FOA CFOS/D key terms
FOA CFOS/D · Get comfortable with the vocabulary.
- Feasibility Study
- Related: Business Case, Scope Definition, Bill of Materials
An early assessment that checks whether a proposed fiber network can be built and operated within budget, schedule, and demand assumptions before major money is committed.
- Scope Definition
- Related: Work Breakdown Structure, Feasibility Study
A written statement fixing what the fiber project will and will not deliver, including routes, premises passed, services enabled, and explicit exclusions, so planners and contractors share one baseline.
- Work Breakdown Structure (WBS)
- Related: Scope Definition, Critical Path, Earned Value Management
A hierarchical decomposition of the project into deliverable packages, such as permitting, trenching, splicing, and testing, used to assign owners, estimate effort, and track progress.
- Critical Path
- Related: Work Breakdown Structure, Float, Milestone
The longest chain of dependent activities through the project schedule; any delay on this path pushes out the completion date unless the plan is compressed or resequenced.
- Float (Slack)
- Related: Critical Path, Milestone
The amount of time an activity can slip without delaying the project finish or a successor; activities with zero float sit on the critical path and need close tracking.
- Milestone
- Related: Critical Path, Punch List
A zero-duration checkpoint marking a significant achievement, such as design freeze, permit issuance, or final acceptance, used to report status to sponsors and stakeholders.
- Earned Value Management (EVM)
- Related: Work Breakdown Structure, Change Order, Contingency
A cost and schedule control method comparing planned value, earned value, and actual cost to forecast overruns and schedule slippage on long fiber builds.
- Contingency
- Related: Earned Value Management, Change Order, Risk Register
A budget reserve held for known risks that are likely but not certain, such as rock excavation or extra permitting, released only through an approved change process.
- Risk Register
- Related: Contingency, Permit
A living log of identified project risks with likelihood, impact, owner, and mitigation action, reviewed at each status meeting so threats to schedule and budget stay visible.
- Change Order
- Related: Contingency, Punch List
A formal, approved modification to scope, cost, or schedule after the baseline is set; without it, extra work has no contractual standing and often goes unpaid.
- Punch List
- Related: Milestone, Change Order, As-Built Documentation
A closing checklist of incomplete or defective items found at walkthrough, tracked until corrected and accepted before the project is formally closed out.
- As-Built Documentation
- Related: Punch List, Splice Closure
Final drawings and records reflecting what was actually installed, including route changes, splice locations, and depths, handed to the owner for future maintenance and records.
- Bill of Materials (BOM)
- Related: Feasibility Study, Fiber Count
An itemized list of every component needed for the build, with quantities and part numbers, used to price the project, order stock, and reconcile deliveries against design.
- Permit
- Related: Right-of-Way, Risk Register, Make-Ready
Government or property-owner authorization required before construction, covering rights-of-way, road crossings, pole attachments, or building access; approvals often drive the schedule.
- Right-of-Way (ROW)
- Related: Permit, Easement, Route Survey
The legal corridor, usually public land along roads, in which a network operator is permitted to place conduit, cable, or handholes, subject to conditions set by the authority.
- Easement
- Related: Right-of-Way, Permit
A recorded legal right to cross or use another party's private property for cable placement, negotiated before construction and retained for the life of the network.
- Make-Ready
- Related: Permit, Aerial Plant, Route Survey
Work performed on utility poles, such as replacing or realigning them, so they can safely carry a new attachment; the owning utility sets the cost and timing.
- Route Survey
- Related: Right-of-Way, Make-Ready, GIS Mapping
Field inspection of a proposed path recording distances, obstacles, underground utilities, pole conditions, and access points, forming the factual basis for design and cost estimates.
- GIS Mapping
- Related: Route Survey, As-Built Documentation
Geographic information system records tying network assets to map coordinates, used for route planning, permitting exhibits, asset management, and outage response.
- Link Budget
- Related: Power Budget, Optical Margin, Attenuation
A calculation summing transmitter power, fiber loss, connector and splice loss, and margin to confirm a span will deliver adequate received power over its full length and lifetime.
