positive float indicates available slack.
Question 31Project Management and Administration
A contractor's project manager is quantifying the cost impact of a two-week owner-caused delay. The project is being managed under a contract with a liquidated damages provision. Which cost element is the owner most likely entitled to recover from the contractor if the contractor causes the delay?
- The contractor's extended general conditions and home office overhead
- The contractor's lost profit on future unsecured work
- The pre-agreed liquidated damages amount stated in the contract Correct answer.
- The owner's actual lost rental income, regardless of the stipulated amount
Explanation
Liquidated damages are a pre-agreed amount per day of delay that the owner may recover for contractor-caused delay, avoiding the need to prove actual damages. Extended general conditions and home office overhead are typically contractor delay costs recovered from the owner for owner-caused delay.
Question 32Project Management and Administration
During construction of a warehouse, the owner requests a change that adds a mezzanine. The contractor prepares a change order. Which statement best describes how an executed change order affects the contract?
- It modifies the contract price, schedule, or scope and becomes part of the contract once signed by both parties Correct answer.
- It authorizes the contractor to proceed but leaves price and time unresolved
- It is a non-binding request that has no effect until the project is complete
- It supersedes the original contract in its entirety
Explanation
An executed change order is a written modification signed by both parties that adjusts the contract price, schedule, or scope and becomes part of the contract documents. It is binding and definitive, unlike a construction change directive that may direct work before price is agreed.
Question 33Project Management and Administration
A project manager is reviewing earned value data for a highway project. Planned value is $2,000,000, earned value is $1,800,000, and actual cost is $2,100,000. Which interpretation of the schedule and cost performance is correct?
- The project is ahead of schedule and under budget
- The project is behind schedule and over budget Correct answer.
- The project is behind schedule and under budget
- The project is ahead of schedule and over budget
Explanation
Schedule variance equals earned value minus planned value, which is negative $200,000, indicating the project is behind schedule. Cost variance equals earned value minus actual cost, which is negative $300,000, indicating the project is over budget.
Question 34Project Management and Administration
A constructor is identifying project risks for a new parking structure. The team lists the possibility that a neighboring property owner will file a claim over vibration damage. Which risk response strategy involves purchasing an insurance policy that transfers the financial consequence to a third party?
- Mitigate
- Transfer Correct answer.
- Accept
- Avoid
Explanation
Transferring risk shifts the financial impact to a third party, commonly through insurance or bonding, without eliminating the risk itself. Mitigation reduces probability or impact, avoidance eliminates the threat, and acceptance retains the risk.
Question 35Project Management and Administration
A project manager is preparing for a progress meeting and must present the cumulative cost performance index trend. The index has fallen from 1.05 to 0.92 over three reporting periods. What is the most appropriate management interpretation?
- The project's actual costs are decreasing over time
- The project has completed less work than planned and is behind schedule
- The project is now spending more than the value earned and requires corrective action Correct answer.
- The project is delivering more value per dollar spent than planned and should continue unchanged
Explanation
A cost performance index below 1.0 means the project is earning less value than the cost being spent, and a declining trend signals worsening cost efficiency requiring corrective action. The index measures cost efficiency, not schedule performance or the absolute level of costs.
Question 36Project Management and Administration
A contractor is required to submit a schedule of values with its first pay application. Which purpose does the schedule of values primarily serve in the payment process?
- It documents the contractor's actual labor rates for each trade
- It identifies the subcontractors and suppliers who will perform the work
- It establishes the contract completion date and milestone sequence
- It allocates the contract sum among portions of the work so progress payments can be determined Correct answer.
Explanation
The schedule of values breaks the contract sum into portions of work so that the amount of each progress payment can be measured against work completed. It supports fair valuation of completed work and is typically required before the first payment is certified.
Question 37Project Management and Administration
An owner and contractor are negotiating a contract for a project with a well-defined scope and a firm design. The owner wants price certainty and the contractor is willing to accept the risk of quantity variation within defined limits. Which contract type typically provides the greatest price certainty for the owner while assigning quantity risk to the contractor?
