FL General Contractor study materials
FL General Contractor study resources

FL General Contractor: Contract Administration and Project Management

FL General Contractor · Work through your exam, one topic at a time.

All guide sections

Contract Administration and Project Management

Contract Administration and Project Management covers the documents and deadlines that decide who gets paid and who bears risk: contract formation, changes, submittals, schedule, closeout, and above all the Florida Construction Lien Law (Chapter 713) and the construction-defect notice statute (Chapter 558). This is the highest-yield deadline domain on the exam.

The private-work lien timeline

  • Notice of Commencement: recorded by the owner before work begins (required when the improvement exceeds $2,500) and posted on the job site; a failure to record can be cured within 90 days of permit issuance.
  • Notice to Owner: subs and material suppliers not in privity with the owner must serve an NTO within 45 days of first furnishing labor, services, or materials.
  • Claim of Lien: recorded within 90 days after final furnishing; a copy must be served on the owner within 15 days after recording.
  • Suit to foreclose: within one year of recording the claim of lien, shortened to 60 days if the owner records a Notice of Contest of Lien.
  • Final payment affidavit: the contractor must furnish it before suing on a lien; a Notice of Termination recorded by the owner cuts off later lien rights.

Chapter 558 pre-suit process

A claimant must serve a written notice of claim at least 60 days before filing suit on an alleged construction defect. The recipient may inspect and offer to repair or settle; the statutory response periods are short and the notice is a condition precedent.

Administration mechanics

  • RFIs clarify intent; an architect's supplemental instruction directs work; a change order adjusts price and time. Never let field direction substitute for written change authorization.
  • Differing site conditions, delay, and acceleration claims require contemporaneous notice and records.
  • Closeout is substantial completion, punchlist, final payment, warranty, and as-builts.

Worked example

A drywall subcontractor first furnishes on March 3 and last furnishes on August 20. NTO deadline: March 3 plus 45 days = April 17. Claim of lien deadline: August 20 plus 90 days = November 18. Suit deadline if no Notice of Contest: November 18 of the following year. If the owner records a Notice of Contest on December 1, the suit window collapses to 60 days, expiring January 30.

Traps that cost marks

  • Running the NTO clock from the permit date or the contract date instead of first furnishing.
  • Serving an NTO on a party already in privity with the owner.
  • Forgetting the 15-day service of the recorded claim of lien.
  • Assuming a Notice of Contest ends lien rights outright rather than starting a 60-day suit clock.
  • Suing without the 558 notice or without the final payment affidavit.