EXIN LSSA Lean Six Sigma Yellow Belt study materials
EXIN LSSA Lean Six Sigma Yellow Belt study resources

EXIN LSSA Lean Six Sigma Yellow Belt: Improve phase: improvement and waste-elimination tools

EXIN LSSA Lean Six Sigma Yellow Belt · Work through your exam, one topic at a time.

All guide sections

Improve phase: improvement and waste-elimination tools

Improve turns verified causes into changes that work in practice. The exam asks you to choose a suitable tool for a situation, to know how solutions are generated and selected with discipline, and to recognise Lean techniques by name and purpose.

Generate, select, test

  • Brainstorming: silent generation first, no criticism, build on others, then cluster the output.
  • Benchmarking and SCAMPER prompts keep the option set wider than one person's preferred fix.
  • Selection: impact/effort matrix for speed, Pugh matrix against a datum, FMEA (RPN = Severity × Occurrence × Detection) to expose risk the change creates.
  • Pilot: small-scale, time-boxed, measured against the same operational definitions and the Measure baseline.

Lean elimination tools

  • 5S: Sort, Set in order, Shine, Standardize, Sustain - workplace discipline that makes other waste visible.
  • Poka-yoke: mistake-proofing by prevention (impossible to do wrong) or detection (immediately obvious).
  • SMED: separate internal from external setup to cut changeover time.
  • Kanban and pull: replenishment triggered by consumption, not forecast.
  • Standard work and line balancing: agreed task sequence matched to takt time.
  • Cellular layout: equipment grouped by product family to cut transport and waiting.

Worked example

An FMEA scores mislabelled totes at RPN 168 (S=7, O=6, D=4) and a scanner that cannot read damaged labels at RPN 126 (S=9, O=2, D=7). Ranking by RPN alone favours 168, but severity 9 signals a safety or compliance risk and detection 7 is weak. Reasoning: a high-severity failure is addressed first regardless of the RPN total; RPN is a prioritisation aid, not a decision rule.

Traps that cost marks

  • Selecting the first idea that fits the cause.
  • Buying a capital solution when a poka-yoke or layout change is cheaper, faster and more robust.
  • Piloting without holding the measurement system and definitions constant.
  • Treating 5S as a cleaning campaign rather than a workplace standard.
  • Ignoring waste or defects shifted downstream by the change.