- Kraljic portfolio matrix
- Two-by-two model classifying purchases by profit impact and supply risk into non-critical, leverage, bottleneck, and strategic quadrants, each requiring a different sourcing approach.
- Sole source
- A supplier that is the only possible provider of an item, typically because of patents, proprietary technology, or unique capability, so no alternative source exists.
- Single source
- A deliberately selected sole supplier chosen from several qualified candidates, usually to gain volume leverage or a partnership; other qualified sources remain available.
- Make-or-buy analysis
- Comparison of the total relevant cost and strategic implications of producing an item internally versus purchasing it, including only avoidable fixed costs and qualitative factors.
- Reverse auction
- Online bidding event in which prequalified suppliers compete by lowering prices within a set time; suited to well-specified, commodity-like items with adequate competition.
- Early supplier involvement
- Practice of involving key suppliers in design before specifications are frozen, because most life-cycle cost is committed during design rather than during production.
- Supplier rationalization
- Reduction in the number of active suppliers, often consolidating spend into fewer partners to gain price leverage, lower administrative cost, and closer quality control.
- Spend Pareto analysis
- Ranking of suppliers or categories by spend volume, showing that a small share of them typically accounts for most of the money and indicating where sourcing effort pays.
- Firm-fixed-price contract
- Contract whose price is fixed at award and does not vary with the seller's actual costs, so the seller bears cost risk and is motivated to control cost.
- Cost-reimbursable contract
- Contract paying the seller's allowable incurred costs plus a fee, placing cost risk on the buyer; used when scope is uncertain or costs are difficult to estimate.
- UCC Article 2
- Model US statute governing contracts for the sale of goods; it fills gaps in the parties' agreement and contrasts with common law, which applies to service contracts.
- Statute of Frauds under UCC
- Rule requiring a writing to enforce sale-of-goods contracts of $500 or more, with exceptions such as specially manufactured goods or a contract admitted in pleadings.
- Liquidated damages
- Pre-agreed sum payable for a specified breach such as late delivery; it must approximate a reasonable forecast of anticipated loss or it is an unenforceable penalty.
- Termination for convenience
- Contractual right letting the buyer end the agreement without supplier fault, usually on stated notice and with payment for work performed plus a reasonable settlement.
- Battle of the forms
- Situation where offer and acceptance use conflicting standard terms; under UCC 2-207 a contract may still be formed, with gap-filling rules governing the disputed terms.
- Three-way match
- Payment control comparing purchase order, receiving report, and supplier invoice for quantity and price before an invoice is approved for payment.
- Total cost of ownership
- Sum of acquisition price plus acquisition, operating, maintenance, training, downtime, and end-of-life costs over an asset's life, less any residual value.
- Learning curve
- Model in which unit labor hours fall by a constant percentage each time cumulative production doubles; an 80% curve yields 80% of prior hours per unit.
- Should-cost model
- Bottom-up estimate of what a product ought to cost, built from material, labor, overhead, SG&A, and profit, used to test the reasonableness of a supplier's price.
- Price analysis
- Evaluation of a price by comparison with other prices such as competitive bids, catalogues, historical data, or published indices, without examining the supplier's cost elements.
- Break-even quantity
- Volume at which total revenue equals total cost, calculated as fixed costs divided by the difference between unit price and variable cost per unit.
- Cost of forgoing cash discount
- Annualized financing cost of not taking terms such as 2/10 net 30, computed as d/(100 - d) multiplied by 365 divided by days beyond the discount period.
- Life-cycle costing
- Assessment of all costs across a product's life from concept and acquisition through operation and disposal, used to compare design or investment alternatives.
- Price elasticity of demand
- Percentage change in quantity demanded divided by the percentage change in price; demand is elastic when the absolute value of the ratio exceeds one.
- ISO 9001
- International standard specifying requirements for a quality management system and third-party certified; it certifies process capability, not the quality of specific products.
- Process capability index Cpk
- Measure of how well a stable process fits within specification limits; 1.33 is a common minimum and 1.67 is often required for critical characteristics.
- DMAIC
- Six Sigma improvement sequence of define, measure, analyze, improve, and control, targeting reduction of defects toward 3.4 per million opportunities.
- Cost of poor quality
- Combined prevention, appraisal, internal failure, and external failure costs; failure costs rise sharply the later in the process a defect is discovered.
- OTIF delivery metric
- Supplier performance measure counting orders received complete and on the promised date, expressed as a percentage of total orders delivered.
- Foreign Corrupt Practices Act
- US law making it illegal to bribe foreign government officials to obtain or retain business, and requiring accurate books and effective internal accounting controls.
- Bid rigging
- Antitrust violation in which competitors secretly coordinate bids, rotate winning, or suppress offers to defeat competition; it is treated as per se illegal.
- Acceptable quality level
- Maximum percentage of nonconforming units treated as acceptable as a process average, used with sampling tables to set sample size and acceptance number.