DC General Contractor key terms
DC General Contractor · Get comfortable with the vocabulary.
- Lien
- Related: Mechanics Lien Notice, Lien Waiver, Bonded Stop Notice
A legal claim recorded against a property by a party who supplied labor, materials, or services and was not paid. It can cloud the title until resolved or released.
- Mechanics Lien Notice
- Related: Lien, Lien Waiver, Stop Notice
A preliminary written notice that preserves a potential lien claimant's right to record a lien later. Deadlines and required contents are set by statute and vary by project type.
- Lien Waiver
- Related: Lien, Progress Payment, Retainage
A signed document in which a claimant gives up lien rights, either conditionally on payment or unconditionally once payment is received. Statutory forms are often required.
- Stop Notice
- Related: Bonded Stop Notice, Lien, Public Works Bond
A notice directing a project owner or lender to withhold funds owed to the prime contractor so an unpaid subcontractor or supplier can be paid from those funds.
- Bonded Stop Notice
- Related: Stop Notice, Payment Bond, Lien
A stop notice served on a construction lender or owner that is backed by a surety bond, which may be required to shift liability if the notice later proves improper.
- Payment Bond
- Related: Performance Bond, Public Works Bond, Stop Notice
A surety instrument guaranteeing that a contractor will pay subcontractors, laborers, and suppliers on a project. It gives unpaid parties a remedy on public work where liens are unavailable.
- Performance Bond
- Related: Payment Bond, Bid Bond, Default
A surety instrument guaranteeing the contractor will complete the work according to the contract. If the contractor defaults, the surety must arrange completion or pay the owner's damages.
- Bid Bond
- Related: Performance Bond, Payment Bond, Bid Opening
A surety instrument submitted with a bid that guarantees the bidder will enter the contract if awarded and will furnish required bonds. The owner may claim against it if the bidder refuses.
- Retainage
- Related: Progress Payment, Lien Waiver, Substantial Completion
A percentage of each payment withheld by the owner until the project or a defined phase is complete. It protects the owner against incomplete work and unpaid claims.
- Progress Payment
- Related: Schedule of Values, Retainage, Punch List
Periodic payment to the contractor for work completed and materials stored during a billing period, based on an approved application for payment.
- Schedule of Values
- Related: Progress Payment, Change Order, Pay Application
An itemized breakdown of the contract price allocated to work phases or trades. It supports progress billing and is often required with the first payment application.
- Change Order
- Related: Construction Change Directive, Request for Information, Schedule of Values
A written agreement signed by owner and contractor that modifies the scope, price, or schedule of the contract. It becomes part of the contract documents once executed.
- Construction Change Directive
- Related: Change Order, Request for Information, Delay Claim
A written order from the owner directing a change before price and time are agreed. It lets work proceed while the parties later settle cost and schedule adjustments.
- Request for Information
- Related: Change Order, Shop Drawing, As-Built Drawings
A formal written question from the contractor to the design team seeking clarification of drawings, specifications, or contract terms. Responses become part of the project record.
- Shop Drawing
- Related: Request for Information, Submittal, As-Built Drawings
A detail drawing, diagram, or data sheet prepared by a contractor or supplier showing how a portion of the work will be fabricated or installed, submitted for review before construction.
- Submittal
- Related: Shop Drawing, Request for Information, Specification
Any product data, sample, mockup, or drawing the contractor sends to the design team for review and approval before installation, as required by the specifications.
- Substantial Completion
- Related: Punch List, Final Completion, Retainage
The stage when the work is sufficiently complete for the owner to occupy and use it for its intended purpose, leaving only minor items to finish. It often starts warranty periods.
- Punch List
- Related: Substantial Completion, Final Completion, Retainage
A written list of minor incomplete or defective items identified near completion that the contractor must correct before final acceptance and final payment.
- Final Completion
- Related: Substantial Completion, Punch List, Lien Waiver
The point when all work, including punch list items and closeout documents, is finished and accepted by the owner, triggering release of remaining payments and retainage.
