CPC Certified Professional Constructor study materials
CPC Certified Professional Constructor study resources

CPC Certified Professional Constructor study plan

CPC Certified Professional Constructor · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Project Management and Administration

  • Map Domain 1 into its sub-areas (project delivery, scope definition, project controls, documentation, stakeholder communication) and rate your confidence 1-5 on each to target weak spots.

  • Draft a one-page project management plan outline for a sample commercial building project, covering scope statement, work breakdown structure levels, and reporting cadence.

  • Practice converting a narrative scope description into a 3-level WBS with at least 25 work packages and verify no scope gaps.

  • Build a personal glossary of 20 Domain 1 terms (e.g., baseline, change control, punch list, substantial completion) written in your own words.

Your checkpoint

A one-page sample project management plan plus a 25-package WBS and a scored Domain 1 confidence table.

Week 2

Project Management and Administration & Cost Management and Estimating

  • Write a 10-question self-quiz on Domain 1 administration topics and score at least 80% before moving on.

  • Compute a full quantity takeoff for a small concrete and masonry scope using a provided dimension set you create, showing unit conversions.

  • Assemble a unit-price estimate with labor, material, equipment, and markup lines, then reconcile it against a bottom-up total.

  • Identify the five most common estimating errors (omissions, wrong units, double counting, poor productivity factors, missed escalation) and write a check step for each.

Your checkpoint

A complete sample estimate with takeoff backup and a written pre-submission estimating checklist of at least 10 checks.

Week 3

Cost Management and Estimating & Contract Administration and Legal Issues

  • Build a cost control worksheet that tracks budget, committed cost, actual cost, and forecast-to-complete for 8 cost codes.

  • Calculate earned value metrics (CPI, SPI, EAC, VAC) from a sample data set and write two sentences interpreting each result.

  • Read the standard contract documents structure (agreement, general conditions, supplementary conditions, specifications, drawings) and diagram the order of precedence.

  • Summarize in your own words the difference between lump sum, unit price, cost-plus, and design-build compensation structures with one risk example each.

Your checkpoint

A working cost-control spreadsheet with earned value outputs and a one-page contract document hierarchy diagram.

Week 4

Contract Administration and Legal Issues

  • Outline the change order process end to end: request, pricing, time impact, approval authority, and documentation.

  • Draft a sample notice letter for a differing site condition that satisfies a 7-day notice requirement.

  • List the typical grounds for a claim (delay, disruption, acceleration, differing conditions, defective design) and the records needed to support each.

  • Explain lien, bond, and retainage mechanics in your jurisdiction and note where you must verify local rules rather than rely on memory.

Your checkpoint

A change order and claims packet containing one notice letter, one priced change order, and a record-keeping checklist.

Week 5

Planning, Scheduling and Time Control

  • Build a critical path schedule of at least 40 activities with logic ties, durations, and a calculated float for each activity.

  • Perform a forward and backward pass by hand on a 10-activity network and verify your results match the software output.

  • Compress the schedule by 10% using both crashing and fast-tracking and document the cost and risk consequences of each approach.

  • Create a resource-loaded two-week look-ahead and a progress update showing percent complete by activity.

Your checkpoint

A 40-activity CPM schedule with float report, a crash/fast-track comparison memo, and one look-ahead schedule.

Week 6

Construction Safety and Risk Management

  • Develop a site-specific safety plan outline covering hazard analysis, competent person duties, training, and emergency response.

  • Complete a job hazard analysis for three high-risk tasks (fall work, excavation, steel erection) with controls ranked by hierarchy of control.

  • Build a risk register with 10 project risks scored by probability and impact, each with an owner and mitigation action.

  • Identify the recordkeeping and inspection obligations that apply to your scope of work and list what must be documented daily.

Your checkpoint

A site safety plan outline, three completed JHAs, and a scored 10-item risk register.

Week 7

Quality Management and Inspection & Site Management and Field Operations

  • Write an inspection and test plan for two work items, specifying hold points, witness points, acceptance criteria, and responsible parties.

  • Outline a quality management approach covering submittals, mockups, first-work inspection, nonconformance reports, and closeout documentation.

  • Draft a daily site log template and a two-week site logistics plan covering access, laydown, temporary utilities, and sequencing.

  • Describe how you would run a pre-construction and a weekly coordination meeting, including agenda and action-item tracking.

Your checkpoint

An inspection and test plan for two work items plus a daily log template and site logistics plan.

Week 8

Ethics and Professional Practice & Project Management and Administration

  • Work through at least 10 ethics scenarios covering conflicts of interest, bid integrity, confidential information, and public safety, writing your reasoning for each.

  • Summarize the core professional obligations of a constructor to the owner, the public, and the profession in your own words.

  • Take a timed 60-question mixed-domain practice exam and record your score by domain.

  • Build a final two-week review list targeting the two lowest-scoring domains and schedule the review sessions.

Your checkpoint

A timed practice exam score report by domain plus a written two-week final review plan.

Milestones

Week 2: Domain 1 self-quiz at 80% or better and a complete sample estimate with takeoff backup finished.

Week 4: Cost-control spreadsheet produces correct CPI, SPI, and EAC from sample data, and the change order packet is complete.

Week 6: CPM schedule has a validated critical path and float report; safety plan, three JHAs, and risk register are done.

Week 8: Timed 60-question practice exam completed with domain scores recorded and a final review plan written.