DC General Contractor study materials
DC General Contractor study resources

DC General Contractor key terms

DC General Contractor · Get comfortable with the vocabulary.

Lien

A legal claim recorded against a property by a party who supplied labor, materials, or services and was not paid. It can cloud the title until resolved or released.

Related: Mechanics Lien Notice, Lien Waiver, Bonded Stop Notice
Mechanics Lien Notice

A preliminary written notice that preserves a potential lien claimant's right to record a lien later. Deadlines and required contents are set by statute and vary by project type.

Related: Lien, Lien Waiver, Stop Notice
Lien Waiver

A signed document in which a claimant gives up lien rights, either conditionally on payment or unconditionally once payment is received. Statutory forms are often required.

Related: Lien, Progress Payment, Retainage
Stop Notice

A notice directing a project owner or lender to withhold funds owed to the prime contractor so an unpaid subcontractor or supplier can be paid from those funds.

Related: Bonded Stop Notice, Lien, Public Works Bond
Bonded Stop Notice

A stop notice served on a construction lender or owner that is backed by a surety bond, which may be required to shift liability if the notice later proves improper.

Related: Stop Notice, Payment Bond, Lien
Payment Bond

A surety instrument guaranteeing that a contractor will pay subcontractors, laborers, and suppliers on a project. It gives unpaid parties a remedy on public work where liens are unavailable.

Related: Performance Bond, Public Works Bond, Stop Notice
Performance Bond

A surety instrument guaranteeing the contractor will complete the work according to the contract. If the contractor defaults, the surety must arrange completion or pay the owner's damages.

Related: Payment Bond, Bid Bond, Default
Bid Bond

A surety instrument submitted with a bid that guarantees the bidder will enter the contract if awarded and will furnish required bonds. The owner may claim against it if the bidder refuses.

Related: Performance Bond, Payment Bond, Bid Opening
Retainage

A percentage of each payment withheld by the owner until the project or a defined phase is complete. It protects the owner against incomplete work and unpaid claims.

Related: Progress Payment, Lien Waiver, Substantial Completion
Progress Payment

Periodic payment to the contractor for work completed and materials stored during a billing period, based on an approved application for payment.

Related: Schedule of Values, Retainage, Punch List
Schedule of Values

An itemized breakdown of the contract price allocated to work phases or trades. It supports progress billing and is often required with the first payment application.

Related: Progress Payment, Change Order, Pay Application
Change Order

A written agreement signed by owner and contractor that modifies the scope, price, or schedule of the contract. It becomes part of the contract documents once executed.

Related: Construction Change Directive, Request for Information, Schedule of Values
Construction Change Directive

A written order from the owner directing a change before price and time are agreed. It lets work proceed while the parties later settle cost and schedule adjustments.

Related: Change Order, Request for Information, Delay Claim
Request for Information

A formal written question from the contractor to the design team seeking clarification of drawings, specifications, or contract terms. Responses become part of the project record.

Related: Change Order, Shop Drawing, As-Built Drawings
Shop Drawing

A detail drawing, diagram, or data sheet prepared by a contractor or supplier showing how a portion of the work will be fabricated or installed, submitted for review before construction.

Related: Request for Information, Submittal, As-Built Drawings
Submittal

Any product data, sample, mockup, or drawing the contractor sends to the design team for review and approval before installation, as required by the specifications.

Related: Shop Drawing, Request for Information, Specification
Substantial Completion

The stage when the work is sufficiently complete for the owner to occupy and use it for its intended purpose, leaving only minor items to finish. It often starts warranty periods.

Related: Punch List, Final Completion, Retainage
Punch List

A written list of minor incomplete or defective items identified near completion that the contractor must correct before final acceptance and final payment.

Related: Substantial Completion, Final Completion, Retainage
Final Completion

The point when all work, including punch list items and closeout documents, is finished and accepted by the owner, triggering release of remaining payments and retainage.

