- Degree of static indeterminacy
- Number of unknown reactions plus internal forces minus available equilibrium equations. In 2D, three equations exist per free body, so a propped cantilever is one degree indeterminate.
- Euler buckling load
- Critical axial load for a slender column given by Pcr = pi squared times EI divided by effective length squared. Effective length factor depends on end restraint conditions.
- Terzaghi bearing capacity equation
- Ultimate bearing pressure for a strip footing equals cohesion times Nc plus surcharge times Nq plus half gamma B N gamma. Bearing capacity factors depend on friction angle.
- Consolidation settlement formula
- Primary settlement equals Cc times thickness divided by one plus initial void ratio, multiplied by log of final over effective initial vertical stress ratio.
- Balanced reinforcement ratio
- Reinforcement ratio at which concrete crushing and steel yielding occur simultaneously. Computed from concrete strength, steel yield strength, and steel elastic modulus.
- Lateral-torsional buckling
- Failure mode of steel beams bent about the strong axis when unbraced length exceeds a limit. Nominal moment reduces below plastic moment capacity as unbraced length grows.
- Total float in CPM
- Difference between late start and early start, or late finish and early finish. Activities with zero total float form the critical path controlling project duration.
- Earned value cost performance index
- Ratio of earned value to actual cost. Values above one indicate under-budget performance; values below one indicate cost overrun on the project.
- Manning equation
- Empirical open channel velocity formula: velocity equals one over roughness coefficient, times hydraulic radius to two-thirds power, times slope to one-half power.
- Rational method peak flow
- Peak discharge equals runoff coefficient times rainfall intensity times catchment area, with a unit conversion factor. Assumes uniform rainfall over the catchment.
- Stopping sight distance
- Distance for a driver to perceive, react, and stop before an obstacle. Sum of reaction distance and braking distance, adjusted for roadway grade.
- Superelevation minimum radius
- Minimum horizontal curve radius equals design speed squared divided by 127 times the sum of superelevation rate and side friction factor.
- BOD exertion equation
- Biochemical oxygen demand at time t equals ultimate BOD times one minus exponential of negative rate constant times time. Standard test measures five-day demand.
- Sedimentation overflow rate
- Flow divided by surface area of settling basin. Particles with settling velocity greater than or equal to this rate are completely removed in ideal conditions.
- Bowditch traverse adjustment
- Method distributing closure error in proportion to leg length. Corrections applied to latitudes and departures so the traverse closes exactly.
- Azimuth from coordinates
- Horizontal angle measured clockwise from north, computed as arctangent of easting difference over northing difference. Quadrant must be resolved correctly.
- Engineer sealing work
- A licensed engineer may seal only drawings and calculations personally prepared or directly supervised. Sealing unreviewed work of others is unethical.
- Egyptian concrete cover
- Minimum distance from bar surface to concrete surface, specified by exposure condition. Typically 25 mm slabs and 40 mm beams in mild exposure.
- Characteristic concrete strength
- Compressive strength below which no more than five percent of test results are expected to fall. Determined from standard cube or cylinder tests at 28 days.
- Concrete slump test
- Workability measure recording vertical settlement of a concrete cone after removal. Typical values range from 25 to 100 millimetres for normal construction.
- Net present value
- Sum of discounted cash inflows minus outflows over project life. Positive value at the required rate of return indicates an economically acceptable project.
- Benefit-cost ratio
- Present worth of benefits divided by present worth of costs. A ratio greater than or equal to one indicates the project is economically justified.
- Seismic base shear
- Total lateral design force equal to seismic response coefficient times seismic weight. Coefficient depends on spectral acceleration, response modification, and importance.
- Ductile detailing
- Detailing provisions ensuring structures deform without brittle failure. Includes closely spaced confinement, strong-column weak-beam hierarchy, and adequate joint shear capacity.
- Time of concentration
- Time for runoff to travel from the most hydraulically remote point to the outlet. Used as storm duration in the rational method.
- Curve number method
- Estimates direct runoff from rainfall using soil group and land cover. Potential retention relates to curve number; runoff computed from rainfall excess.
- Retaining wall sliding factor
- Ratio of resisting horizontal forces to driving horizontal forces. Minimum acceptable value typically one and a half for stability against sliding.
- Wellpoint dewatering
- System of shallow wells connected to a header pipe and pump. Effective for lowering groundwater up to about five metres in permeable soils.
- Prestress losses
- Reduction in initial prestress from elastic shortening, creep, shrinkage, relaxation, and friction. Typically fifteen to twenty-five percent for post-tensioned members.
- Bridge scour
- Erosion of bed material around piers and abutments from flowing water. Estimated by empirical equations considering flow depth, velocity, and pier geometry.
- Coagulation optimum pH
- pH range where coagulant achieves best particle destabilisation. For alum, optimum typically lies between six point five and seven point five.
- Water hammer pressure surge