Dell VxRail Deploy flashcards
Dell VxRail Deploy · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- VxRail minimum cluster size
- A standard VxRail cluster requires a minimum of three nodes so that vSAN can tolerate one failure. Two-node clusters need a witness appliance at a third site.
- vSAN RAID-5 node minimum
- Erasure-coded RAID-5 in vSAN needs at least four nodes in the cluster. Below four nodes, failure tolerance is provided by RAID-1 mirroring instead.
- vSAN RAID-6 node minimum
- RAID-6 erasure coding in vSAN requires a minimum of six nodes. It tolerates two failures but consumes more capacity overhead than RAID-5.
- Witness appliance purpose
- A witness appliance holds metadata only, not data. It provides quorum for two-node and stretched clusters so the cluster survives loss of one site or node.
- VxRail Manager role
- VxRail Manager is a VM running on the cluster that provides deployment wizards, lifecycle bundle upgrades, health monitoring, and the vCenter plugin for the VxRail system.
- NTP requirement
- All VxRail components, including ESXi hosts, vCenter, and VxRail Manager, must synchronize to reachable NTP sources. Clock skew breaks certificates and authentication during deployment.
- Deployment client prerequisites
- The browser host running the VxRail deployment wizard must resolve VxRail Manager and ESXi FQDNs, reach their management addresses, and trust the certificates presented.
- External vCenter support
- VxRail can deploy into a customer-supplied external vCenter instead of the embedded VxRail vCenter. The external vCenter must be a supported version with adequate permissions.
- iDRAC first connection
- Connect and configure the iDRAC management port before powering nodes into service. It provides remote console and virtual media for the rest of the build.
- Redundant PDU cabling
- Each VxRail node has two power supplies. Connect one PSU to the A feed and one to the B feed so a single PDU or circuit failure does not power off the node.
- Dedicated boot device
- VxRail nodes boot from a separate device such as a BOSS card or M.2 RAID-1 mirror, keeping vSAN cache and capacity drives dedicated to the datastore.
- vSAN disk group cache
- Each vSAN disk group has one cache-tier drive and one or more capacity drives. All-flash configurations use the cache drive as a write buffer.
- Firmware bundle discipline
- VxRail validates a specific firmware and software bundle for each model. Upgrade components only through the VxRail bundle, not individually, to preserve support.
- Pre-deployment hardware check
- Before starting the VxRail wizard, verify in iDRAC that power supplies, fans, memory, and all drives report healthy. A failed component halts or degrades the automated build.
- Uplink redundancy
- VxRail nodes connect to a pair of top-of-rack switches using supported optics or DAC cables. Uplinks are teamed with LACP or active/standby for path redundancy.
- Rack airflow direction
- Install VxRail nodes so air flows front to back, with the cold aisle at the front. Maintain clearance above and below the chassis to avoid hot spots.
- VxRail deployment wizard
- The initial VxRail Manager wizard collects vCenter credentials, network settings, DNS, NTP, and the software bundle, then automates the ESXi and vSAN cluster build.
- VDS default networking
- VxRail 7.x deployments use the vSphere Distributed Switch by default, with physical NICs mapped to uplinks and port groups carrying VLAN IDs per traffic type.
- Jumbo frame consistency
- vSAN and vMotion port groups commonly use MTU 9000. Physical switches, the distributed switch, and every VMkernel on the path must match or large frames are dropped.
- VMkernel IP planning
- Each ESXi node needs a separate VMkernel address for vSAN, vMotion, and management traffic. Reserve contiguous IP ranges before running the deployment wizard.
- Witness traffic separation
- Two-node and stretched clusters require a dedicated witness VMkernel and VLAN so witness traffic is isolated from vSAN and management traffic across sites.
- VxRail Manager bootstrap address
- VxRail Manager initially answers on a temporary bootstrap address. The wizard sets the permanent IP and FQDN, which must match forward and reverse DNS records.
- Post-build validation
- After the wizard completes, confirm all nodes joined the cluster, vSAN health passes in vCenter, and the VxRail plugin reports no configuration drift.
- External vCenter permissions
- Deploying to an external vCenter requires an account with sufficient privileges to create datacenters, clusters, and distributed switches, plus the VxRail-specific roles.
- VxRail bundle upgrade order
- A VxRail bundle upgrade runs VxRail Manager pre-checks, then upgrades vCenter if embedded, then ESXi nodes one at a time, then VxRail Manager itself.
- Pre-upgrade health check
- Before upgrading, confirm no degraded vSAN objects, no failed disks, and enough free capacity for rebuilds during rolling node upgrades.
- Maintenance mode data migration
- Full data migration evacuates all data from a node before service. Ensure accessibility mode only moves what is needed. Full migration requires spare capacity.
- VxRail log bundle
- The VxRail Manager log bundle collects ESXi, vCenter, and VxRail Manager logs into one archive. It is the standard first artifact for support cases.
- vSAN health network check
- The vSAN health network check tests connectivity and MTU between hosts. Failures usually indicate a VLAN mismatch or inconsistent jumbo frame configuration.
- Configuration drift reconcile
- When the VxRail plugin reports drift, use the reconcile or resync operation in VxRail Manager. Manual edits in vCenter can worsen drift and complicate support.
- VxRail Manager unreachable
- If VxRail Manager is unreachable, confirm the VM is powered on in vCenter, verify its IP and DNS records, and check that the plugin service is running.
- Rebuild reserve capacity
- Keep enough free vSAN capacity to rebuild a failed node or disk. Monitor capacity alerts and expand the cluster before usable space falls below the rebuild reserve.