Related: Substantial Completion, Punch List, Lien Waiver
Default

A party's failure to perform a material contract obligation, such as missing schedule, abandoning work, or not paying subcontractors. It can trigger termination and surety claims.

Related: Termination for Cause, Performance Bond, Delay Claim
Termination for Cause

The owner's ending of the contract because of the contractor's default. The owner may complete the work with others and charge the contractor for resulting excess costs.

Related: Default, Termination for Convenience, Performance Bond
Termination for Convenience

The owner's ending of the contract without the contractor being at fault, typically with notice and payment for work performed plus allowable costs.

Related: Termination for Cause, Change Order, Delay Claim
Delay Claim

A request for additional time or money when project progress is slowed by events outside the contractor's control, such as owner-caused changes, weather, or differing site conditions.

Related: Construction Change Directive, Differing Site Conditions, Liquidated Damages
Liquidated Damages

A preset amount stated in the contract that the contractor owes the owner for each day of late completion. It must be a reasonable estimate, not a penalty.

Related: Delay Claim, Substantial Completion, Default
Differing Site Conditions

Physical conditions at the site that differ materially from what the contract documents indicated or that are unusual for the work, often supporting a price or time adjustment.

Related: Delay Claim, Change Order, Request for Information
Bid Opening

The scheduled public or private event at which sealed bids are opened and read aloud, usually followed by evaluation and award.

Related: Bid Bond, Bidder's List, Invitation to Bid
Invitation to Bid

An owner's published request for contractors to submit priced proposals for a defined scope, with instructions, deadlines, and bid documents attached.

Related: Bid Opening, Bid Bond, Bidder's List
Bidder's List

A roster of contractors who have obtained bid documents or been prequalified to submit proposals on a specific project.

Related: Invitation to Bid, Prequalification, Bid Opening
Prequalification

A process in which an owner screens contractors for licensing, experience, financial capacity, and safety record before allowing them to bid or be awarded work.

Related: Bidder's List, Invitation to Bid, Contractor License
Contractor License

A credential issued by a state or local authority permitting a person or firm to perform or offer construction work. Bidding or working without one can void contracts and draw penalties.

Related: Prequalification, Building Permit, Qualifying Party
Qualifying Party

The individual whose license, examination, and experience support a construction firm's license. The firm's license depends on that person remaining connected to the business.

Related: Contractor License, Responsible Managing Employee, Building Permit
Building Permit

Written government authorization to construct, alter, or demolish a structure. Work must match approved plans, and inspections are required at defined stages.

Related: Certificate of Occupancy, Code Compliance, Contractor License
Certificate of Occupancy

A document issued by the building authority confirming that a completed structure complies with applicable codes and may be legally occupied and used.

Related: Building Permit, Substantial Completion, Code Compliance
Code Compliance

Meeting the adopted building, fire, energy, and accessibility codes that govern design and construction in the jurisdiction where the work occurs.

Related: Building Permit, Certificate of Occupancy, Specification
Specification

The written portion of contract documents describing materials, products, workmanship standards, and performance requirements for the project, usually organized by trade divisions.

Related: Submittal, Shop Drawing, Code Compliance
As-Built Drawings

Construction drawings marked up by the contractor to record actual installed conditions, dimensions, and changes, then delivered to the owner at closeout.

Related: Shop Drawing, Submittal, Punch List
Critical Path Method

A scheduling technique that identifies the longest sequence of dependent activities, showing which tasks control the project finish date and where float exists.

Related: Baseline Schedule, Float, Delay Claim
Float

The amount of time an activity can slip without delaying the project finish or a later activity. Ownership of float is often addressed in contract scheduling clauses.

Related: Critical Path Method, Baseline Schedule, Delay Claim
Baseline Schedule

The initial approved project schedule against which actual progress and time impacts are measured throughout construction.

Related: Critical Path Method, Float, Substantial Completion