- Certified vs. registered contractor
- A certified fire protection system contractor may work anywhere in Florida; a registered contractor is limited to the municipality or county that issued the registration.
- Qualifying agent rule
- A qualifying agent may qualify only one fire protection system contracting business unless the licensing board approves an additional business, and the agent must supervise the work.
- Continuing education hours
- Certified fire alarm contractors complete 14 hours per biennial renewal cycle, including at least one hour each on Florida laws and rules, workers' compensation, workplace safety, and business practices.
- License number requirement
- Under s. 489.119, the contractor's certificate or registration number must appear on advertising, bids, contracts, and vehicles; omitting it is a citable violation.
- Financial responsibility amount
- Certificate holders must maintain a $10,000 surety bond or irrevocable letter of credit, or demonstrate at least $10,000 net worth, and file proof with DBPR.
- Notice to Owner deadline
- On private projects, a contractor must serve a Notice to Owner within 45 days of first furnishing labor or materials to preserve the right to file a construction lien.
- Notice of Commencement threshold
- On projects over $2,500, the owner records a Notice of Commencement before the first inspection; the contractor must receive a certified copy before starting work.
- Private retainage limit
- Under s. 713.346, retainage on private construction contracts is limited to 10 percent of each progress payment until final completion.
- Final Payment Affidavit
- Before filing a lien foreclosure action, a contractor must provide a Contractor's Final Payment Affidavit stating the amount owed and that the owner was given notice.
- Recovery Fund cap
- The Florida Homeowners' Construction Recovery Fund may pay up to $50,000 per claimant for financial losses caused by a licensed contractor's misconduct, subject to aggregate caps.
- Written contract threshold
- Fire alarm contracts over $500 must be in writing and include the license number, scope of work, price, and payment schedule under Florida contracting rules.
- Section 440.10 liability
- A general contractor is liable for workers' compensation benefits to employees of an uninsured subcontractor, so coverage must be verified before any sub starts work.
- Officer exemption rule
- A corporate officer owning at least 10 percent may elect exemption from workers' compensation by filing the election with the Division of Workers' Compensation.
- First injury report
- The employer must report a workplace injury to the workers' compensation carrier within 7 days of knowledge; the carrier then reports to the state within 14 days.
- Temporary total disability rate
- Florida pays temporary total disability indemnity at 66 2/3 percent of the average weekly wage, subject to the statewide maximum and minimum rates for the injury date.
- Coverage lapse consequence
- A lapse in workers' compensation coverage must be reported to the licensing board and can result in suspension of the contractor's license until coverage is reinstated.
- Fall protection trigger
- OSHA requires fall protection in construction at heights of 6 feet or more, using guardrails, safety nets, or personal fall arrest systems.
- Extension ladder setback
- Extension ladders use a 4-to-1 base setback ratio, must extend 3 feet above the landing, and the top three rungs may not be used for standing.
- Lockout/tagout requirement
- 29 CFR 1910.147 requires a written energy control procedure, trained employees, and verified de-energization before working on alarm panels or circuits.
- Arc flash clothing
- NFPA 70E requires arc-rated clothing and PPE for energized work performed within the arc flash boundary, based on an incident energy analysis.
- Hazard communication program
- 29 CFR 1910.1200 requires a written hazard communication program, accessible Safety Data Sheets, and labels on secondary containers of chemicals such as battery electrolyte.
- Confined space entry
- Entry into vaults and risers requires atmospheric testing, an attendant outside the space, and a permit under 29 CFR 1926 Subpart AA.
- False alarm definition
- A false alarm is any alarm activation not caused by a fire or emergency condition, including activations from construction dust, cooking smoke, or system malfunction.
- False alarm fee authority
- Section 633.4265 allows local governments to adopt false alarm fees, often escalating after the second or third false alarm within a 12-month period.
- Detector distance from diffusers
- Smoke detectors should be at least 3 feet from HVAC supply diffusers and at least 20 feet from cooking appliances to reduce nuisance activations.
- Alarm verification period
- NFPA 72 alarm verification requires a 60-second confirmation period before a smoke detector signal is transmitted, reducing nuisance alarm transmissions.
- Construction phase detector protection
- During construction, detectors are covered or disabled and the system placed on test; the AHJ must be notified before any part of the system is disabled.
- FBC update cycle
- The Florida Building Code is updated every three years; the 8th Edition took effect December 31, 2023, and local amendments require state approval.
- NFPA 72 adoption
- NFPA 72 is adopted by reference in the Florida Building Code; the edition cited by the current code governs fire alarm design, installation, testing, and maintenance.
- Battery calculation requirement
- Battery calculations must show 24 hours of standby plus 5 minutes of alarm (15 minutes for voice systems) at the end of the battery's useful life.
- Record of Completion
- NFPA 72 requires a Record of Completion and a Record of Inspection and Testing after acceptance testing of every initiating device and notification appliance.
- High-rise fire alarm threshold
- Florida Building Code requires voice evacuation and a fire command center in high-rise buildings over 75 feet, with specific pathway survivability requirements.