- Firm fixed price Correct answer.
- Cost plus incentive fee
- Cost plus percentage of cost
- Time and materials with a not-to-exceed cap
Explanation
A firm fixed price contract sets a price that is not subject to adjustment for the contractor's cost experience, giving the owner the greatest price certainty and placing cost risk on the contractor. Cost-reimbursable arrangements shift cost risk back to the owner.
Question 38Project Management and Administration
A project manager is analyzing a delay claim on a multiprime project. Two independent events occurred: the owner delayed approval of shop drawings by ten days on a critical path activity, and a supplier delivered equipment five days late on a non-critical activity with twelve days of total float. How should the time impact be evaluated?
- The contractor may recover fifteen days because both delays occurred during the project
- Both delays are concurrent and the contractor may recover ten days only if it proves the supplier delay was independent
- Neither delay supports an extension because both events occurred in the same period
- The owner-caused delay affects the critical path and supports a ten-day time extension, while the supplier delay is absorbed by float Correct answer.
Explanation
Only delays that affect the critical path or consume total float extend the project completion date. The ten-day owner delay on a critical activity supports a time extension, while the five-day supplier delay on an activity with twelve days of float is absorbed without affecting the finish date.
Question 39Project Management and Administration
A constructor is evaluating the cash flow profile of a project under a cost-reimbursable contract versus a lump-sum contract with monthly progress payments and a ten percent retainage. Which statement best describes the effect of retainage on the contractor's cash position?
- Retainage increases the contractor's early cash inflow because it defers payment of subcontractors
- Retainage withholds a portion of each payment, reducing cash inflow during construction until it is released at substantial completion or later Correct answer.
- Retainage eliminates the need for the contractor to finance any costs during construction
- Retainage has no effect on cash flow because it is returned with each subsequent payment
Explanation
Retainage withholds a percentage of each progress payment, which reduces the contractor's cash inflow and increases the financing burden until the retained amounts are released, typically at substantial completion and after punch list completion. It does not eliminate the need to finance work in progress.
Question 40Project Management and Administration
A project manager is resolving a dispute over differing site conditions. The contract contains a differing site conditions clause, and the contractor encountered subsurface rock not indicated in the geotechnical report. Which action best preserves the contractor's right to an equitable adjustment?
- Proceed with the work and submit written notice within the contract-specified period, documenting the conditions before they are disturbed Correct answer.
- Stop all work on the project until the owner agrees to a revised contract price
- Complete the affected work and include the claim only in the final payment application
- Direct the subcontractor to absorb the additional cost and pursue recovery after acceptance
Explanation
Differing site conditions clauses require prompt written notice and typically require the contractor to document the conditions before they are disturbed, while continuing performance to avoid delay. Failing to give timely notice or disturbing the evidence can waive or weaken the claim.
Question 41Cost Management and Estimating
In a construction estimate, which cost category includes field supervision salaries, temporary utilities, and site office expenses?
- Owner's reserve
- General conditions Correct answer.
- Contingency
- Direct material cost
Explanation
General conditions (also called general requirements) cover the project-wide costs of running the job that are not tied to a single work item, such as site supervision, temporary facilities, utilities, and cleanup. Material cost is a direct cost of installed work, while contingency and owner's reserve are risk allowances rather than recurring field support costs.
Question 42Cost Management and Estimating
A contractor's historical records show that for every 100 hours of carpenter labor, 8 hours of foreman time are required. This relationship is best described as which type of estimate component?
- A lump-sum allowance
- A labor burden factor
- A production rate
- A unit price Correct answer.
Explanation
A ratio of supervisory hours to craft hours represents a unit price or cost relationship used to build up the total labor cost for an activity. Production rates express output per labor hour (for example, square feet per hour), while burden factors apply to wage costs for taxes and insurance.
Question 43Cost Management and Estimating
Which of the following best defines the purpose of a quantity takeoff in the estimating process?
- To measure the quantities of work items from the drawings and specifications Correct answer.
