CPSWQ · Put your knowledge to work in context.

All case studies

Green Infrastructure Retrofit Under a New MS4 Permit

A city must comply with a new MS4 permit requirement to retrofit 20 acres of impervious area with green infrastructure over five years. Public works proposes a 1.8-acre bioretention basin in a parking lot that drains 2.4 acres of asphalt. Site constraints: clay soils with an infiltration rate of 0.05 in/hr, seasonal high groundwater 2 feet below the proposed basin bottom, and an outfall to a stream impaired for nitrogen and E. coli. The lot is plowed and salted in winter. The city has a $400,000 budget and wants to count the retrofit toward its pollutant load reduction. A vendor offers a proprietary media filter with a 10-year lifespan and a 70% nitrogen removal claim. The city engineer is concerned about standing water, chloride, and maintenance.

1. Evaluate the proposed bioretention design and identify the key feasibility issues.

Read the worked answer

The design cannot rely on infiltration as the primary loss mechanism. A rate of 0.05 in/hr is very low for clay soils, and groundwater only 2 feet below the basin bottom leaves little separation to protect groundwater and maintain unsaturated treatment. The project should use an underdrain, a properly designed media layer, and a positive overflow to avoid standing water. Pretreatment is important because the parking lot will deliver sediment and hydrocarbons. Winter salt is a real constraint: chloride will pass through most media, so the city should not claim chloride reduction and should manage deicing practices. The basin should also be sized for the treatment volume required by the permit and for local rainfall, not just the vendor's filter. These issues affect feasibility, cost, and whether the retrofit can be credited at all.

2. How should the city credit pollutant reduction and evaluate the vendor's 70% nitrogen removal claim?

Read the worked answer

The city should use the credit methodology approved in its MS4 permit or TMDL framework, not a vendor's marketing claim. A 70% nitrogen removal figure may be based on a different media, influent concentration, temperature, or maintenance regime. The city should ask for the underlying test data, confirm whether the claim is for total nitrogen or a specific form, and check whether the local crediting authority accepts proprietary devices. Because the stream is impaired for nitrogen, the city should prioritize a design with demonstrated performance and documented maintenance. The credit should be calculated from the treated volume and the approved removal rate, and the city should keep conservative assumptions. If the claim cannot be verified locally, the city should not count 70% in its load reduction.

3. What O&M and long-term funding should be secured before construction?

Read the worked answer

The city should secure an O&M plan and a dedicated funding source before construction, not after. The plan should cover inspection frequency, sediment and debris removal, vegetation management, media replacement, underdrain cleaning, and winter operations. The 10-year media lifespan should be treated as an estimate and budgeted as a future capital cost. The city should assign a responsible department, keep an asset inventory, and track maintenance costs. Because the basin is in a parking lot, access and snow storage should be designed to avoid damage. Without a credible O&M commitment, the pollutant reduction credit is vulnerable and the facility may become a standing-water complaint. The city should also monitor performance during the first few years to confirm the design assumptions.