Owner-Caused Delay, Missed Notice, and a Liquidated Damages Assessment

FL General Contractor · Put your knowledge to work in context.

All case studies

Owner-Caused Delay, Missed Notice, and a Liquidated Damages Assessment

You are the general contractor on an $18.4 million, five-story mixed-use project in Orlando under AIA A101/A201, with a 410-day contract time and liquidated damages of $2,500 per day. Two owner-caused events hit the schedule: the owner-furnished elevator controller arrived 47 days after its required delivery date, and the owner took 12 days longer than the contract allowed to execute the right-of-way permit the county required before you could widen the driveway. Separately, your concrete crew ran 10 days light on manpower in month five, but that gap was absorbed before the elevator work ever started. You finished 58 days after the contract date. The owner is assessing $145,000 in liquidated damages and points to the claims clause: written notice within 21 days of the occurrence. Your superintendent raised both issues in weekly OAC meetings, and the owner's project manager signed minutes that record them. Otherwise nothing was submitted in writing until the final pay application. The contract contains a no-damage-for-delay clause and a mutual waiver of consequential damages.

1. Is the contractor's claim dead for lack of written notice, and how do you frame the argument?

Read the worked answer

Not dead - but weak enough that it has to be built carefully. The clause makes written notice within 21 days a condition of the claim, and courts generally enforce those clauses when the owner can show prejudice. The best available argument is that the signed OAC minutes are a writing delivered to and acknowledged by the owner's authorized project manager, identifying the event, the cause, and the schedule impact - that is notice in substance if the contract does not dictate a specific form.

Build the record before you argue: pull every set of minutes, the superintendent's daily reports, the correspondence log, and the schedule updates issued around each event. Show that the owner had actual contemporaneous knowledge, was not surprised at closeout, and made decisions (such as refusing the time extension) with that knowledge. Distinguish any case law where the owner was blindsided - that is not this owner.

Separately, check what the liquidated damages clause requires before assessment: many contracts require the architect or owner to certify the actual date of substantial completion and to give notice of intent to assess. If the owner simply deducted the money from a pay application without following that mechanism, that is an independent procedural challenge.

File a formal claim now with a full reservation of rights, and do not let the argument rest only on 'the minutes count.'

2. How do you prove the 58 days are excusable? Walk through the causation analysis.

Read the worked answer

Prove it with a time impact analysis, not with a total-days comparison. For each event, take the CPM schedule update current at the time the event occurred, insert a fragnet reflecting the actual duration and logic of the delay, and measure the resulting movement of the project completion date.

Elevator controller: 47 days of late delivery only becomes 47 days of project delay if elevator installation and the associated inspections/turnover were on the critical path at that moment. Check the float on that path in the contemporaneous update - if the controller had 20 days of total float, only the excess delays completion. The likely reality on a five-story project is that the elevator and its inspection sit near the end of the critical path, so most or all of the 47 days translates.

Right-of-way permit: the 12 days is owner-caused only if the contract assigned that permit to the owner. Read the permit matrix and the general conditions, not just the spec section. If the contractor owned that permit, the 12 days is yours.

Concrete manpower: it occurred earlier, was absorbed, and does not overlap either owner event. It is not a concurrent delay in the legal sense, so it does not reduce the time extension - though it is exactly the kind of fact an owner will use to argue the contractor was already behind.

Bottom line to present: 59 days of owner-caused critical delay against 58 days of actual late completion supports full time extension and reversal of the $145,000.

3. What does the no-damage-for-delay clause actually bar, and could you pursue acceleration costs instead?

Read the worked answer

Separate time from money. A no-damage-for-delay clause bars recovery of delay damages - extended home office overhead, lost productivity, extended field costs - but it does not ordinarily bar a time extension or relief from liquidated damages. So the first objective is the 59-day extension to defeat the $145,000, regardless of the money claim.

Read the clause's scope before conceding anything: many are limited to delays 'within the owner's control' or exclude delays not contemplated by the parties, gross negligence, or active interference. If the owner's failure to deliver its own furnished equipment was an active breach rather than an administrative delay, there is an argument the clause does not reach it. The mutual waiver of consequential damages may overlap the same dollars, so map which clause governs which cost category before filing a number.

Constructive acceleration is the second track. The elements are: an excusable, compensable delay; a timely request for a time extension; the owner's refusal; an owner direction (or effective insistence) to finish on the original date; and actual acceleration cost. Your weak element is the timely written request - the same notice problem. If the owner's PM ever said 'hold the date' or 'recover the lost days' in a meeting, find it in the minutes. Then document overtime, second shifts, and added crews with daily coded cost records tied to the directive. Acceleration costs are not delay damages, so the no-damage clause is a weaker defense to that portion.