- To assign responsibility for each subcontract package
- To negotiate the final contract price with the owner
- To establish the project schedule and milestone dates
Explanation
The quantity takeoff is the systematic measurement of materials and work items required by the drawings and specifications, providing the basis for pricing. Scheduling, price negotiation, and subcontract scoping are separate later activities that consume the takeoff rather than replace it.
Question 44Cost Management and Estimating
A project estimate is prepared at the schematic design stage with a documented accuracy range of -15% to +25%. Which AACE International estimate class does this most closely correspond to?
- Class 2
- Class 5
- Class 3 Correct answer.
- Class 4
Explanation
AACE Class 3 estimates are typically prepared from preliminary drawings and have an expected accuracy range of roughly -15% to +25%, suitable for budget authorization. Class 4 and Class 5 are earlier and less accurate, while Class 2 is more definitive with a tighter range.
Question 45Cost Management and Estimating
A crew of 4 workers installs 320 square feet of formwork in an 8-hour day. What is the labor productivity expressed in square feet per labor hour?
- 20
- 80
- 40
- 10 Correct answer.
Explanation
Total labor hours equal 4 workers times 8 hours, or 32 labor hours. Dividing 320 square feet by 32 labor hours yields 10 square feet per labor hour, which is the productivity rate used to price the activity.
Question 46Cost Management and Estimating
A contractor wants to add a markup that covers home office overhead and profit as a percentage of total project cost. Which markup basis is most appropriate?
- Applied only to labor cost
- Applied to the total direct cost including general conditions Correct answer.
- Applied only to subcontractor cost
- Applied only to material cost
Explanation
Home office overhead and profit are typically recovered as a percentage applied to the total cost of the work, including direct costs and general conditions, because they support the entire project. Applying markup to only one cost component would under-recover overhead and distort pricing across trades.
Question 47Cost Management and Estimating
In a unit-price contract, how is the contractor paid for work performed?
- The actual quantity installed multiplied by the bid unit price Correct answer.
- Cost plus a fixed fee with no quantity adjustment
- A fixed lump sum regardless of actual quantities installed
- A guaranteed maximum price with shared savings
Explanation
Under a unit-price contract, the contractor bids a price per unit of work and is paid for the measured quantity actually installed times that unit price. Quantity variation risk is therefore borne largely by the owner, unlike a lump-sum contract where the contractor bears it.
Question 48Cost Management and Estimating
An estimator applies a 12% labor burden to base wages. Which of the following costs is properly included in that burden?
- Overtime premium paid for schedule acceleration
- The cost of hand tools consumed by the crew
- Employer payroll taxes and workers' compensation insurance Correct answer.
- The project superintendent's salary
Explanation
Labor burden consists of the statutory and insurance costs an employer pays on top of base wages, principally payroll taxes, workers' compensation, and fringe benefits. Overtime premium, small tools, and supervision are priced separately as direct or general conditions costs.
Question 49Cost Management and Estimating
A contractor is preparing an estimate and must account for costs that are known to occur but whose magnitude is uncertain, such as minor design detail gaps typical of the current design stage. Which allowance best fits this description?
- Contingency Correct answer.
- Retainage
- Escalation
- Bond premium
Explanation
Contingency is a provision for costs that are expected but not yet fully defined, sized to the level of design development and known risk. Escalation addresses price changes over time, retainage is withheld payment, and bond premiums are a specific insurance cost.
Question 50Cost Management and Estimating
An owner asks for a conceptual budget before any drawings exist, based only on the type, size, and location of a planned facility. Which estimating method is most appropriate?
- Detailed unit-price takeoff
- Parametric or capacity-factor estimating Correct answer.
- Assembly-based quantity survey
- Bid comparison from subcontractor quotes
Explanation
When design information is minimal, estimators use parametric methods such as cost per square foot, per bed, or capacity factors derived from historical data for similar facilities. Detailed takeoffs, assembly surveys, and subcontractor quotes all require defined design information that does not yet exist.