The 9% Resin Increase on a Molded Housing
A medical equipment manufacturer buys 1,200,000 molded instrument housings a year at $2.85 each. The supplier has requested a 9% increase, asserting that "resin is now 52% of the price and resin is up 22%." Engineering data: the housing weighs 185 grams in a glass-filled engineering resin currently quoted at $5.60/kg. The part runs in a two-cavity tool on a 24-second cycle on an 800-ton press billed at $150/hour. Unrecoverable scrap runs 4%; runner material is fully reground and returned, so the net resin content is the part weight. Secondary operations and assembly run $0.30/part; packaging $0.07; inbound freight $0.10; tooling amortization $0.10. Industry norm for SG&A plus margin on this commodity is 13%. The buyer's resin price service shows the supplier's specific grade moved 11% over the period, not 22%. A second, offshore option is also on the table at $2.42 FOB origin, 6.5% duty, $0.11/part ocean freight and insurance, 11 weeks total lead time versus 3 weeks domestic, and $0.03/part source inspection.
1. Build a should-cost for the housing and test the supplier's claim. What increase, if any, is supportable?
Read the worked answer
Step 1 - Should-cost build-up
Resin: 0.185 kg × $5.60/kg = $1.036; at 4% unrecoverable scrap, ÷ 0.96 = $1.079/part
Machine: 24 s cycle ÷ 2 cavities = 12 s/part → 3,600 ÷ 12 = 300 parts/hour. At $150/hour → $0.500/part
Other: secondary/assembly $0.300 + packaging $0.070 + freight $0.100 + tooling amortization $0.100 = $0.570/part
Subtotal: 1.079 + 0.500 + 0.570 = $2.149/part
SG&A plus margin at 13%: $2.149 × 1.13 = $2.428/part should-cost
Step 2 - Compare to the quoted price
$2.85 ÷ $2.428 = 1.174. The supplier's price is 17.4% above should-cost ($0.422/part, roughly $506,000 a year). Either the supplier has a cost element not visible in the model, or the price already carries a cushion. That must be resolved before any adjustment is discussed.
Step 3 - Test the claim
- "Resin is 52% of the price." At should-cost, resin is $1.079 ÷ $2.428 = 44.4%. On the quoted price it is 1.079 ÷ 2.85 = 37.9%. The 52% figure implies a resin content of $1.48/part (52% × $2.85), which is 37% more resin than the part physically contains.
- "Resin is up 22%." The buyer's price service shows this specific grade up 11%. A 22% move may be true of a broader index or a different grade, but the contract should follow the grade actually consumed.
Step 4 - Supportable increase
Resin pass-through = $1.079 × 0.11 = $0.119/part, which is 4.9% of should-cost or 4.2% of the current price. Against the supplier's request of 9% ($0.257/part), the overstatement is roughly $0.137/part × 1.2M = $164,000 a year.
Conclusion: a resin adjustment of about $0.12/part is supportable on the should-cost base. But the base is 17.4% high. Applying an index to an inflated base compounds the problem.
Recommended position: agree the index mechanism and the 11% figure in principle, but reset the base to should-cost (or require the supplier to open the books and show what the model is missing) before the adjustment is applied. Indexing a wrong number produces a wrong number with a defensible-looking formula attached.
2. Compare the domestic and offshore options on total cost of ownership. Show the arithmetic and state what the comparison does not capture.
Read the worked answer
Step 1 - Landed cost, offshore
- FOB price: $2.4200
- Duty at 6.5% ad valorem on FOB: $2.42 × 0.065 = $0.1573
- Ocean freight and insurance: $0.1100
- Source inspection: $0.0300
- Landed and inspected: $2.7173/part
Domestic at $2.85 is already only $0.133/part ahead. The offshore option does not have the cost advantage it appears to have at the FOB quote.
Step 2 - Pipeline inventory carrying cost
Offshore requires 8 extra weeks of supply in the pipeline versus domestic.
- Extra inventory: (8 ÷ 52) × 1,200,000 = 184,615 parts
- Value at landed cost: 184,615 × $2.7173 = $501,700
- Carrying cost at 22%/yr: $501,700 × 0.22 = $110,374/yr
- Per part: $110,374 ÷ 1,200,000 = $0.0920
Step 3 - Total cost of ownership
$2.7173 + $0.0920 = $2.8093/part
Against domestic at $2.8500/part. The advantage is $0.041/part, about $48,800 a year - roughly 1.4% of spend, on an estimate that rests on several assumptions.
Step 4 - What the comparison does not capture
- Forecast error. Demand historically varies ±18%. On 184,615 parts of pipeline, an 18% swing is ~33,000 parts, and the portion that becomes excess or obsolete at $2.72 is real money. A single bad quarter consumes the entire annual saving.
- Expedite and recovery cost. At 11 weeks, a quality problem cannot be recovered by air freight at anything close to $0.04/part.
- Quality. No PPM data is given for the offshore source; if it runs worse than the domestic incumbent, inspection cost and returns rise.
- Currency and duty volatility. A 6.5% duty is 6.5% of the landed calculation; a tariff change or a currency move of 5% wipes out a 1.4% saving.
- Working capital. The pipeline is a cash commitment, not just a carrying cost.
Conclusion: at 1.4% of spend, the offshore case is not a sourcing decision, it is a bet. It becomes viable if the supplier shortens lead time, holds consignment stock at a regional hub, or moves to a delivered-duty-paid basis that transfers the pipeline risk. Otherwise the domestic incumbent is the rational choice even at a higher piece price.
3. Write the negotiation position you would take to the incumbent on the resin increase, including what you concede and what you require in return.
Read the worked answer
Opening position
"We accept that resin costs have risen and we are prepared to share that movement on a documented, indexed basis. We do not accept a 9% increase, and we do not accept the cost model underlying it."
Sequence - base first, then index
- Challenge the base. Present the should-cost ($2.428) against the quoted $2.85 and ask the supplier to explain the $0.422 gap. Give a specific window (ten business days) and a specific format (cost breakdown by element, not a narrative). Silence or a refusal to open the model is itself information.
- Correct the claim. Show that resin is 44.4% of should-cost, not 52% of price, and that the relevant grade moved 11%, not 22%. Use the buyer's independent price service so the conversation is about data, not assertions.
- Concede the real number. Offer $0.119/part as a documented pass-through - about 4.2% of price - contingent on the base being reset or adequately explained.
What to concede
- A genuine, indexed pass-through on the resin element only, quarterly, using a named published index for the specific grade.
- Symmetry: the mechanism reduces price when the index falls. This is the single most valuable term in the package and is usually the hardest to get.
- Term: offer 24 months in exchange for the index mechanism and the base reset. Term is cheap; price is not.
What to require in return
- Open-book cost model refreshed annually, with an audit right.
- Dead band (e.g., movements under 3% are absorbed) to eliminate administrative churn.
- A productivity commitment of 2% a year on the conversion element (machine, secondary, packaging), which is where the supplier actually controls cost.
- A cap on any single adjustment (e.g., 6% of price) and a floor.
- Price reduction if volume exceeds agreed bands.
Walk-away
The maximum acceptable outcome is the indexed adjustment applied to a base no more than 5% above should-cost. Above that, the offshore option becomes live at roughly parity - and the supplier should know that a valid second source exists, without being told the analysis is thin.