Change Mgmt flashcards
Change Mgmt · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Request for Change (RFC)
- Formal document proposing a modification to a configuration item or service. Records description, justification, risk, impact, rollback plan, and approver, forming the auditable basis for assessment and authorisation.
- Standard change
- A pre-authorised, low-risk, repeatable change with a documented procedure, such as a routine password reset or adding a user. It bypasses individual CAB approval but is still logged.
- Normal change
- A change requiring full assessment, risk classification, and authorisation by the appropriate change authority, typically the CAB. It follows the complete lifecycle including scheduling and post-implementation review.
- Emergency change
- A change needed to restore service or address a critical vulnerability, using an expedited approval path. It is documented retrospectively and reviewed to prevent recurrence.
- Change Advisory Board (CAB)
- A group that assesses and authorises normal changes by reviewing risk, impact, readiness, and scheduling. It advises and approves; implementation remains with delivery teams.
- Change freeze
- A defined period when normal changes are prohibited, such as year-end or peak trading. Only emergency changes proceed, under heightened scrutiny and senior authorisation.
- Seven Rs of change
- Assessment questions: raised (who/when), reason, return (benefit), risks, resources, responsible (owner and implementer), and relationships (dependencies). Answers determine approve, defer, or reject.
- Change failure rate
- Percentage of changes that cause an incident, rollback, or remediation. A DORA-style delivery metric indicating change quality and the effectiveness of testing and assessment.
- Unauthorised change
- Any change implemented without required approval or record. Tracked as a compliance metric because it bypasses impact analysis, rollback planning, and configuration records.
- Configuration item (CI)
- Any component under configuration control: hardware, software, documentation, or service. Changes reference affected CIs so impact analysis and rollback scope are accurate.
- CMDB
- Configuration Management Database holding records of configuration items and their relationships. Supports impact analysis, dependency mapping, and incident diagnosis during change.
- Rollback plan
- Documented procedure to revert a change to the prior known-good state, including triggers, steps, verification, and time limit. Required before authorisation of higher-risk changes.
- Change lead time
- Elapsed time from change request submission to deployment in production. A flow metric revealing approval bottlenecks, batch sizes, and handoff delays.
- Post-implementation review
- Structured check after a change verifying intended outcome, absence of unexpected side effects, and closure of actions. Feeds lessons learned into future change assessment.
- Change authority
- The person or group empowered to approve a given class of change, defined by risk and cost thresholds. Delegation must be explicit and recorded to keep approvals auditable.
- Kotter's eight steps
- Sequenced model: urgency, coalition, vision, communication, enable action, short-term wins, consolidate gains, anchor in culture. Skipping early steps produces superficial adoption that erodes later.
- Lewin's change model
- Three phases: unfreeze existing behaviour, implement the transition, refreeze new practice. Refreezing requires reinforcement through policy, metrics, and role expectations to prevent reversion.
- ADKAR model
- Individual change sequence: Awareness, Desire, Knowledge, Ability, Reinforcement. Progress is blocked by the weakest element, so diagnosis targets the first gap rather than the final outcome.
- Bridges' transition model
- Psychological transition with three stages: ending, neutral zone, new beginning. The neutral zone carries the largest productivity dip and needs explicit structure and communication.
- Guiding coalition
- A cross-functional group with authority, credibility, and expertise that sponsors the change. It must act visibly and consistently, since inconsistent sponsor behaviour undermines adoption fastest.
- Burning platform
- A communicated, credible case for urgency showing the cost of inaction. Effective only when backed by evidence; manufactured crises erode trust and increase cynicism.
- Stakeholder power-interest grid
- Mapping stakeholders by influence and stake. High power and high interest: manage closely; high power, low interest: keep satisfied; low power, high interest: keep informed.
- Resistance analysis
- Classifying opposition as rational (workload, cost), emotional (fear, identity), or political (influence loss). Each cause requires a different response; treating all as attitude problems fails.
- Change readiness assessment
- Pre-implementation evaluation of leadership alignment, capability, capacity, change history, and culture. Low readiness scores predict adoption failure and justify sequencing or delay.
- Change curve
- Adapted grief sequence: shock, frustration, bargaining, low mood, acceptance. Support style should shift per stage, from information early to involvement and coaching later.
- Communication plan
- Specifies audience segments, key messages, channels, frequency, owner, and feedback loop. Repetition across channels is required because single-channel announcements rarely shift behaviour.
- Benefits realisation plan
- Defines baseline, target, measure, owner, and review date for each expected benefit. Distinguishes leading adoption indicators from lagging business outcome measures.
- Change saturation
- The point where concurrent initiatives exceed organisational capacity to absorb them. Symptoms include project delays, fatigue, and compliance decay; managed by sequencing and portfolio limits.
- Sponsor roadmap
- Schedule of visible sponsor actions across the change lifecycle, such as town halls, decisions, and reinforcement messages. Makes active sponsorship a tracked commitment rather than an assumption.
- Training needs analysis
- Identifies which roles need which skills before go-live, and the gap from current capability. Outputs drive training design, timing, and the ability element of ADKAR.
- Adoption metric
- A leading indicator of behaviour change, such as active usage, process compliance, or ticket deflection. Tracked early to predict whether lagging business benefits will materialise.
- Lessons learned register
- A maintained record of what worked and failed in past changes. Used at initiation to avoid repeating known pitfalls and to calibrate risk assessment and effort estimates.