FAC-C Professional: Pre-Award: Market Research, Requirements, and Solicitation

FAC-C Professional ยท Work through your exam, one topic at a time.

All guide sections

Pre-Award: Market Research, Requirements, and Solicitation

Market research first

Market research (FAR Part 10) is the bridge between a need and a strategy. It answers whether commercial items exist, how many capable sources there are, what price is realistic, and whether a small business set-aside is appropriate. Do it before finalizing strategy, document the results, and scale the effort to the dollar value and risk.

Choosing the requirement document

  • Statement of Work (SOW): describes work the contractor performs (contractor shall...).
  • Performance Work Statement (PWS): describes outcomes plus measurable performance standards and the surveillance method.
  • Statement of Objectives (SOO): states high-level goals and lets offerors propose the PWS.
  • Specification: precise technical or design requirements. A common error is writing a PWS that lacks measurable standards, or a SOW that smuggles design specs into a service buy.

Solicitation mechanics

Sealed bidding (FAR 14) requires a firm-fixed-price, award to the lowest responsive, responsible bidder on price and price-related factors, and no discussions. Negotiated procurement (FAR 15) permits tradeoffs, discussions, and best-value. Commercial acquisitions (FAR 12) use streamlined procedures. Section L (instructions) and Section M (evaluation factors) must mirror each other exactly: nothing may be evaluated that is not stated in Section M.

Also know: synopsis publication at least 15 days before solicitation issuance (FAR 5.201) absent an exception; a justification for brand-name-or-equal requirements; subcontracting plans when the offer reaches $750,000 ($1.5 million for construction); and amendments that change requirements must extend deadlines when fairness requires.

Worked example

A $2 million help-desk requirement at three sites. Market research finds GSA schedule holders and several small resellers. The CO sets the acquisition aside for small business, drafts a PWS with service-level metrics (response time, resolution rate, customer satisfaction), states in Section M that technical and past performance are significantly more important than price, and states that award may be made without discussions.

Trap to avoid

Treating market research as a one-time checkbox instead of documented evidence that shaped the strategy.