FL General Contractor study materials
FL General Contractor study resources

FL General Contractor key terms

FL General Contractor · Get comfortable with the vocabulary.

Retainage

A percentage of each progress payment withheld by the owner until substantial or final completion, protecting the owner against liens and incomplete work while reducing the contractor's cash flow.

Related: Substantial Completion, Schedule of Values
Schedule of Values

An itemized breakdown of the contract sum allocated to work components, used to evaluate progress payment requests and to track costs against the contract amount.

Related: Retainage, Change Order
Change Order

A written, signed modification to the contract documents adjusting scope, price, or time, executed by the owner and contractor after agreement on the adjustment.

Related: Constructive Change, Schedule of Values
Constructive Change

A change resulting from owner direction, defective plans, or differing site conditions without a formal change order; the contractor may pursue equitable adjustment through written notice and documentation.

Related: Change Order, Differing Site Conditions
Differing Site Conditions

Subsurface or physical conditions materially different from those shown in the contract documents or unusual for the work, entitling the contractor to notice and possible adjustment.

Related: Constructive Change, Geotechnical Report
Substantial Completion

The stage when the work is sufficiently complete for its intended use, triggering warranty start, release of retainage, and the punch list process.

Related: Retainage, Punch List
Punch List

A written list of incomplete or deficient items identified at substantial completion that the contractor must correct before final acceptance and final payment.

Related: Substantial Completion, Final Payment
Final Payment

The last payment under the contract, made after all punch list work, closeout documents, and lien releases are accepted by the owner.

Related: Punch List, Lien Waiver
Lien Waiver

A document in which a party relinquishes lien rights, typically conditioned on receipt of payment; unconditional waivers take effect immediately upon signing.

Related: Notice to Owner, Final Payment
Notice to Owner

A Florida statutory notice given by a subcontractor or supplier to the owner within 45 days of first furnishing labor or materials, preserving lien rights on the property.

Related: Lien Waiver, Construction Lien
Construction Lien

A statutory claim against real property recorded by an unpaid party who furnished labor or materials, subject to strict Florida notice, recording, and foreclosure deadlines.

Related: Notice to Owner, Lien Waiver
Bid Bond

A surety instrument guaranteeing that a bidder will enter the contract and furnish required bonds if awarded; failure may expose the bidder to the difference in price.

Related: Performance Bond, Payment Bond
Performance Bond

A surety bond securing the contractor's completion of the contract according to its terms, giving the owner a remedy if the contractor defaults.

Related: Bid Bond, Payment Bond
Payment Bond

A surety bond protecting subcontractors and suppliers by ensuring they are paid for labor and materials furnished on bonded construction work.

Related: Performance Bond, Construction Lien
Critical Path Method

A scheduling technique identifying the longest sequence of dependent activities; delay to any critical activity delays project completion unless the network is adjusted.

Related: Float, Baseline Schedule
Float

The amount of time an activity can slip without delaying the project completion date; total float differs from free float, which affects only the next activity.

Related: Critical Path Method, Baseline Schedule
Baseline Schedule

The approved initial project schedule against which actual progress and delay claims are measured, updated only through formal revision.

Related: Critical Path Method, Float
Geotechnical Report

A soils investigation report describing subsurface strata, groundwater, bearing capacity, and recommendations that inform foundation design and excavation methods.

Related: Differing Site Conditions, Bearing Capacity
Bearing Capacity

The maximum pressure soil or rock can support without shear failure or excessive settlement, used to size footings and determine allowable foundation loads.

Related: Geotechnical Report, Spread Footing
Spread Footing

A shallow foundation that distributes column or wall loads over a widened base area so soil pressure stays within the allowable bearing capacity.

Related: Bearing Capacity, Pile Foundation
Pile Foundation

A deep foundation using driven or drilled elements to transfer loads through weak upper soils to competent strata or by friction along the pile shaft.

Related: Spread Footing, Bearing Capacity
Dewatering

Controlled removal of groundwater from an excavation using pumps, wells, or wellpoints to keep the work dry and stable during construction.

Related: Shoring, Hydrostatic Pressure
Shoring

Temporary support systems such as bracing, sheeting, or underpinning that prevent soil collapse and protect adjacent structures during excavation.

Related: Dewatering, Excavation Safety
Excavation Safety

Practices including sloping, benching, or shoring of trenches, spoil pile setbacks, and competent person inspections required to protect workers from cave-ins.

Related: Shoring, Competent Person
Competent Person

An individual capable of identifying existing and predictable hazards and authorized to take prompt corrective action, required for excavation, scaffolding, and fall protection inspections.

Related: Excavation Safety, Fall Protection
Fall Protection

Systems and procedures, such as guardrails, personal fall arrest, and controlled access zones, required where workers are exposed to falls of six feet or more.