- Optical Margin
- Related: Link Budget, Power Budget
The spare loss allowance built into a design to cover aging, repairs, additional splices, and measurement uncertainty so the link still works years after installation.
- Attenuation
- Related: Link Budget, Wavelength Window
The loss of optical power as light travels through fiber, expressed in decibels per kilometer and varying with wavelength and fiber type.
- Wavelength Window
- Related: Attenuation, Wavelength Division Multiplexing
A band of wavelengths where fiber loss is low and equipment operates, such as 1310 nm, 1490 nm, or 1550 nm, chosen to match reach and transmission needs.
- Wavelength Division Multiplexing (WDM)
- Related: Wavelength Window, Fiber Count
Combining multiple signals at different wavelengths onto one fiber strand, multiplying capacity without adding cable and requiring filters or multiplexers at each end.
- Fiber Count
- Related: Bill of Materials, Wavelength Division Multiplexing, Buffer Tube
The number of individual strands inside a cable, sized to serve current demand plus growth, sparing policy, and restoration needs rather than only today's subscribers.
- Buffer Tube
- Related: Fiber Count, Splice Closure
A protective plastic tube surrounding one or more fibers inside a cable, keeping strands organized, isolated from moisture, and identifiable for splicing.
- Splice Closure
- Related: Fusion Splicing, As-Built Documentation, Handhole
A sealed enclosure protecting fused or mechanical splices and slack coil from water, dirt, and physical damage, placed at handholes, aerial spans, or building entries.
- Fusion Splicing
- Related: Splice Closure, Optical Time Domain Reflectometer
Joining two fibers by melting their ends with an electric arc, producing a low-loss permanent connection; splice loss and location must be recorded for the as-built record.
- Optical Time Domain Reflectometer (OTDR)
- Related: Fusion Splicing, Link Budget
A test instrument that launches light pulses and graphs backscatter and reflections, revealing loss, splice quality, connector condition, and fault distance along a fiber.
- Optical Distribution Frame (ODF)
- Related: Fiber Distribution Hub, Patch Panel
A rack-mounted patch panel that terminates incoming fiber cables and cross-connects them to active equipment, keeping central office or headend cabling orderly and testable.
- Fiber Distribution Hub (FDH)
- Related: Optical Distribution Frame, Feeder Cable
A field cabinet or enclosure where feeder cables terminate and distribution cables branch toward subscribers, providing a point for cross-connection, testing, and service activation.
- Feeder Cable
- Related: Fiber Distribution Hub, Distribution Cable
The high-count cable running from the central office or headend to distribution hubs, carrying aggregated traffic and sized for long-term growth across many serving areas.
- Distribution Cable
- Related: Feeder Cable, Fiber Distribution Hub, Handhole
The lower-count cable from a distribution hub to access points near subscribers, balancing fiber count against the cost of splices and later activation work.
- Handhole
- Related: Splice Closure, Distribution Cable
A small underground access chamber, smaller than a manhole, letting crews pull cable, store slack, and reach splices without entering confined space.
- Aerial Plant
- Related: Make-Ready, Underground Plant
Fiber installed on utility poles and strand rather than underground, usually faster and cheaper to deploy but dependent on pole attachment rights and make-ready work.
- Underground Plant
- Related: Aerial Plant, Permit, Handhole
Fiber placed in buried conduit, ducts, or direct-buried trenches, offering better protection from weather and damage at the cost of excavation, permitting, and higher upfront expense.
- Power Budget
- Related: Link Budget, Optical Margin
The total allowable loss between transmitter and receiver, derived from launch power minus receiver sensitivity, against which calculated span loss and margin are compared.
- Redundancy
- Related: Route Diversity, Restoration
Deliberate duplication of routes, equipment, or fiber paths so a single failure does not interrupt service, planned through ring topologies or alternate paths and paid for in cost.
- Route Diversity
- Related: Redundancy, GIS Mapping
Physically separating primary and backup paths so one dig-up, fire, or flood cannot cut both, verified on maps rather than assumed from logical diagrams.
- Restoration
- Related: Redundancy, As-Built Documentation
The process and time target for returning service after a fiber cut, supported by spare fibers, documented splice records, and pre-planned alternate routes.