FOA CFOS/D flashcards
FOA CFOS/D · Build recall with a focused review session.
31 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Link power budget
- Difference between minimum transmitter output power and receiver sensitivity, minus design margin. Must cover fiber attenuation, splice loss, connector loss, and splitter loss for the link to work.
- Insertion loss formula
- Total loss = (fiber dB/km × length km) + (splice count × splice dB) + (connector pairs × connector dB) + splitter dB. Compare result to available budget minus margin.
- Splitter loss 1×N
- Ideal loss is 10·log10(N) dB; practical loss adds about 0.3–0.5 dB excess per stage. A 1×32 splitter is roughly 15 dB ideal and 16–17 dB real.
- OM3 vs OM4 reach
- At 10GBASE-SR, OM3 supports about 300 m and OM4 about 400 m. At 40/100GBASE-SR4, OM3 reaches about 100 m and OM4 about 150 m.
- Single-mode wavelength windows
- 1310 nm is the zero-dispersion window; 1550 nm has lowest attenuation near 0.2 dB/km and supports EDFA amplification. OS2 attenuation limits are 0.35 and 0.25 dB/km.
- APC vs UPC connectors
- APC uses an 8-degree angled polish with reflectance ≤ −60 dB, used in PON and RFoG. UPC is flat polish ≤ −50 dB. Never mate APC to UPC; loss and damage result.
- Bend-insensitive fiber
- Multimode fiber designed for a 7.5 mm minimum bend radius instead of 10× cable OD. Reduces macrobend loss in tight cabinets and high-density patch panels.
- PON power budget classes
- ITU-T PON classes: B+ 28 dB, C+ 32 dB, D 35 dB. Split ratio and reach must fit within the class budget after splitters and fiber loss.
- PON wavelengths
- Downstream 1490 nm, upstream 1310 nm, video overlay 1550 nm. Each wavelength has a separate budget and must be tested at its operating wavelength.
- MPO polarity method B
- Straight-through key-up-to-key-down MPO trunk with reversed pair order at each end. Default for parallel optics such as 40/100GBASE-SR4 using 12- or 24-fiber MPO.
- PMD and chromatic dispersion
- PMD is in ps/√km and grows with distance; chromatic dispersion is in ps/(nm·km). Both must be budgeted for 10G+ single-mode spans to avoid pulse spreading.
- OTDR dead zones
- Event dead zone is about 1 m and attenuation dead zone about 4 m for standard modules. Short pulse widths reduce dead zones for closely spaced splices.
- Tier 1 vs Tier 2 test
- Tier 1 uses an OLTS to measure insertion loss and length. Tier 2 adds an OTDR trace to locate events. Specify Tier 2 for backbone and high-count links.
- Design margin
- Reserve of at least 3 dB in the link budget for aging, repairs, temperature, and future splices. Never consume the full transceiver budget.
- Return loss definition
- Return loss in dB = −10·log10(reflected/incident). A larger positive value means less reflection; 55 dB is better than 40 dB.
- Spare fiber provisioning
- Design rule to provision at least 25–50% spare strands per cable and at least one spare tube per closure for growth, repairs, and future services.
- Critical path and float
- Float = late start − early start = late finish − early finish. The critical path has zero float and sets the minimum project duration.
- Earned value core formulas
- CV = EV − AC; SV = EV − PV; CPI = EV/AC; SPI = EV/PV. Positive CV/SV is favorable; index above 1 is favorable.
- EAC forecast formulas
- EAC = BAC/CPI when current variance persists; EAC = AC + (BAC − EV) for atypical variance; EAC = AC + bottom-up ETC when the original estimate is flawed.
- PERT three-point estimate
- Expected = (O + 4M + P)/6 and standard deviation = (P − O)/6. Used for schedule and cost uncertainty in splicing and termination labor.
- Scope baseline components
- Scope statement plus WBS plus WBS dictionary. Any change to these requires integrated change control and CCB approval before work proceeds.
- Contingency vs management reserve
- Contingency reserve covers identified risks and sits inside the cost baseline. Management reserve covers unknown-unknowns, sits above baseline, and needs sponsor approval.
- TCPI meaning
- To-complete performance index = (BAC − EV)/(BAC − AC). A value above 1 means remaining work must be more efficient than planned to hit budget.
- WBS 100% rule
- Children sum exactly to parent scope. Work packages are typically 8–80 hours and decompose into activities for scheduling and estimating.
- Crashing vs fast-tracking
- Crashing adds resources and cost, such as a second splice crew. Fast-tracking overlaps phases and adds risk. Apply only to critical path activities.
- Resource leveling vs smoothing
- Leveling may change start and finish dates and extend the critical path. Smoothing uses existing float without changing the critical path.
- Parametric estimating
- Uses unit rates such as dollars per km or per splice from historical data. Faster than bottom-up and more accurate than analogous estimating.
- Project charter purpose
- Formally authorizes the project and names the sponsor. Without it there is no budget authority, baseline, or project manager assignment.
- RACI accountability rule
- Each work package or activity has exactly one Accountable owner. Responsible, Consulted, and Informed roles may have multiple people.
- One-call locate lead time
- Utility locate requests (811/one-call) are typically submitted 2–3 business days before excavation. Missed locates are a common schedule risk in buried OSP work.
- Long-lead procurement
- Fiber cable 6–12 weeks, OLT/ONT 4–12 weeks, permits and pole attachments 60–120 days. Order these before design freeze to protect the schedule.