DCSW · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Data Center Design and Standards

  • Build a one-page map of the standards landscape: map each of the four ANSI/TIA-942, Uptime Institute Tier, BICSI 002, and EN 50600 rating schemes to the four availability levels and note where the definitions diverge.

  • Distinguish rated vs. concurrently maintainable vs. fault tolerant topologies by writing three short worked examples that classify a given single-line description into the correct topology class.

  • Translate the tier/criticality concepts into design consequences: list for each level which distribution paths, redundant components, and maintenance procedures are implied.

  • Define the key design-basis parameters (design IT load density, floor loading, ceiling height, redundancy class, availability target) and record the typical value ranges used in practice.

  • Summarize the standards' treatment of site selection, structural loading, and compartmentalization in your own notes with clause-level references you can cite.

Your checkpoint

A 2-page standards crosswalk table (rows = design attributes, columns = each rating scheme) plus a 1-page glossary of 25 design terms, self-quizzed to 90% recall.

Week 2

Electrical Systems and Power Distribution

  • Trace utility service from the medium-voltage feed through transformers, switchgear, ATS/STS, UPS, and PDU to the rack, and label every point of redundancy on your own single-line diagram.

  • Compare UPS topologies (double conversion, line-interactive, rotary, modular) on efficiency, ride-through, fault clearing, and maintenance bypass implications, and state which fits which tier.

  • Size a battery string from a stated load profile: compute required runtime, apply aging and temperature derating, and verify the result against a manufacturer's discharge curve.

  • Explain grounding and bonding for a data center: separately derived systems, bonding jumpers, isolated ground myths, and the role of the equipotential ground grid.

  • Explain generator and fuel-system design decisions: N+1 sizing, load-step acceptance, fuel polishing, day-tank sizing, and testing under load.

Your checkpoint

A hand-drawn or CAD single-line diagram of a concurrently maintainable electrical topology with all redundancy points labeled, plus a worked battery-sizing calculation showing derating factors.

Week 3

Mechanical Systems, Cooling and Environmental Control

  • Compute heat load from IT, lighting, people, and envelope, and convert between kW, tons, and CFM so you can sanity-check any vendor's numbers.

  • Compare air-cooled, water-cooled, and economizer-based cooling plants on PUE impact, water use, and climate suitability, and justify a selection for two contrasting climates.

  • Design an airflow path: choose containment strategy, calculate bypass and recirculation, and set supply/return temperature targets within ASHRAE recommended envelopes.

  • Explain liquid cooling options (direct-to-chip, immersion, rear-door heat exchangers) and identify the rack densities at which air cooling stops being practical.

  • Draft a humidity and pressurization control strategy that avoids both overcooling and condensation risk, and state the failure modes if it is misconfigured.

Your checkpoint

A cooling design brief for a 1 MW hall: heat-load calculation, chosen cooling architecture with justification, containment plan, and target PUE with the assumptions behind it.

Week 4

ICT and Network Infrastructure

  • Design a structured cabling hierarchy from entrance facility to horizontal distribution, specifying media, distance limits, and pathway separation from power.

  • Explain redundancy at the network layer: compare redundant switch pairs, MLAG/VPC, and routed designs, and state what each protects against.

  • Distinguish meet-me-room, MDA, HDA, EDA, and ZDA roles and describe how cross-connect and interconnect architectures change the cabling count.

  • Plan physical infrastructure for growth: port density per rack, fiber counts, conduit fill, and labeling schemes that survive a decade of change.

Your checkpoint

A cabling and network architecture diagram with a bill of materials (media types, counts, distances) and a written justification of the redundancy model chosen.

Week 5

Fire Protection and Life Safety & Security and Physical Access Control

  • Select detection technology per zone (spot smoke, VESDA/ASD, linear heat, water-flow) and justify placement in white space, ceiling voids, and subfloors.

  • Design a clean-agent suppression scheme: agent selection, concentration calculation inputs, hold time, and enclosure integrity testing requirements.

  • Sequence a fire event end to end: detection, alarm, suppression release, damper/shutdown interlock, egress, and coordination with the fire authority.

  • Build a layered physical security model: perimeter, lobby, mantraps, cabinet locks, and the credential and anti-passport (tailgating) controls at each layer.

  • Map surveillance and access-control data retention, privacy, and audit obligations to the operational procedures that enforce them.

Your checkpoint

A one-page fire and life-safety sequence-of-operations matrix plus a layered security zone diagram annotated with the control at each boundary.

Week 6

Operations, Maintenance and Commissioning

  • Write a commissioning plan covering Level 1 through Level 5: factory, site, functional performance, integrated systems, and post-occupancy, with the acceptance criteria for each.

  • Distinguish commissioning, integrated systems testing, and continuous verification, and describe what a failure during integrated testing should trigger.

  • Build a preventive maintenance calendar for electrical, mechanical, and fire systems, including the load-bank and generator test cadence and the documentation each produces.

  • Explain MOP/SOP/EOP discipline: what belongs in each, who approves, and how change control prevents configuration drift.

  • Define operational KPIs (PUE, availability, MTTR, MTBF, capacity utilization) and describe how each is measured and where the data comes from.

Your checkpoint

A commissioning test script for one integrated system (e.g., utility loss to generator-to-UPS transfer) with pass/fail criteria and a 12-month PM calendar for one plant.

Week 7

Business Continuity, Risk and Compliance & Data Center Design and Standards

  • Perform a risk assessment: identify threats (utility, weather, human, cyber-physical), score likelihood and impact, and rank mitigations by cost-effectiveness.

  • Build a business impact analysis that ties RTO and RPO for each critical system to the infrastructure and process design that delivers it.

  • Draft a continuity and recovery plan structure: roles, escalation, failover procedures, communications, and the exercise cadence that keeps it current.

  • Map compliance obligations (audit, certification, contractual SLAs, data protection) to the evidence artifacts operations must retain.

  • Revisit the week-1 standards crosswalk and reconcile it with the risk and continuity posture you have now built.

Your checkpoint

A risk register with at least 12 scored risks and a 1-page BIA table linking each critical system to its RTO/RPO and the design feature that satisfies it.

Week 8

Data Center Design and Standards & Electrical Systems and Power Distribution & Mechanical Systems, Cooling and Environmental Control & ICT and Network Infrastructure & Fire Protection and Life Safety & Security and Physical Access Control & Operations, Maintenance and Commissioning & Business Continuity, Risk and Compliance

  • Synthesize across domains by solving three full-length practice scenarios end to end and reviewing every missed item against its source concept.

  • Drill weak areas identified by practice scores, spending the majority of the week on the two lowest-scoring domains.

  • Rehearse calculations under time pressure: battery sizing, heat load, PUE, redundancy math, and availability arithmetic.

  • Build a one-page exam-day reference sheet of formulas, tier definitions, and standards names from memory, then verify it against your notes.

Your checkpoint

A scored practice exam log with per-domain accuracy, a list of the top 10 recurring error patterns, and a corrected one-page formula and definitions sheet.

Milestones

Week 2: Can draw a concurrently maintainable single-line diagram from memory and explain each redundancy point without notes.

Week 4: Can compute heat load and battery runtime for a stated scenario within 10% and defend the topology choice in one paragraph.

Week 6: Can write a Level 4/5 integrated systems test script with pass/fail criteria and describe the PM cadence for both electrical and mechanical plants.

Week 8: Score at least 80% overall on a full-length practice exam with no domain below 70%, and complete the formula sheet from memory.