UPS Addition Without Losing 2N Redundancy

DCSW · Put your knowledge to work in context.

All case studies

UPS Addition Without Losing 2N Redundancy

A 500 kW dual-corded IT load is served by two 600 kVA/600 kW UPS modules configured as 2N. Each UPS currently carries about 250 kW. The site has a 1,000 kVA standby generator, 12 kV utility service, and flooded-cell batteries that are seven years old. At the present load, a recent discharge test measured nine minutes of runtime to end voltage; the design requirement is ten minutes at full load. The business wants to add 150 kW of storage and GPU equipment without changing the UPS or generator. The electrical contractor says the UPS modules are only at 42% load, so there is 'plenty of headroom.' The generator was last load-banked at 80% two years ago. The utility has had two outages in 18 months, each lasting 20-35 minutes. The facility operates 24/7 and cannot accept a full shutdown this year.

1. Calculate the post-addition UPS loading and determine whether 2N redundancy is maintained. Show assumptions.

Read the worked answer

Assume the 150 kW is balanced across the two power paths and the critical load is dual-corded. New total = 500 + 150 = 650 kW. Each UPS carries about 325 kW, or 54% of its 600 kW rating. That is not the relevant test for 2N. On loss of one UPS, the surviving module must carry the entire 650 kW. Its rating is 600 kW, so it would be at 108% and would either go to static bypass, transfer to the other source, or shut down, depending on settings. Redundancy is therefore lost, even though normal loading looks comfortable. The contractor's 42% figure describes present average load, not contingency capacity. The addition can only proceed without UPS changes if the critical load is capped at 600 kW or load shedding is proven to drop at least 50 kW automatically. Verify actual kW, power factor, and phase balance; kVA ratings alone are insufficient.

2. Evaluate battery and generator readiness for the added load. What tests and calculations are needed before acceptance?

Read the worked answer

The battery is already marginal: nine minutes at 500 kW does not meet a ten-minute requirement, and at 650 kW the delivered runtime will be significantly shorter, perhaps roughly six to seven minutes before end voltage, before accounting for aging and temperature. A seven-year-old flooded battery may also be at or beyond its useful life. Require a capacity test at the new load or a manufacturer's aged-battery calculation; replace or augment the battery if the required runtime at end-of-life cannot be guaranteed. The 1,000 kVA generator is nominally 800 kW at 0.8 PF, but it serves the whole site, not just the UPS. Verify actual site peak, generator derating for altitude and temperature, fuel autonomy, transient response to the UPS step load, and breaker and ATS coordination. Load-bank at the anticipated peak with the UPS on battery and the mechanical load running. Two outages of 20-35 minutes also mean the battery must bridge until the generator is stable, not just start.

3. Recommend a phased plan to support the 150 kW addition while preserving redundancy and avoiding a full shutdown.

Read the worked answer

Phase the work. First, model and meter the actual load; freeze new installations until capacity is proven. Second, replace or augment batteries and load-bank the generator, because those are prerequisites. Third, install UPS capacity that allows each module to carry the full 650 kW, using modular frames or a temporary parallel UPS if a full shutdown is impossible. Migrate one cord at a time during controlled windows, validate dual-cord balance, and test transfer to each module and to bypass. If capital is not approved this year, cap the addition at 600 kW and implement automatic load shedding of at least 50 kW; document that this is a temporary risk acceptance. Do not accept a plan that relies on the second UPS being healthy during maintenance.