Egypt Engineering Consultant Electrical study plan
Egypt Engineering Consultant Electrical · Give each week a clear focus.
8 weeks · About 7 hours per week
Power System Analysis and Design
Build a one-page formula sheet covering per-unit conversion, symmetrical components, and short-circuit MVA method, then solve five load-flow and fault problems using it without notes
Compute a 3-phase and single-phase fault current at two bus levels of a simple radial industrial network by hand and verify with software or a spreadsheet model
Explain in writing when to apply per-unit versus actual-quantity analysis and list the base-change formulas from memory
Draw the positive, negative, and zero-sequence networks for a transformer-grounded generator arrangement and annotate where zero-sequence current can flow
Your checkpoint
A 10-problem worked solution set on load flow and fault analysis, each with assumptions, formula sheet reference, and a numeric answer checked against a second method
Power System Analysis and Design & Electrical Installation and Distribution Systems
Size feeders and protective devices for a multi-storey distribution board using derating factors for ambient temperature, grouping, and installation method
Calculate voltage drop for the longest feeder by both the mV/A/m tabular method and the impedance method, and reconcile any difference
Produce a single-line diagram for a small building service including utility intake, main switchboard, sub-mains, and generator/ATS changeover
Select cable cross-sections for three circuits and justify each choice against ampacity, voltage drop, and short-circuit withstand
Your checkpoint
A complete single-line diagram plus a cable and protection schedule for a 5-floor building, with voltage drop and derating calculations shown for every feeder
Electrical Installation and Distribution Systems & Protection, Switchgear, and Coordination
Classify the earthing system (TN-S, TN-C-S, TT) for three described installations and state the protective-device requirements for each
Compute prospective fault current at each distribution level and select breaking capacity for every device in the chain
Build a discrimination study between upstream and downstream devices using time-current curves, and identify at least one loss-of-discrimination point
Size a residual current device scheme for socket circuits and justify sensitivity and time delay choices
Your checkpoint
A coordination study for a 4-level distribution system showing time-current curves, selected device ratings, and a written note on every discrimination margin
Protection, Switchgear, and Coordination & Electrical Codes and Egyptian Standards
Map each major design decision from weeks 1-3 to the clause that governs it in the Egyptian Electrical Code and the relevant IEC standard
List the mandatory tests and inspection items required before energizing an installation and state acceptance criteria for each
Identify ten common code non-compliances from a written description of an installation and cite the requirement violated
Summarize differences between Egyptian code requirements and IEC 60364 practice for earthing, conductor sizing, and protection
Your checkpoint
A code-compliance checklist of at least 40 line items, each cross-referenced to a clause number and marked pass/fail against your week 2 design
Electrical Safety, Earthing, and Lightning Protection & Lighting and Illumination Engineering
Design an earthing system for a substation with a given soil resistivity profile, compute grid resistance, and check step and touch potentials against permissible limits
Size a lightning protection system using the rolling sphere method for a described structure and select down-conductor count and spacing
Perform a lumen method calculation for an office and a workshop, then verify illuminance uniformity and select luminaires to meet the target maintained illuminance
Explain the difference between earthing for fault protection and earthing for lightning, and state why bonding of services matters for both
Your checkpoint
An earthing and lightning protection design report with soil model, grid resistance calculation, step/touch voltage check, and a lighting layout with lumen calculations for two space types
Renewable Energy and Energy Efficiency & Electrical Materials, Testing, and Commissioning
Size a grid-tied PV system for a given daily load profile including array, inverter, and cable selection, and compute the payback period
Write a commissioning test plan listing insulation resistance, continuity, earth electrode resistance, RCD trip time, and protective device tests, with instruments and acceptance values
Describe the procedure for transformer oil testing and interpret a dissolved gas analysis result
Evaluate two energy-efficiency measures for an existing building and quantify annual savings and demand reduction for each
Your checkpoint
A combined PV sizing and commissioning package: PV calculation sheet with payback analysis plus a commissioning test plan with acceptance criteria for every test
Project Management, Contracts, and Engineering Ethics
Draft a scope of work and payment schedule for an electrical design consultancy assignment under a FIDIC-style contract, identifying deliverables and milestones
Analyze three ethics scenarios involving conflict of interest, sign-off responsibility, and pressure to relax a safety requirement, and state the correct action with justification
Build a simple earned value report from given project data and interpret cost and schedule variance
List the contractual steps for handling a design change and the documentation required to protect the consultant's position
Your checkpoint
A contract and ethics case-study portfolio: one scope of work with payment schedule, one earned value analysis, and three written ethics rulings with cited reasoning
Power System Analysis and Design & Electrical Installation and Distribution Systems & Protection, Switchgear, and Coordination & Electrical Codes and Egyptian Standards & Electrical Safety, Earthing, and Lightning Protection
Complete two full timed mock exams under exam conditions and score each by domain to find weak areas
Re-solve every question missed in the mocks and write a one-line reason for each error
Review the formula sheet, code checklist, and design reports from weeks 1-7 and consolidate into a single exam-day reference
Rehearse the highest-weight domain calculations until each can be completed within the target time per question
Your checkpoint
Two scored mock exams with an error log and a consolidated one-page exam-day reference sheet covering formulas, code clause numbers, and acceptance values
Milestones
Week 2: Can complete a fault current calculation and a feeder sizing calculation from a blank page in under 20 minutes each, with correct units and assumptions stated
Week 4: Code checklist is complete with clause references, and at least 35 of 40 items are correctly classified against your own design
Week 6: Earthing, lightning, lighting, and PV calculations all reproduce correctly on a second attempt without referring to the worked solution
Week 8: Mock exam scores are at or above 70 percent overall with no single domain below 60 percent