EXIN Dynamic Project Management Method Project Manager flashcards
EXIN Dynamic Project Management Method Project Manager · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Dynamic project model
- A structured set of linked objects - deliverables, activities, resources, conditions, and decisions - from which schedules are generated and regenerated as circumstances change, rather than a fixed hand-drawn plan.
- Deliverable object
- A defined result the project must produce. It is realized only when its producing activity completes and all conditions attached to that activity are satisfied.
- Activity object
- Work that transforms input deliverables into output deliverables. It requires named resources to execute and is bound by start and completion conditions.
- Resource object
- A person, team, tool, or facility required to execute an activity. Resource availability constrains scheduling and can itself be expressed as a condition on the activity.
- Condition object
- A boolean predicate or constraint that must hold for an activity to start or finish. If a condition becomes false, dependent activities are invalidated and downstream re-planning is triggered.
- Decision object
- A model node representing a choice among alternative activity sets. Exactly one branch is active at a time, and switching branches is a controlled change requiring impact analysis.
- Model versus schedule
- The model states what must be true and how objects relate; the schedule states when work happens. One model can yield many successive schedules without changing its underlying logic.
- Realized deliverable
- A deliverable whose producing activity is complete and whose governing conditions are all satisfied. Realized deliverables, not activity percentages, are the unit of progress reporting.
- Orphan deliverable
- A deliverable with no producing activity in the model. It is a validation defect that must be resolved before the model can be baselined.
- Orphan activity
- An activity that produces no deliverable. It is a validation defect indicating either a missing output definition or work that should be removed from scope.
- Dependency cycle
- A closed loop of activity dependencies in which each activity waits on another in the same chain. Cycles make the model unschedulable and must be broken before baselining.
- Model validation
- The pre-baseline check for orphan nodes, dependency cycles, unreachable conditions, and unassigned decision branches. A model failing validation cannot be approved as a baseline.
- Baseline in DPMM
- An approved snapshot of the model and its generated schedule at a point in time. Changes to the model after baselining require impact analysis and re-approval of affected segments.
- Impact analysis
- Tracing the downstream effect of a change to a deliverable, condition, or decision branch through all dependent nodes, to identify which activities, dates, and approvals are affected.
- Critical path in DPMM
- The longest chain of dependent activities through the model. Activities on it have zero float, so any delay there moves the project completion date directly.
- Float calculation
- Float equals late start minus early start, or late finish minus early finish. Zero-float activities form the critical path; positive float indicates scheduling slack.
- Percent-complete fallacy
- Treating an activity at partial completion as delivered value. In DPMM an incomplete activity has realized no deliverable, so progress counts only completed outputs.
- Condition failure
- The event of a previously true condition becoming false. It invalidates dependent activities and forces re-planning of the affected downstream portion of the model.
- Contingency activity
- A prepared activity attached to a risk condition that activates through a decision node if that condition fails, allowing a planned response rather than an improvised one.
- Decision branch switch
- Changing which alternative path under a decision node is active. It is a controlled model change requiring sponsor approval when it affects the critical path or baseline.
- Iterative elaboration
- The practice of adding model detail in successive cycles as understanding grows, re-validating and re-baselining each cycle rather than specifying everything upfront.
- Project manager role
- Owns model integrity, baseline control, and re-planning execution. Escalates changes affecting the critical path or approved decision branches to the sponsor.
- Sponsor role
- Approves baselines and decision branches and receives escalations. Holds authority over scope-level model changes that the project manager cannot approve alone.
- Team member role
- Executes activities, reports status, and reports condition changes promptly. Supplies the factual input that keeps the model an accurate representation of reality.
- Escalation threshold
- The rule that condition changes altering the critical path or an approved decision branch go to the sponsor, while changes confined within float stay with the project manager.
- Model detail sufficiency
- The principle that the model should carry only the detail needed to support actual decisions and control points. Excess detail adds maintenance cost without improving control.
- Dynamic re-planning
- Regenerating the schedule from the model after a condition change or decision switch, then re-validating and re-approving the affected baseline segment before execution resumes.
- Top-down deliverable identification
- The first planning step: decompose the project goal into required deliverables before deciding what activities will produce them, keeping scope anchored to outputs.
- Bottom-up activity derivation
- The second planning step: for each deliverable, define the activities, resources, and conditions needed to produce it, working from outputs back to the work.
- Resource-constrained scheduling
- Scheduling that respects resource availability as a binding condition, which can push activities later than their pure dependency dates and shift the critical path.
- Dynamic versus agile
- Dynamic refers to model-driven re-planning when conditions change; agile is a branded iterative delivery framework. The exam treats them as distinct concepts and penalizes conflation.
- Change control in DPMM
- Any alteration to a deliverable definition, condition, or active decision branch requires impact analysis on dependent nodes plus re-approval of the affected baseline segment.
- Progress by realized output
- Reporting project status as the count or weight of realized deliverables rather than activity completion percentages, giving a factual measure of delivered value.