Related: Competent Person, Excavation Safety
Concrete Slump Test

A field consistency test measuring the vertical settlement of a standard concrete cone, used to judge workability against the specified slump range.

Related: Water-Cement Ratio, Curing
Water-Cement Ratio

The mass of water divided by the mass of cementitious material in a mix; lower ratios increase strength and durability but reduce workability.

Related: Concrete Slump Test, Curing
Curing

Maintaining adequate moisture and temperature after concrete placement so cement hydration continues and the concrete develops specified strength and durability.

Related: Water-Cement Ratio, Concrete Slump Test
Reinforcement Cover

The concrete depth between the outer surface and the nearest reinforcing steel, protecting bars from corrosion and fire and ensuring bond.

Related: Curing, Hydrostatic Pressure
Mortar Joint

The layer of mortar between masonry units whose thickness and tooling affect bond, compressive strength, and water penetration resistance.

Related: Flashing, Weep Hole
Weep Hole

A small opening in masonry or cladding that drains accumulated moisture from behind the wall assembly to the exterior.

Related: Flashing, Mortar Joint
Flashing

Sheet metal or membrane installed at roof, wall, and opening intersections to direct water away from joints and prevent moisture intrusion into the building envelope.

Related: Weep Hole, Air Barrier
Air Barrier

A continuous system of materials that limits uncontrolled air leakage through the building envelope, improving energy performance and moisture control.

Related: Flashing, Vapor Retarder
Vapor Retarder

A low-permeability material placed to limit moisture vapor diffusion through an assembly, positioned according to climate to avoid trapping moisture.

Related: Air Barrier, Hydrostatic Pressure
Hydrostatic Pressure

The pressure exerted by standing or flowing water against a surface, which below-grade waterproofing and drainage systems must resist and relieve.

Related: Dewatering, Vapor Retarder
Wind Uplift

The upward force wind exerts on roof coverings and cladding, requiring attachment and edge detailing designed for the site's wind speed.

Related: Flashing, Load Path
Load Path

The continuous route by which gravity, wind, and seismic forces travel from the point of application through structural members to the foundation.

Related: Shear Wall, Wind Uplift
Shear Wall

A wall designed to resist lateral forces in its own plane, transferring wind and seismic loads down to the foundation through diaphragm and collector action.

Related: Load Path, Wind Uplift
Coordination Drawing

A combined drawing overlaying structural, mechanical, electrical, and plumbing systems to identify clashes and establish routing and penetration locations before installation.

Related: Clash Detection, Sleeve
Clash Detection

The process of comparing building models or drawings to find physical conflicts between systems, such as ductwork intersecting structural beams, before construction.

Related: Coordination Drawing, Sleeve
Sleeve

A pipe or formed opening cast or drilled through concrete or masonry to allow a service line to pass while preserving structure and allowing sealing.

Related: Coordination Drawing, Firestop
Firestop

An approved material or assembly that seals penetrations and joints in rated walls and floors to maintain the fire-resistance rating of the barrier.

Related: Sleeve, Fire-Resistance Rating
Fire-Resistance Rating

The period, in hours, that a building element resists fire exposure under standardized testing, governing structural protection and separation requirements.

Related: Firestop, Life Safety Plan
Life Safety Plan

A drawing showing egress paths, exit widths, travel distances, and rated separations used to demonstrate code compliance and coordinate construction.

Related: Fire-Resistance Rating, Certificate of Occupancy
Certificate of Occupancy

An official document issued after inspection confirms a building complies with applicable codes and approved plans, permitting legal occupancy.

Related: Life Safety Plan, Notice of Commencement
Notice of Commencement

A Florida document recorded and posted before starting improvements, identifying the owner, contractor, surety, and lender for lien law purposes.

Related: Notice to Owner, Construction Lien
Building Permit

Written authorization from the local building department to construct or alter work in accordance with approved plans and applicable Florida codes.

Related: Certificate of Occupancy, Notice of Commencement
Threshold Building

A Florida building over three stories or 50 feet in height, or of assembly occupancy with occupant load over 500, requiring special inspector oversight.

Related: Special Inspector, Building Permit
Special Inspector

A Florida-licensed architect or engineer, or qualified firm, retained to perform threshold building inspections and report findings to the building official.

Related: Threshold Building, Building Permit
Quality Assurance Plan

A documented program defining inspection, testing, and acceptance procedures used to verify that materials and workmanship meet the contract documents.

Related: Special Inspector, Submittal
Submittal

Product data, shop drawings, or samples submitted by the contractor for the designer's review to confirm compliance before fabrication or installation.

Related: Quality Assurance Plan, Coordination Drawing