- Default
- Related: Termination for Cause, Performance Bond, Delay Claim
A party's failure to perform a material contract obligation, such as missing schedule, abandoning work, or not paying subcontractors. It can trigger termination and surety claims.
- Termination for Cause
- Related: Default, Termination for Convenience, Performance Bond
The owner's ending of the contract because of the contractor's default. The owner may complete the work with others and charge the contractor for resulting excess costs.
- Termination for Convenience
- Related: Termination for Cause, Change Order, Delay Claim
The owner's ending of the contract without the contractor being at fault, typically with notice and payment for work performed plus allowable costs.
- Delay Claim
- Related: Construction Change Directive, Differing Site Conditions, Liquidated Damages
A request for additional time or money when project progress is slowed by events outside the contractor's control, such as owner-caused changes, weather, or differing site conditions.
- Liquidated Damages
- Related: Delay Claim, Substantial Completion, Default
A preset amount stated in the contract that the contractor owes the owner for each day of late completion. It must be a reasonable estimate, not a penalty.
- Differing Site Conditions
- Related: Delay Claim, Change Order, Request for Information
Physical conditions at the site that differ materially from what the contract documents indicated or that are unusual for the work, often supporting a price or time adjustment.
- Bid Opening
- Related: Bid Bond, Bidder's List, Invitation to Bid
The scheduled public or private event at which sealed bids are opened and read aloud, usually followed by evaluation and award.
- Invitation to Bid
- Related: Bid Opening, Bid Bond, Bidder's List
An owner's published request for contractors to submit priced proposals for a defined scope, with instructions, deadlines, and bid documents attached.
- Bidder's List
- Related: Invitation to Bid, Prequalification, Bid Opening
A roster of contractors who have obtained bid documents or been prequalified to submit proposals on a specific project.
- Prequalification
- Related: Bidder's List, Invitation to Bid, Contractor License
A process in which an owner screens contractors for licensing, experience, financial capacity, and safety record before allowing them to bid or be awarded work.
- Contractor License
- Related: Prequalification, Building Permit, Qualifying Party
A credential issued by a state or local authority permitting a person or firm to perform or offer construction work. Bidding or working without one can void contracts and draw penalties.
- Qualifying Party
- Related: Contractor License, Responsible Managing Employee, Building Permit
The individual whose license, examination, and experience support a construction firm's license. The firm's license depends on that person remaining connected to the business.
- Building Permit
- Related: Certificate of Occupancy, Code Compliance, Contractor License
Written government authorization to construct, alter, or demolish a structure. Work must match approved plans, and inspections are required at defined stages.
- Certificate of Occupancy
- Related: Building Permit, Substantial Completion, Code Compliance
A document issued by the building authority confirming that a completed structure complies with applicable codes and may be legally occupied and used.
- Code Compliance
- Related: Building Permit, Certificate of Occupancy, Specification
Meeting the adopted building, fire, energy, and accessibility codes that govern design and construction in the jurisdiction where the work occurs.
- Specification
- Related: Submittal, Shop Drawing, Code Compliance
The written portion of contract documents describing materials, products, workmanship standards, and performance requirements for the project, usually organized by trade divisions.
- As-Built Drawings
- Related: Shop Drawing, Submittal, Punch List
Construction drawings marked up by the contractor to record actual installed conditions, dimensions, and changes, then delivered to the owner at closeout.
- Critical Path Method
- Related: Baseline Schedule, Float, Delay Claim
A scheduling technique that identifies the longest sequence of dependent activities, showing which tasks control the project finish date and where float exists.
- Float
- Related: Critical Path Method, Baseline Schedule, Delay Claim
The amount of time an activity can slip without delaying the project finish or a later activity. Ownership of float is often addressed in contract scheduling clauses.
- Baseline Schedule
- Related: Critical Path Method, Float, Substantial Completion
The initial approved project schedule against which actual progress and time impacts are measured throughout construction.