DPMO at six sigma
Defects per million opportunities at six sigma equals 3.4 when the conventional 1.5 sigma long-term shift is applied; without the shift, six sigma corresponds to about 0.002 defects per million.
DMAIC vs DMADV
DMAIC improves an existing process that is not meeting requirements. DMADV (Design for Six Sigma) creates a new product or process when no baseline exists or redesign is required.
Value-added criteria
A step is value-added only if the customer would pay for it, it physically changes the product or information form, fit, or function, and it is performed correctly the first time.
Eight wastes acronym
TIMWOODS: Transport, Inventory, Motion, Waiting, Overproduction, Overprocessing, Defects, and Skills or talent unused. Overproduction is usually considered the worst waste because it hides the others.
Champion and sponsor role
The champion selects and funds projects, removes organizational barriers, and owns the business result. The sponsor or process owner accepts the improved process at handoff and sustains the gains.
Cost of poor quality
Four categories: internal failure, external failure, appraisal, and prevention. Prevention and appraisal are control costs; internal and external failures are the cost of failing to meet requirements.
Kaizen versus kaikaku
Kaizen is continuous, incremental improvement performed by the people doing the work. Kaikaku is radical, breakthrough redesign of a process, often led by a cross-functional team.
Problem statement content
States the measurable gap between current and required performance, including metric, baseline, time frame, and location, without naming a cause or prescribing a solution.
SIPOC diagram purpose
Suppliers, Inputs, Process, Outputs, Customers. It defines project scope with five to seven high-level process steps and links supplier inputs to customer outputs before detailed mapping.
CTQ tree structure
Translates a verbatim voice-of-customer need into a quality driver and then into a measurable characteristic with a target and tolerance that can be tracked in the process.
Kano model categories
Must-be requirements cause dissatisfaction when absent but do not delight when present. Performance requirements scale linearly with satisfaction. Delighters create disproportionate satisfaction when present but are not expected.
SMART goal statement
Specific, Measurable, Achievable, Relevant, and Time-bound. In a charter it quantifies the improvement against the baseline and states the deadline for achieving it.
Pareto chart interpretation
Ranks causes by frequency or cost in descending bars with a cumulative percentage line. It focuses effort on the few categories that account for most of the problem.
RACI matrix meaning
Responsible performs the work, Accountable is the single decision owner, Consulted provides two-way input, Informed receives one-way updates. Only one person should be Accountable per deliverable.
Repeatability versus reproducibility
Repeatability is variation when one operator measures the same item repeatedly with the same gauge. Reproducibility is variation between different operators using the same gauge on the same items.
Gage R&R acceptance criteria
Percent Gage R&R below 10 percent is acceptable, 10 to 30 percent is conditionally acceptable depending on risk and cost, and above 30 percent is unacceptable and requires gauge improvement.
Measurement discrimination rule
The measurement increment should be no larger than one tenth of the process tolerance or of the total process variation, giving at least ten distinct readings across the range.
Cp and Cpk formulas
Cp equals (USL minus LSL) divided by six sigma. Cpk equals the smaller of (USL minus mean) or (mean minus LSL), each divided by three sigma. Cpk penalizes off-center processes.
Ppk versus Cpk
Cpk uses within-subgroup short-term sigma and reflects potential capability. Ppk uses the overall long-term standard deviation and reflects actual performance. Ppk is normally lower than Cpk.
Attribute agreement kappa
Kappa adjusts agreement for chance. Values above 0.75 indicate good agreement, 0.40 to 0.75 is marginal, and below 0.40 indicates poor agreement among appraisers or against a standard.
Sample size for a mean
n equals (z times s divided by E) squared, where z is the standard normal value for the confidence level, s is the standard deviation estimate, and E is the desired margin of error.
Hypothesis test p-value
The probability of observing data at least as extreme as the sample if the null hypothesis is true. Reject the null hypothesis when the p-value is less than the chosen significance level alpha.
Type I and Type II error
Type I error, alpha, rejects a true null hypothesis, which is producer risk. Type II error, beta, fails to reject a false null hypothesis, which is consumer risk. Power equals one minus beta.
Test choice by data type
Continuous response with categorical factor: two-sample t-test for two levels, ANOVA for three or more. Two categorical variables: chi-square. Two continuous variables: correlation or regression.
ANOVA F statistic
F equals mean square between groups divided by mean square within groups. A large F with p below alpha indicates at least one group mean differs, requiring post-hoc pairwise comparison.
Paired t-test condition
Used when observations are naturally matched, such as before-and-after on the same unit. It tests whether the mean of the within-pair differences equals zero.
Coefficient of determination r-squared
The proportion of variation in the response explained by the regression model. A high r-squared does not prove causation and does not by itself confirm that model assumptions are satisfied.
FMEA risk priority number
RPN equals Severity times Occurrence times Detection, each scored typically from one to ten. Higher RPN means higher priority, but high-severity items are addressed regardless of RPN.
DOE design resolution
Resolution III aliases main effects with two-factor interactions. Resolution IV clears main effects but aliases two-factor interactions with each other. Resolution V clears main effects and two-factor interactions.
Poka-yoke categories
Prevention devices stop an error from occurring, using contact, fixed-value, or motion-step methods. Detection devices signal that an error occurred. Prevention at the source is preferred.
SPC chart selection rule
Continuous data uses X-bar and R for small subgroups, X-bar and s for larger subgroups, and individuals with moving range for single observations. Attribute data uses p, np, c, or u charts.
Control limits versus specifications
Control limits are computed as plus or minus three sigma from process data and describe what the process actually does. Specification limits come from customer requirements and are never drawn on a control chart.